| Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Date of Stage-I | View Report on Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | View TimeLine Details | Site Inspection Report | Other Related Documents | Whether EC required (if so, status)? |
|
1
|
Arunachal Pradesh
|
FP/AR/HYD/26729/2017
|
3-ANC 076/2018-SHI
|
NYIKGONG HYDRO ELECTRIC PROJECT
|
Hydel
|
SRIKAR ENERGY LIMITED
|
11.9
|
IN-PRINCIPLE
|
05-Dec-2019
|
|
|
|
|
|
No
|
|
2
|
Arunachal Pradesh
|
FP/AR/HYD/33232/2018
|
3-ANC 097/2017-SHI
|
DIVERSION OF FOREST LAND OF 10.43 HA (SURFACE AREA=8.55 HA & UNDER GROUND AREA=1.88 HA) FOR THE CONSTRUCTION OF (20MW) YAMMENG HEP IN UPPER SIANG DISTRICT OF ARUNACHAL PRADESH
|
Hydel
|
YAMMENG GREEN ENERGY PRIVATE LIMITED
|
10.43
|
IN-PRINCIPLE
|
05-Dec-2019
|
|
|
|
|
|
No
|
|
3
|
Arunachal Pradesh
|
FP/AR/ROAD/36494/2018
|
3-AN-C-006/2021-GHY
|
Diversion of Forest Land for Construction of Taksing - Ghora Camp Lung OP Road from 0.00 km to 7.09 km by CPWD under Upper subansiri District of Arunachal Pradesh
|
Road
|
128 RCC (BRO)
|
15.262
|
IN-PRINCIPLE
|
11-Nov-2021
|
|
|
|
|
|
No
|
|
4
|
Arunachal Pradesh
|
FP/AR/TRANS/29908/2017
|
3-AN-B-109/2019-SHI
|
132 KV Transmission Line Single Circuit Of 28.947 Kms Length From Dikshi Power House To Existing Gridline Balipara-Khuppi, Near Nichupu.
|
Transmission Line
|
DEVI ENERGIES PVT LTD
|
4.6
|
IN-PRINCIPLE
|
22-Aug-2022
|
|
|
|
|
|
No
|
|
5
|
Arunachal Pradesh
|
FP/AR/ROAD/33202/2018
|
3-AN-C-057/2020/SHI
|
Proposal for Diversion of Forest land For improvement/widening of NH-415 (Old-NH-52A) from Design Chainage 40.400KM to 59.170KM (Pappunallah to Banderdewa Section) in Papumpare District , Arunachal Pradesh.
|
Road
|
PWD HIGHWAY ARUNACHAL PRADESH
|
29.421
|
IN-PRINCIPLE
|
05-Jun-2025
|
|
|
|
|
|
No
|
|
6
|
Arunachal Pradesh
|
FP/AR/ROAD/42916/2019
|
FNO 3 AN B 045/2021/GHY
|
construction of ITBP Khukri to Long Bridge foot tracks in the state of Arunachal Pradesh
|
Road
|
NHIDCL
|
2.785
|
IN-PRINCIPLE
|
15-Mar-2022
|
|
|
|
|
|
No
|
|
7
|
Arunachal Pradesh
|
FP/AR/SubStation/46601/2020
|
3-AN-B-063/2021/GHY
|
Diversion Proposal of 5336 sq.mtrs (0.534 Ha) of Forest land for Construction of 132 kV LILO Switching Sub-Station at Tippi near Industrial Estate area.
|
Sub Station
|
DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH
|
0.534
|
IN-PRINCIPLE
|
22-Oct-2025
|
|
|
|
|
|
No
|
|
8
|
Arunachal Pradesh
|
FP/AR/ROAD/142362/2021
|
3-AN-C-128/2022-GHY
|
Construction of Foot Track Tappa - Goying km 18.6
|
Road
|
BORDER ROADS ORGANISATION 756 TASK FORCE
|
10.3
|
IN-PRINCIPLE
|
31-Jul-2023
|
|
|
|
|
|
No
|
|
9
|
Arunachal Pradesh
|
FP/AR/HYD/153202/2022
|
3 AN C 168/2023/GHY
|
Dengzi Small Hydro Project(10MW)
|
Hydel
|
BAMANG TAGO
|
6.005
|
IN-PRINCIPLE
|
13-Jan-2026
|
|
|
|
|
|
No
|
|
10
|
Arunachal Pradesh
|
FP/AR/ROAD/153722/2022
|
3 ANC/268/2024/GHY
|
Proposal for diversion of 27.19 ha of forest land for construction of Tamen to Dollungmukh Road (Phase 1) 42.03 km to 72.03 km
|
Road
|
BAMANG RAJU
|
27.19
|
IN-PRINCIPLE
|
12-Mar-2025
|
|
|
|
|
|
No
|