Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Date of Stage-I | View Report on Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | View TimeLine Details | Site Inspection Report | Other Related Documents | Whether EC required (if so, status)? |
1
|
Orissa
|
FP/OR/TRANS/25459/2017
|
5-ORC391/2019-BHU
|
132/33 KV LILO Transmission Line by OPTCL
|
Transmission Line
|
ODISHA POWER TRANSMISSION CORPORATION LIMITED
|
14.019
|
IN-PRINCIPLE
|
11-Dec-2019
|
|
|
|
|
|
No
|
2
|
Orissa
|
FP/OR/ROAD/50071/2020
|
5-ORB580/2023-BHU
|
PWD Road (PMGSY) to Siuli Via Kadaliguda in Ganjam District, Odisha
|
Road
|
OFFICE OF THE ENGINEER-IN-CHIEF RURAL WORKS: BHUBANESWAR
|
2.562
|
IN-PRINCIPLE
|
04-Jul-2023
|
|
|
|
|
|
No
|
3
|
Orissa
|
FP/OR/ROAD/150863/2022
|
5-ORC543/2022-BHU
|
Improvement of Road from Kharabhuin PWD road chhak to Khandahata P.S.road via-Sankulei, Ghantabania, Panasaputuli road for the year 2018-19
|
Road
|
EXECUTIVE ENGINEER RURAL WORKS DIVISION BOUDH
|
6.098
|
IN-PRINCIPLE
|
18-Jan-2023
|
|
|
|
|
|
No
|
4
|
Orissa
|
FP/OR/MIN/20092/2016
|
8-01/2019-FC
|
Tirigpahar Iron & Manganese Mine (Guruda Block)
|
Mining
|
TATA STEEL LIMITED SUKINDA CHROMITE MINE
|
80.826
|
IN-PRINCIPLE
|
02-Aug-2019
|
|
|
|
|
|
EC File NA
|
5
|
Orissa
|
FP/OR/IRRIG/40827/2019
|
5-ORA472/2021-BHU
|
Kanupur Canal System
|
Irrigation
|
KANPUR CANAL DIVISION
|
310.11
|
IN-PRINCIPLE
|
03-Mar-2023
|
|
|
|
|
|
No
|
6
|
Orissa
|
FP/OR/IND/42155/2019
|
5-ORB438/2020-BHU
|
Proposal for diversion of 0.91 ha. forest Land in favour of M/s Mahakali Ispat (P) Ltd. for setting up Pollution Control Tank at village Gurundupali of Bonai Tehsil of Sundargarh District.
|
Industry
|
MAHAKALI ISPAT PVT LTD
|
0.91
|
IN-PRINCIPLE
|
29-Jan-2021
|
|
|
|
|
|
No
|
7
|
Orissa
|
FP/OR/TRANS/50828/2020
|
5-ORA487/2021-BHU
|
220 kV LILO Transmission Line from Existing LoC No. 70 of 220 KvMalkangiri – Balimela Transmission Line to 220/ 33 kV Grid Sub - Station, Khairput, Govindapalli of OPTCL in Malkangiri District, Odisha
|
Transmission Line
|
ODISHA POWER TRANSMISSION CORPORATION LIMITED
|
48.782
|
IN-PRINCIPLE
|
27-Nov-2024
|
|
|
|
|
|
No
|
8
|
Orissa
|
FP/OR/ROAD/124274/2021
|
5-ORB511/2022-BHU
|
Improvement to Road and CD works from Ranaba to Badagada
|
Road
|
EXECUTIVE ENGINEER RURAL WORKS DIVISION PHULBANI
|
1.518
|
IN-PRINCIPLE
|
18-Jan-2023
|
|
|
|
|
|
No
|
9
|
Orissa
|
FP/OR/Others/46243/2020
|
5-ORA456/2021-BHU
|
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), Odisha Phase-2 Project of GAIL
|
Others
|
GAIL INDIA LIMITED
|
65.4036
|
IN-PRINCIPLE
|
30-Mar-2021
|
|
|
|
|
|
No
|
10
|
Orissa
|
FP/OR/IND/13222/2015
|
5-ORB444/2021-BHU
|
KARMA RE ROLLERS PVT. LTD. CUTTACK
|
Industry
|
KARMA RE ROLLERS PVT. LTD.
