Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Date of Stage-I | View Report on Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | View TimeLine Details | Site Inspection Report | Other Related Documents | Whether EC required (if so, status)? |
1
|
Assam
|
FP/AS/MIN/35222/2018
|
3-ASB/125/2022/GHY
|
ONGC exploratory Drilling Location KSAI
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
2.1
|
IN-PRINCIPLE
|
09-Feb-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
2
|
Assam
|
FP/AS/ROAD/46680/2020
|
3-AS-B-163/2023-GHY
|
Up-gradation of existing Jogighopa to Swahid Bedi (near Bongaigaon) road
|
Road
|
ASSAM PWRD
|
3.086
|
IN-PRINCIPLE
|
26-May-2023
|
|
|
|
|
|
No
|
3
|
Assam
|
FP/AS/QRY/27223/2017
|
3-AS B 041/2017-SHI
|
CHITALMARI STONE QUARRY NO.2
|
Quarrying
|
BONO DAS
|
1
|
IN-PRINCIPLE
|
08-Jan-2018
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
4
|
Assam
|
FP/AS/MIN/37983/2018
|
F.NO 3 AS B 027/2021-GHY
|
To Drill 06 Nos of wells DPDM, DMDN, DPDO, DPDP, DPDQ and DPDR from new drill site.
|
Mining
|
JORHAT ASSET ONGC
|
2.629
|
IN-PRINCIPLE
|
20-Jun-2022
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
5
|
Assam
|
FP/AS/MIN/146383/2021
|
3-AS-B-099/2022/GHY
|
Forest diversion proposal to drill 06 Development wells from KHDH cluster of area 2.569 ha in Khoraghat Ext -1 PML
|
Mining
|
JORHAT ASSET ONGC
|
2.569
|
IN-PRINCIPLE
|
16-Mar-2023
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
6
|
Assam
|
FP/AS/MIN/32798/2018
|
3-AS-B-138/2022/GHY
|
Proposed Development Drilling Wells and Testing of Hydrocarbons in Dipling Block-AA/ONDSF/DIPLING/2016 in Sivasagar (Charaideo) and Dibrugarh District,Assam
|
Mining
|
RAMAYANA ISPAT PVT LTD
|
3.06
|
IN-PRINCIPLE
|
11-Apr-2023
|
|
|
|
|
|
EC File NA
|
7
|
Assam
|
FP/AS/MIN/87902/2020
|
3-AS B/124/2022/GHY
|
ONGC, Drilling of Exploratory Location SPAA
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.731
|
IN-PRINCIPLE
|
09-Feb-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
8
|
Assam
|
FP/AS/QRY/27131/2017
|
3-AS B 027/2017-SHI
|
MODERTOLI STONE MAHAL NO.2
|
Quarrying
|
OLIUR RAHMAN LASKAR
|
1
|
IN-PRINCIPLE
|
04-May-2018
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
9
|
Assam
|
FP/AS/MIN/113884/2020
|
3-ASB/122/2022/GHY
|
ONGC, Drilling of Exploratory Location TLAB
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.781
|
IN-PRINCIPLE
|
09-Feb-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
10
|
Assam
|
FP/AS/ROAD/16713/2015
|
3-AS C 011/2016-SHI
|
Four Laning work from Gohpur to Holongi (NH-52A)
|
Road
|
MORTH (NHIDCL)
|
23.547
|
IN-PRINCIPLE
|
20-May-2016
|
|
|
|
|
|
No
|
11
|
Assam
|
FP/AS/ROAD/125122/2021
|
3-AS-C-136/2022-GHY
|
WIDENING / UP-GRADATION OF NH-29 FROM 2-LANE TO 4-LANE DIVIDED NATIONAL HIGHWAY FROM DABOKA TO LAHORIJAN (KARBI ANGLONG EAST FOREST DIVISION PART) UNDER BHARATMALA PARIYOJANA (LOT-1-PACKAGE-II)
