PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
AP-021/2017
1.
Location of the project/Scheme :
Andhra Pradesh
(i)
State / Union Territory :
Andhra Pradesh
(ii)
District :
Chittoor
(iii)
Forest Division :
WL Chittoor East
 (iv)
Area of forest land proposed for diversion (in ha.) :
4.69
 (v)
Category of the Proposal:
Quarrying
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
WL Chittoor East
4.69
Section 16
Total
4.69
Division 1. : WL Chittoor East
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Chittoor
4.69
Total
4.69
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
4.69
0.1
Eco 3
Total.
4.69
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Others
Bagi
0
4
2
0
0
0
2
Others
Beera
0
7
2
0
0
0
3
Albezzia Amara
Chigara
0
2
0
0
0
0
4
Others
Nallabalasa
0
18
1
1
0
0
5
Others
Narava
0
29
0
0
0
0
6
Others
Pachari
0
8
4
1
3
0
7
Others
Peddaulinja
0
0
2
0
0
0
8
Cassia Fistula
Rela
1
16
0
0
0
0
9
Wrigtria Tingtoria
Reppala
0
9
2
0
0
0
10
Others
Sandra
103
540
42
7
0
0
11
Others
Tapasi
0
0
0
1
0
0
12
Diasporus Melanoxylon
Thuki
3
15
0
0
0
0
13
Others
Udaga
0
1
0
0
0
0
14
Others
Ulinja
0
16
0
0
0
0
15
Azadirachta Indica
Vepa
4
20
1
0
0
0
Total
111
685
56
10
3
0
Sub Total (No of Trees.)
865
5.
Working plan prescription for the forest land proposed for diversion :
The proposed diversion area is a part of Mangunta West Reserved Forest which is notified U/s 15 of A.P Forest Act, 1967. Since, the proposed area of diversion is having open forest / degraded forest it was proposed for raising plantation.
6.
Brief note on vulnerability of the forest area to erosion :
There shall be less impact on the ecology specially soil erosion in and around the proposed mining area
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.086
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NO rare / endangered / unique endemic species of flora & fauna are found in the area
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
(i).
Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no
District Name
Village
Area(in ha.)
khasra
KML file
Present Owner file
1
Anantapur
Ramagiri
5.22
Sy.No.109-1C, D
(ii).
Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iii).
Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A:
(iv).
Copy of CA scheme details:
(iv).
Copy of CA scheme details:
NA
Additional information Details
S. No.
Documents
Remarks
1
Field Inspection of DFO
2
Cost of benefit analysis
3
Aerial distance map
4
Assessment of NPV
5
Topo map of CA land
6
CA Scheme
7
Certificate of DFO
8
Enumeration list
9
Part II
10
Reclamation plan
11
RoFR
12
Safety zone map
13
safety zone scheme
14
site suitability certificate of CA
15
Topo map of mining area
16
DGPS of CA land
17
site inspection report of CA
18
Grama sabha
19
User agency under taking
20
DGPS of Mining area
21
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Chittoor
1515200
452167
834.495
19
322.041
30/06/2018
319.475
574.870
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
WL Chittoor East
WLM - Tirupathi
DFO
Yes
One
21/12/2017
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
WL Chittoor East
WLM - Tirupathi
DFO
Recommended
Recommended
WLM - Tirupathi
CF
Recommended
Basing on the recommendations of the DFO, Chittoor East, proposals are considered
Yes
Nodal Officer
Recommended
Reommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Andhra Pradesh
State Secretary
Recommended
19/09/2018
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Vijayawada
Regional Office
4-APB076/2018-CHN
12/11/2018
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/AP/QRY/26772/2017
QRY267722017784
9,830,000.00
9,830,000.00
2019-03-02
BARBR52019030200569250
Corporation Bank
NEFT/RTGS (Challan)
2019-02-12
2019-02-15
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
5.36
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
5.36
Status of CA Land so identified :
Non Forest Area
Site Name :
NIL
Location Details :
NIL
Uploaded GPS File :
Uploaded Scanned copy of Map :
Mutation Status :
Mutated
Mutation Status
Circle Name.
Name of Division.
Name of Range.
Mutation Order No.
Mutation Date
How Much Area of Mutated Land Received
Mutation Letter
Ananthapur
Ananthapur
Anantapur
181/2019/A
22 Jul 2019
5.36
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/AP/QRY/26772/2017
16 Oct 2019
No Data
Verified and Accepted
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/AP/QRY/26772/2017
16 Oct 2019
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/AP/QRY/26772/2017
Compliance
24 Jan 2020
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/AP/QRY/26772/2017
07 Feb 2020
APPROVED
Print
Checklist for State Nodal Officer
×