PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : AP-07/2016
1. Location of the project/Scheme : Andhra Pradesh
 (i) State / Union Territory : Andhra Pradesh  (ii) District : Nellore  (iii) Forest Division : Nellore  (iv) Area of forest land proposed for diversion (in ha.) : 0.9916  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Nellore0.9916Reserved Forest
Total 0.9916
Division 1. : Nellore
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Nellore0.9916
Total0.9916
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.99160Eco 6
Total. 0.9916


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : this is plain area, not vulnerable for erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): Yes
  Details of Protected Area and comments on the impact of Project on the ESZ : As per S.O 2559 dt.22-08-2013 by EFS Notification EIA not required for this project
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
NO Data
(ii). Copy of CA scheme details: NA (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.: (V). Copy of NOC from Competent Authority:
Additional information Details
S. No. DocumentsRemarks
1 RoFR Certificate,
2 FIELD inspection Report

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Nellore1307600279138.514752.06281036.9924/03/20161036.997260.25
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
NelloreGunturDFOYesOne19/03/2016
 GunturCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
NelloreGunturDFO RecommendedIt is Govt Project
GunturCF RecommendedYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Andhra PradeshState SecretaryRecommended19/09/2016approval orders issuedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
VijayawadaState Government2382/Section-II/201620/08/2016
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/AP/ROAD/17576/2016ROAD175762016237434,321.00S47679017Union Bank Of IndiaNEFT/RTGS (Challan)2016-09-282016-10-19
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/AP/ROAD/17576/201613 Jul 2017No DataDiversion area is below 1 Ha
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/AP/ROAD/17576/201619 Dec 2020
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/AP/ROAD/17576/2016IN-PRINCIPLENo Data