|
1.97
|
IN-PRINCIPLE
|
09-Feb-2021
|
|
|
|
|
|
No
|
11
|
Orissa
|
FP/OR/TRANS/26634/2017
|
5-ORB353/2018-BHU
|
Odisha Power Transmission Corporation Ltd
|
Transmission Line
|
E.H.T. (C) DIVISION OPTCL ANUGUL
|
3.94
|
IN-PRINCIPLE
|
18-Jul-2018
|
|
|
|
|
|
No
|
12
|
Orissa
|
FP/OR/WATER/47760/2020
|
5-ORB445/2021-BHU
|
Mega PWS Project to 200 villages of Mahakalapada & Marsaghai Block in Kendrapara District.
|
Drinking Water
|
RURAL WATER SUPPLY & SANITATION KENDRAPARA
|
1.809
|
IN-PRINCIPLE
|
16-Sep-2021
|
|
|
|
|
|
No
|
13
|
Orissa
|
FP/OR/Others/46243/2020
|
5-ORA456/2021-BHU
|
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), Odisha Phase-2 Project of GAIL
|
Others
|
GAIL INDIA LIMITED
|
65.4036
|
IN-PRINCIPLE
|
30-Mar-2021
|
|
|
|
|
|
No
|
14
|
Orissa
|
FP/OR/IND/43075/2019
|
5-ORC442/2021-BHU
|
Establishment of OIL DEPOT by Bharat Petroleum Corporation Limited (BPCL) through IDCO, Bhubaneswar at village Arda, Tahasil- Kirmira, District- Jharsuguda, Odisha.
|
Industry
|
IDCO
|
39.599
|
IN-PRINCIPLE
|
09-Feb-2021
|
|
|
|
|
|
No
|
15
|
Orissa
|
FP/OR/Others/46243/2020
|
5-ORA456/2021-BHU
|
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), Odisha Phase-2 Project of GAIL
|
Others
|
GAIL INDIA LIMITED
|
65.4036
|
IN-PRINCIPLE
|
30-Mar-2021
|
|
|
|
|
|
No
|
16
|
Orissa
|
FP/OR/IRRIG/13379/2015
|
8-65/2016-FC
|
Turi-Guntat Irrigation Project
|
Irrigation
|
KORAPUT INVESTIGATION DIVISION, JEYPORE
|
51.783
|
IN-PRINCIPLE
|
24-Jul-2017
|
|
|
|
|
|
Yes
EC File No.: 2006
Proposal Status: EC Granted
|
17
|
Orissa
|
FP/OR/Others/7344/2014
|
5-ORC629/2024-BHU
|
Proposal for Diversion of Forest Land over 11.371 Ha required for construction of Balangir By-Pass Road under Balangir R & B Division
|
Others
|
WORKS DEPARTMENT
|
11.371
|
IN-PRINCIPLE
|
14-Mar-2024
|
|
|
|
|
|
No
|
18
|
Orissa
|
FP/OR/ROAD/52724/2020
|
5-ORC527/2022-BHU
|
Widening & Strengthening of Raruan-Fagu via Ghagarbeda road from 0/000 km to 25/000km in the District of Mayurbhanj under CRF
|
Road
|
EXECUTIVE ENGINEER RAIRANGPUR RB DIVISION
|
7.043
|
IN-PRINCIPLE
|
25-Oct-2022
|
|
|
|
|
|
No
|
19
|
Orissa
|
FP/OR/ROAD/154910/2022
|
5-ORB537/2022-BHU
|
Approach Road to Gothapatna Industrial Area
|
Road
|
IDCO
|
1.82
|
IN-PRINCIPLE
|
22-Feb-2023
|
|
|
|
|
|
No
|
20
|
Orissa
|
FP/OR/IND/12823/2015
|
5-ORB228/2015-BHU
|
Surendra Mining Industries (P) Ltd, Barhamusa.