|
Road
|
NHIDCL
|
14.56
|
IN-PRINCIPLE
|
05-Jul-2023
|
|
|
|
|
|
No
|
12
|
Assam
|
FP/AS/ROAD/46695/2020
|
3-AS-C-139/2022/GHY
|
Up-gradation of Chapaguri to Amteka (Bhutan Border) Road
|
Road
|
ASSAM PWRD
|
36.92
|
IN-PRINCIPLE
|
07-Mar-2024
|
|
|
|
|
|
No
|
13
|
Assam
|
FP/AS/Others/27120/2017
|
3-AS B 033/2017-SHI
|
Kafitoli Stone Mahal No. 1 (River Bed)
|
Others
|
JAYANTA KUMAR LASKAR
|
1
|
IN-PRINCIPLE
|
25-Jan-2018
|
|
|
|
|
|
EC File NA
|
14
|
Assam
|
FP/AS/Others/20093/2016
|
3-AS-B-044/2018/SHI
|
ROU for oil flow line from well No. NRAA to Nambar GGS in Nambor area
|
Others
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.43
|
IN-PRINCIPLE
|
18-Jul-2023
|
|
|
|
|
|
No
|
15
|
Assam
|
FP/AS/TRANS/152968/2022
|
3-AS-A-157/2023/GHY
|
Construction of 400 kV DC Bongaigaon Nangalbibra Transmission Line
|
Transmission Line
|
NANGALBIBRA-BONGAIGAON TRANSMISSION LIMITED
|
61.6
|
IN-PRINCIPLE
|
28-Feb-2023
|
|
|
|
|
|
No
|
16
|
Assam
|
FP/AS/TRANS/152968/2022
|
3-AS-A-157/2023/GHY
|
Construction of 400 kV DC Bongaigaon Nangalbibra Transmission Line
|
Transmission Line
|
NANGALBIBRA-BONGAIGAON TRANSMISSION LIMITED
|
61.6
|
IN-PRINCIPLE
|
28-Feb-2023
|
|
|
|
|
|
No
|
17
|
Assam
|
FP/AS/TRANS/152968/2022
|
3-AS-A-157/2023/GHY
|
Construction of 400 kV DC Bongaigaon Nangalbibra Transmission Line
|
Transmission Line
|
NANGALBIBRA-BONGAIGAON TRANSMISSION LIMITED
|
61.6
|
IN-PRINCIPLE
|
28-Feb-2023
|
|
|
|
|
|
No
|
18
|
Assam
|
FP/AS/ROAD/48518/2020
|
3-AS-B-153/2023/GHY
|
Diversion of forest land for improvement and upgradation of Hamren to Howrahghat Section of SH-19 under Axom Mala roads in the state of Assam
|
Road
|
ASSAM PWRD
|
4.193
|
IN-PRINCIPLE
|
10-Jul-2023
|
|
|
|
|
|
No
|
19
|
Assam
|
FP/AS/MIN/140252/2021
|
3-AS-B-130/2022/GHY
|
ONGC Drilling of Exploratory well NRAH
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.7888
|
IN-PRINCIPLE
|
07-Jul-2023
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
20
|
Assam
|
FP/AS/MIN/146633/2021
|
3-AS-B-105/2022/GHY
|
Forest diversion proposal to drill 06 Development wells from KSDE cluster of area 2.282 ha in Kasomarigaon PML
|
Mining
|
JORHAT ASSET ONGC
|
2.282
|
IN-PRINCIPLE
|
16-Mar-2023
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
21
|
Assam
|
FP/AS/MIN/146335/2021
|
3-AS-B-101/2022/GHY
|
Forest diversion proposal to drill 06 Development wells from KHDO Cluster of area 2.686 ha. in Nambar PML
|
Mining
|
JORHAT ASSET ONGC
|
2.686
|
IN-PRINCIPLE
|
16-Mar-2023
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
22
|
Assam
|
FP/AS/ROAD/44439/2020
|
3-AS-C-100/2022/GHY
|
Up gradation of Bilasipura-Chapar-Tulungia-Jogighopa-Gendera-Paikan-Dudhnoi-Guwahati Road (Length 225.000 km) for Goalpara district, in the State of Assam
|
Road
|
