PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : AP-032/2016
1. Location of the project/Scheme : Andhra Pradesh
 (i) State / Union Territory : Andhra Pradesh  (ii) District : Guntur  (iii) Forest Division : Markapur (WLM)  (iv) Area of forest land proposed for diversion (in ha.) : 21.343  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Markapur (WLM)21.343Reserved Forest
Total 21.343
Division 1. : Markapur (WLM)
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Guntur21.343
Total21.343
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
121.3430.3Eco 3
Total. 21.343


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Albezzia AmaraNarlinga01020000
2Acacia CatechuSandra06780000
3Azadirachta IndicaVepa0540000
4Acacia NiloticaTumma0420000
5Others011710000
6Terminalia bellericaTane001100
7Holoptolia IntegrifoliaRavi001000
Total 0 20472 10 0
Sub Total (No of Trees.) 2050


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : Erosion would be minimum as the surface is hard rocky surface.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.1
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : It is a part of Nagarjuna Sagar Srisailam Tiger Reserve (Rajiv Gandhi Wild Life Sanctuary) in Markapur (WL)Division.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : It is a part of Nagarjuna Sagar Srisailam Tiger Reserve (Rajiv Gandhi Wild Life Sanctuary) in Markapur (WL) Division of Project Tiger Circle, Srisailam. The said area falls in the buffer zone of Nagarjuna Sagar Srisailam Tiger Reserve.
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 213.999
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1142.27Kakirala Extn-3&4MacherlaCompt.No. 54 & 57    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 PART-II Recommendation Letter
2 Site Inspection Letter
3 Species Wise Girth Details
4 Mitigation Plan
5 CA Land Authenticated Dgps Map
6 CA Land Topo Map
7 NPV Leter
8 CA Scheme Letter
9 CA Land Identified Details

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Guntur6588142543482020.96193.57931/12/201619482.506
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Markapur (WLM)FDPT -  SrisailamDFOYesOne10/12/2016
 FDPT -  SrisailamCFYesOne05/02/2017
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Markapur (WLM)FDPT -  SrisailamDFO RecommendedRecommended
quetiapin ritalin markenavntablet.site quetiapin wirkstoff
quetiapin ritalin markenavntablet.site quetiapin wirkstoff
FDPT -  SrisailamCF RecommendedRecommendedYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Andhra PradeshState SecretaryRecommended06/03/2017Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
VijayawadaRegional Office4-APC032/2017-CHN06/07/2017
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/AP/ROAD/19911/2016ROAD199112016172157,187,790.00157,187,790.0012/11/2021CNRB131571647190Union Bank Of IndiaNEFT/RTGS (Challan)17/09/202120/09/2021
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 42.27   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 3
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)12.64
  Status of CA Land so identified : Forest Area   Site Name : NIL   Location Details : NIL   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
NA
  No. of patches : 2
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
2Block(Polygon)7.67
  Status of CA Land so identified : Forest Area   Site Name : NIL   Location Details : NIL   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
NA
  No. of patches : 3
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
3Block(Polygon)21.96
  Status of CA Land so identified : Forest Area   Site Name : NIL   Location Details : NIL   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
NA
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/AP/ROAD/19911/201617 Mar 2022No DataDetails uploaded found to be correct
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/AP/ROAD/19911/201628 Mar 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/AP/ROAD/19911/2016Compliance report submitted 31 Mar 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/AP/ROAD/19911/201628 Apr 2022APPROVED