|
Industry
|
SURENDRA MINING INDUSTRIES PRIVATE LIMITED
|
0.797
|
IN-PRINCIPLE
|
08-Jul-2015
|
|
|
|
|
|
Yes
EC File No.: J-11011/728/2008-IA.II(I)
Proposal Status: EC Granted
|
21
|
Orissa
|
FP/OR/TRANS/153797/2022
|
5-ORC576/2023-BHU
|
2X160 MVA ,220/132 KV & 2X20 MVA, 220/33KV Grid Substation with associated 220 KV DC line from 400/200 KV PGCIL Grid Substation, Keonjhar to Turumunga & 132 KV LILO line from 132 KV Polaspanga-Karanjia SC line to Turumunga, Keonjhar
|
Transmission Line
|
ODISHA POWER TRANSMISSION CORPORATION LIMITED
|
8.435
|
IN-PRINCIPLE
|
14-Mar-2024
|
|
|
|
|
|
No
|
22
|
Orissa
|
FP/OR/ROAD/13102/2015
|
5-ORB326/2017-BHU
|
Approach Road & Parking Zone
|
Road
|
M/S J.S. CONSTRUCTION (P) LTD
|
0.802
|
IN-PRINCIPLE
|
19-Jan-2018
|
|
|
|
|
|
No
|
23
|
Orissa
|
FP/OR/TRANS/42103/2019
|
5-ORB431/2020-BHU
|
Construction of power transmission line of 132 KV between 132/33 KV GIS Substation , Khuntuni OPTCL and MRSS ( Main receiving sub station ) of M/s Odisha Cement Plant ( A unit of Shree Cement Ltd.) at Chandrabalishyampur, Athagarh, Cuttack.
|
Transmission Line
|
ODISHA CEMENT PLANT A UNIT OF SHREE CEMENT LTD
|
4.495
|
IN-PRINCIPLE
|
15-Oct-2020
|
|
|
|
|
|
No
|
24
|
Orissa
|
FP/OR/REHAB/26600/2017
|
5-ORC388/2019-BHU
|
Relocation of villages situated in Core and Buffer area of Similipal Tiger Reserve
|
Rehabilitation
|
TAHASILDAR THAKURMUNDA
|
39.59
|
IN-PRINCIPLE
|
08-Nov-2019
|
|
|
|
|
|
No
|
25
|
Orissa
|
FP/OR/Pipeline/148855/2021
|
5-ORB526/2022-BHU
|
Natural Gas Pipelines to Aditya Birla Plant (ABPL) & Tata Refractories Limited (TRL) under Bokaro Angul Pipeline Project of JHBDPL Phase-II Project
|
Pipeline
|
GAIL INDIA LIMITED
|
2.0234
|
IN-PRINCIPLE
|
29-Aug-2022
|
|
|
|
|
|
No
|
26
|
Orissa
|
FP/OR/ROAD/112032/2020
|
5-ORA608/2023-BHU
|
Construction of 4 Lane Carriage Way Road with service road of SH-10 Lacturers Colony to Balijore Chowk from 0/00Km to 3/581 Km in the District of Jharsuguda.
|
Road
|
EXECUTIVE ENGINEER ROAD AND BUILDING DIVSION JHARSUGDA
|
2.323
|
IN-PRINCIPLE
|
10-Nov-2023
|
|
|
|
|
|
No
|
27
|
Orissa
|
FP/OR/ROAD/28940/2017
|
FP/OR/ROAD/28940/2017
|
R.D. Road to Aradapal PMGSY Road- OR-13ADB-15/Tr-III
|
Road
|
RURAL DEVLOPMENT
|
1.912
|
IN-PRINCIPLE
|
11-Jul-2018
|
|
|
|
|
|
No
|
28
|
Orissa
|
FP/OR/ROAD/31846/2018
|
5-ORA462/2021-BHU
|
Widening and Strengthening of Tomka- Mangalpur Road (ODR) to 4 lane without paved shoulder from 0/000 Km to 45/150 Km in the District Jajpur Odisha.
|
Road
|
EXECUTIVE ENGINEER PANIKOILI R AND B DIVISIONPANIKOILI
|
133.579
|
IN-PRINCIPLE
|
15-Dec-2021
|
|
|
|
|
|
No
|
29
|
Orissa
|
FP/OR/IRRIG/40723/2019
|
5-ORC419/2020-BHU
|
Khairibhandan Barrage Project
|
Irrigation
|
EE, MAYURBHANJ INVESTIGATION DIVISION
|
26.444
|
IN-PRINCIPLE
|
22-Mar-2021
|
|
|
|
|
|
No
|
30
|
Orissa
|
FP/OR/REHAB/149174/2021
|
5-ORB506/2022-BHU
|
Relocation of Pitanau, Ratnamara & Jhunaposi situated inside Hadagarh Wildlife Sanctuary
|
Rehabilitation
|
TAHASILDAR, HATADIHI TAHASIL
|
4.31
|
IN-PRINCIPLE
|
23-Sep-2022
|
|
|
|
|
|
No
|
31
|
Orissa
|
FP/OR/IND/16495/2015
|
8-176/1997-Fc Vol.