NHIDCL BO TEZPUR
|
27.054
|
IN-PRINCIPLE
|
16-Dec-2022
|
|
|
|
|
|
No
|
23
|
Assam
|
FP/AS/IND/16231/2015
|
F.No. 3-AS B 061/2016-SHI
|
Dirok Field Development Project
|
Industry
|
OIL INDIA LIMITED
|
4.8444
|
IN-PRINCIPLE
|
17-Jan-2017
|
|
|
|
|
|
Yes
Proposal Status: EC under process
|
24
|
Assam
|
FP/AS/MIN/139446/2021
|
3-ASB/116/2022/GHY
|
ONGC Drilling of Exploratory location SUAD
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.8212483
|
IN-PRINCIPLE
|
09-Feb-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
25
|
Assam
|
FP/AS/MIN/140108/2021
|
3-ASB/121/2022/GHY
|
ONGC Drilling of Exploratory Location TLAA
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.76783
|
IN-PRINCIPLE
|
09-Feb-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
26
|
Assam
|
FP/AS/ROAD/155754/2022
|
3-AS-A-147/2022/GHY
|
WIDENING / UPGRADATION OF NH-29 FROM 2-LANE TO 4-LANE DIVIDED NATIONAL HIGHWAY FROM DABOKA TO LAHORIJAN (NAGAON SOUTH FOREST DIVISION, HOJAI PART) UNDER BHARATMALA PARIYOJANA (LOT-1-PACKAGE-II)
|
Road
|
NHIDCL
|
42.6
|
IN-PRINCIPLE
|
11-Apr-2023
|
|
|
|
|
|
No
|
27
|
Assam
|
FP/AS/QRY/27142/2017
|
3-AS B 028/2017-SHI
|
MODERTOLI STONE MAHAL NO.4
|
Quarrying
|
MD FARHAN UDDIN
|
1
|
IN-PRINCIPLE
|
09-May-2018
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
28
|
Assam
|
FP/AS/TRANS/44841/2020
|
3-AS-C-162/2023/GHY
|
PROPOSED 17.195 HECTARE AREA FOREST DIVERSION PROPOSAL FOR 132 kV SANKARDEVNAGAR – LUMDING TRANSMISSION LINE AT LUMDING & LUNGTING MUPA RESERVE FOREST FOR 220 kV GRID SUB-STATION, AEGCL, SAMAGURI
|
Transmission Line
|
ASSAM ELECTRICITY GRID CORPORATION LIMITED (AEGCL)
|
17.195
|
IN-PRINCIPLE
|
30-Jan-2024
|
|
|
|
|
|
No
|
29
|
Assam
|
FP/AS/TRANS/44841/2020
|
3-AS-C-162/2023/GHY
|
PROPOSED 17.195 HECTARE AREA FOREST DIVERSION PROPOSAL FOR 132 kV SANKARDEVNAGAR – LUMDING TRANSMISSION LINE AT LUMDING & LUNGTING MUPA RESERVE FOREST FOR 220 kV GRID SUB-STATION, AEGCL, SAMAGURI
|
Transmission Line
|
ASSAM ELECTRICITY GRID CORPORATION LIMITED (AEGCL)
|
17.195
|
IN-PRINCIPLE
|
30-Jan-2024
|
|
|
|
|
|
No
|
30
|
Assam
|
FP/AS/MIN/146691/2021
|
3-AS-B-103/2022/GHY
|
Forest diversion proposal to drill 06 Development wells from DPDU cluster of area 2.75 ha in Kasomarigaon Addl PML
|
Mining
|
JORHAT ASSET ONGC
|
2.75
|
IN-PRINCIPLE
|
16-Mar-2023
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
31
|
Assam
|
FP/AS/MIN/47775/2020
|
3ASC132/2022/GHY
|
ONGC Silchar exploratory drilling TNAA
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
6.09
|
IN-PRINCIPLE
|
09-Aug-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
32
|
Assam
|
FP/AS/Others/27107/2017
|
3-AS B 026/2017-SHI
|
Jagiroad Stone Quarry No. F(3)
|
Others
|
SRI NRISHINGHA HAZARIKA
|
1
|
IN-PRINCIPLE
|
08-Jan-2018
|
|
|
|
|
|
Yes
Proposal No.:
EC File No.:
Proposal Status: No Proposal no.