|
BASUNDHARA COAL WASHERY (10MTY)
|
Industry
|
MCL
|
29.41
|
IN-PRINCIPLE
|
11-Mar-2019
|
|
|
|
|
|
Yes
Proposal No.: IA/OR/CMIN/20520/2013
EC File No.: J-11015/435/2013-IA-II(M)
Proposal Status: EC Granted
|
32
|
Orissa
|
FP/OR/ROAD/17128/2015
|
5-ORB317/2017-BHU
|
Rehabilitation & Upgradation of NH-149 from Pallahara to Pitri Section (Pallahara Bypass road)
|
Road
|
NH DIVISION PALLAHARA
|
4.546
|
IN-PRINCIPLE
|
13-Mar-2018
|
|
|
|
|
|
No
|
33
|
Orissa
|
FP/OR/IRRIG/27702/2017
|
8-27/2020-FC
|
PROPOSAL FOR DIVERSION OF 113.075 ha OF FOREST LAND FOR KARAPANI IRRIGATION PROJECT
|
Irrigation
|
EXECUTIVE ENGINEER IB INVESTIGATION DIVISION
|
113.075
|
IN-PRINCIPLE
|
15-Dec-2021
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
34
|
Orissa
|
FP/OR/Others/9825/2015
|
5-ORB428/2020-BHU
|
Barbil - Angul Iron Ore Slurry Pipeline Project
|
Others
|
Jindal Steel & Power Ltd.
|
1.99
|
IN-PRINCIPLE
|
24-Sep-2020
|
|
|
|
|
|
No
|
35
|
Orissa
|
FP/OR/TRANS/33755/2018
|
5-ORC449/2021-BHU
|
220 KV S/C (2 Conductor) Transmission Line from 220/33 KV GSS, Bonaito RTSS,Bimlagarh in Sundargarh district
|
Transmission Line
|
OPTCL
|
3.305
|
IN-PRINCIPLE
|
05-Mar-2021
|
|
|
|
|
|
No
|
36
|
Orissa
|
FP/OR/Others/9825/2015
|
5-ORB428/2020-BHU
|
Barbil - Angul Iron Ore Slurry Pipeline Project
|
Others
|
Jindal Steel & Power Ltd.
|
1.99
|
IN-PRINCIPLE
|
24-Sep-2020
|
|
|
|
|
|
No
|
37
|
Orissa
|
FP/OR/IRRIG/13364/2015
|
5-ORC303/2017-BHU
|
Aherajore Irrigation Project
|
Irrigation
|
EXECUTIVE ENGINEER, IB INVESTIGATION DIVISION
|
14.53
|
IN-PRINCIPLE
|
04-Aug-2017
|
|
|
|
|
|
Yes
Proposal Status: EC application yet to be submitted
|
38
|
Orissa
|
FP/OR/ROAD/8330/2014
|
7(86)2013-FCE(Pt)
|
Approch road to High level Bridge over Sileru river Near Motu
|
Road
|
EXECUTIVE ENGINEER RB
|
2.994
|
IN-PRINCIPLE
|
22-Feb-2017
|
|
|
|
|
|
No
|
39
|
Orissa
|
FP/OR/RAIL/153463/2022
|
5-ORC617/2023-BHU
|
Koraput to Singaram Doubling Railway Project. from Km- 0.000 to Km- 74.800
|
Railway
|
DYCE2CONECOR@WAT.RAILNET.GOV.IN
|
5.117
|
IN-PRINCIPLE
|
25-Jan-2024
|
|
|
|
|
|
No
|
40
|
Orissa
|
FP/OR/RAIL/154542/2022
|
5-ORC618/2023-BHU
|
Bhalumaska to Singapur Road Doubling Railway Project From Km. 128.95 to 163.725
|
Railway
|
DYCE2CONECOR@WAT.RAILNET.GOV.IN
|
33.152
|
IN-PRINCIPLE
|
25-Jan-2024
|
|
|
|
|
|
No
|
41
|
Orissa
|
FP/OR/MIN/142115/2021
|
8-49/1998-FC (PT-I)
|
Jilling Langalotta Iron Ore Mine
|
Mining
|
ODISHA MINING CORPORATION LTD
|
22.697
|
IN-PRINCIPLE
|
09-Feb-2024
|
|
|
|
|
|
EC File NA
|
42
|
Orissa
|
FP/OR/WATER/42503/2019
|
FP/OR/WATER/42503/2019
|
Mega PWS to 22 GP’s of Champua Block, 21 GP’s of Jhumpura Block,25 GP’s of Keonjhar Block & 21 GP’s of Banspal Block in Keonjhar Distroct.