|
33
|
Assam
|
FP/AS/TRANS/30498/2017
|
3-AS-B-044/2021/GHY
|
132 KV S/C Transmission line from Salakati Grid S/S to APM (Jogighopa)
|
Transmission Line
|
ASSAM ELECTRICITY GRID CORPORATION LINITED
|
1.9413
|
IN-PRINCIPLE
|
26-May-2023
|
|
|
|
|
|
No
|
34
|
Assam
|
FP/AS/TRANS/153641/2022
|
3-AS-C-146/2022/GHY
|
Construction of 132 KV EHT single circuit transmission line on double circuit tower from AEGCL Gohpur GSS to N.F.Railway Gohpur TSS in connection with RNY MZS Railway Electrification project.
|
Transmission Line
|
NORTHEAST FRONTIER RAILWAY, CONSTRUCTION,ELECTRICAL
|
7.971
|
IN-PRINCIPLE
|
02-Nov-2023
|
|
|
|
|
|
No
|
35
|
Assam
|
FP/AS/Others/26735/2017
|
3-AS C 028/2018-SHI
|
Extension of Brahmaputra Dyke Ph-IV from Chaulkhowa Medela gaon to Madhupur Deurigaon
|
Others
|
EXECUTIVE ENGINEER DIBRUGARH WATER RESOURCE DIVISION
|
20.5
|
IN-PRINCIPLE
|
28-Aug-2018
|
|
|
|
|
|
No
|
36
|
Assam
|
FP/AS/MIN/23925/2017
|
3-AS B 081/2017-SHI
|
ONGC drilling location KHDF
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
3.48
|
IN-PRINCIPLE
|
29-Nov-2018
|
|
|
|
|
|
Yes
EC File No.: No.J-11011/147/2008-1A-11(1)
Proposal Status: EC Granted
|
37
|
Assam
|
FP/AS/MIN/20304/2016
|
3-AS B 082/2016-SHI
|
ONGC exploratory drilling location URAA
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.918
|
IN-PRINCIPLE
|
19-Feb-2018
|
|
|
|
|
|
Yes
EC File No.: j11011/111/20151AII(I)
Proposal Status: EC Granted
|
38
|
Assam
|
FP/AS/Pipeline/48074/2020
|
F.No.3- AS B 07 6 /2021-GHy
|
Laying of Proposed 18" Ø (Carbon steel) Natural Gas Pipeline along with OFC Conduit From Guwahati to Panisagar.