|
Drinking Water
|
RURAL WATER SUPPLY AND SANITATTION KEONJHAR
|
2.428
|
IN-PRINCIPLE
|
17-Mar-2020
|
|
|
|
|
|
No
|
43
|
Orissa
|
FP/OR/ROAD/32294/2018
|
5-ORC461/2021-BHU
|
Coal Corridor Road project
|
Road
|
SATYABAN
|
26.99
|
IN-PRINCIPLE
|
03-Dec-2021
|
|
|
|
|
|
No
|
44
|
Orissa
|
FP/OR/TRANS/150350/2021
|
5-ORC546/2023-BHU
|
Construction of 132 KV D/C Transmission line from existing 132/33 KV D/C Grid Sub-Station at Brajarajnagar to proposed 132/33 KV Grid Sub-station at village Kudaloi in Lakhanpur Tahsil of Jharsuguda D
|
Transmission Line
|
OPTCL
|
13.465
|
IN-PRINCIPLE
|
03-Feb-2023
|
|
|
|
|
|
No
|
45
|
Orissa
|
FP/OR/RAIL/150861/2022
|
5-ORB601/2023-BHU
|
Y – Connection for Railway Project by M/s Vedanta Limited
|
Railway
|
VEDANTA LIMITED LANJIGARH
|
1.148
|
IN-PRINCIPLE
|
21-Dec-2023
|
|
|
|
|
|
Yes
Proposal No.: IA/OR/IND/24310/2011
EC File No.: J-11011/406/2011-IA.II(I)
Proposal Status: EC Granted
|
46
|
Orissa
|
FP/OR/SCH/29971/2017
|
7(86)2013-FCE(Pt)
|
Odisha Adarsha Vidyalaya, (Model School), Dungripali
|
School
|
DISTRICT EDUCATION OFFICER, SONEPUR
|
4.16
|
IN-PRINCIPLE
|
26-Dec-2018
|
|
|
|
|
|
No
|
47
|
Orissa
|
FP/OR/Others/26114/2017
|
5-ORB430/2020-BHU
|
Re-Diversion Proposal for Barbil - Angul Iron Ore Slurry Pipeline Project
|
Others
|
Jindal Steel & Power Ltd.
|
2.405
|
IN-PRINCIPLE
|
17-Mar-2022
|
|
|
|
|
|
No
|
48
|
Orissa
|
FP/OR/REHAB/44871/2020
|
5-ORB429/2020-BHU
|
Relocation of Pitanau (W) Hamlet situated inside Hadagarh Wildlife Sanctuary
|
Rehabilitation
|
TAHASILDAR, HATADIHI TAHASIL
|
4.928
|
IN-PRINCIPLE
|
16-Sep-2020
|
|
|
|
|
|
No
|
49
|
Orissa
|
FP/OR/TRANS/8680/2014
|
5-ORC312/2017-BHU
|
220 Kv Line Diversion from Loc-59 to 75
|
Transmission Line
|
OPTCL
|
7.102
|
IN-PRINCIPLE
|
29-May-2017
|
|
|
|
|
|
No
|
50
|
Orissa
|
FP/OR/IND/36705/2018
|
5-ORC400/2019-BHU
|
Iron Ore Grinding, De-Sliming (Beneficiation) Plant & Slurry Pumping Station and Water Intake System of M/s JSW Utkal Steel Ltd., Barbil Tahasil, Keonjhar District
|
Industry
|
JSW UTKAL STEEL LIMITED
|
22.671
|
IN-PRINCIPLE
|
23-Dec-2019
|
|
|
|
|
|
Yes
Proposal No.: IA/OR/IND/74415/2018
EC File No.:
Proposal Status: Delisted
|
|