|
Pipeline
|
INDRADHANUSH GAS GRID LIMITED
|
4.7289
|
IN-PRINCIPLE
|
09-Mar-2022
|
|
|
|
|
|
No
|
39
|
Assam
|
FP/AS/Others/27089/2017
|
3-AS B 025/2017-SHI
|
Baghara Stone Mahal No 10 located within Tetelia Baghara RF under Morigaon Range, Morigaon of Nagaon Division
|
Others
|
RATUL CH BORDOLOI
|
1
|
IN-PRINCIPLE
|
25-Jan-2018
|
|
|
|
|
|
EC File NA
|
40
|
Assam
|
FP/AS/THE/8413/2014
|
3-AS B 007/2017-SHI
|
Construction of Water Intake Pump House at Dilli River, near to existing Intake pump house
|
Thermal
|
ASSAM POWER GENERATION CORPORATION LIMITED
|
0.069
|
IN-PRINCIPLE
|
27-Jul-2017
|
|
|
|
|
|
No
|
41
|
Assam
|
FP/AS/MIN/139315/2021
|
3-ASB/126/2022/GHY
|
ONGC Drilling of Exploratory location ELAJ
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
2.2091
|
IN-PRINCIPLE
|
12-Feb-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
42
|
Assam
|
FP/AS/ROAD/16086/2015
|
3-AS C 009/2016-SHI
|
Four Lanning work from km 0 to km 17.3 of NH37A
|
Road
|
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
|
6
|
IN-PRINCIPLE
|
18-Sep-2017
|
|
|
|
|
|
No
|
43
|
Assam
|
FP/AS/TRANS/119559/2021
|
3-AS-C-096/2022/GHY
|
Diversion of Forest Land for 11 nos. of Tower Location (123 to 136A) against “Diversion work of 132KV S/C Haflong-Jiribam transmission line of POWERGRID in the section between tower location no. 104 to location no. 164 for facilitating the construction of NH-54 (E) under Borail Wildlife Sanctuary under Cachar Dist. of Assam State
|
Transmission Line
|
POWERGRID CORPORATION OF INDIA LIMITED
|
9.23
|
IN-PRINCIPLE
|
09-Feb-2023
|
|
|
|
|
|
No
|
44
|
Assam
|
FP/AS/MIN/37981/2018
|
F.NO 3 AS B 029/2021-GHY
|
To Drill 06 Nos of wells DPDD, DPDH, DPDI, DPDJ, DPDK and DPDL from new drill site.
|
Mining
|
JORHAT ASSET ONGC
|
2.73
|
IN-PRINCIPLE
|
20-Jun-2022
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
45
|
Assam
|
FP/AS/Others/27102/2017
|
3-AS B 029/2017-SHI
|
Jagiroad Stone Quarry No. F(2)
|
Others
|
HILLS TRADE AGENCIES
|
1
|
IN-PRINCIPLE
|
10-May-2018
|
|
|
|
|
|
Yes
Proposal No.:
EC File No.:
Proposal Status: No Proposal no.
|
46
|
Assam
|
FP/AS/MIN/113896/2020
|
3-ASB/117/2022/GHY
|
ONGC, Drilling of Exploratory Location DPAB
|
Mining
|
OIL AND NATURAL GAS CORPORATION LIMITED
|
1.889
|
IN-PRINCIPLE
|
09-Feb-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
47
|
Assam
|
FP/AS/Others/154603/2022
|
3-AN-B-183/2023/GHY
|
To create Production Facility GGS/EPS in Khoraghat area.
|
Others
|
JORHAT ASSET ONGC
|
4.1
|
IN-PRINCIPLE
|
19-Dec-2024
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
48
|
Assam
|
FP/AS/ROAD/146185/2021
|
3-AS-B-135/2022/GHY
|
WIDENING / UP-GRADATION OF NH-29 FROM 2-LANE TO 4-LANE DIVIDED NATIONAL HIGHWAY FROM DABOKA TO LAHORIJAN (KARBI ANGLONG WEST FOREST DIVISION PART) UNDER BHARATMALA PARIYOJANA (LOT-1-PACKAGE-7)
|
Road
|
NHIDCL
|
0.81
|
IN-PRINCIPLE
|
13-Dec-2022
|
|
|
|
|
|
No
|
49
|
Assam
|
FP/AS/Others/27117/2017
|
3-AS B 035/2017-SHI
|
Tapatjuri Stone Mahal no 1
|
Others
|
JAYANTA KUMAR LASKAR
|
1
|
IN-PRINCIPLE
|
25-Jan-2018
|
|
|
|
|
|
EC File NA
|
50
|
Assam
|
FP/AS/RAIL/7657/2014
|
3 AS C 028/2015-SHI
|
New BG Railway line from New Maynaguri to Jogighopa
|
Railway
|
NORTH EAST FRONTIER RAILWAY
|
29.855
|
IN-PRINCIPLE
|
21-Jul-2015
|
|
|
|
|
|
No
|
|