Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Haryana FP/HR/Approach/48981/2020 9555 Diversion of forest land for access to the Proposed Retail Outlet of Bharat Petroleum Corporation Ltd. on Bilaspur - Ranjeetpur Road at Village Ruhlaheri, Tehsil Bilaspur, Distt. Yamunanagar, Haryana Approach Access BHARAT PETROLEUM CORPORATION LIMITED 0.1109 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 29 Aug 2020
Stage-I Approval on : 01 Nov 2020
Compliance Report Submitted by User Agency on : 04 May 2026
2 Haryana FP/HR/ROAD/138894/2021 9-HRB155-2021-CHA Widening strengthening of road from Sirsa-Ottu-Rania-Dabwali road Road PUBLIC WORKS DEPARTMENT BUILDING AND ROADS 0.808 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 20 Mar 2021
Stage-I Approval on : 26 May 2022
Compliance Report Submitted by User Agency on : 28 Apr 2026
3 Haryana FP/HR/ROAD/151320/2022 D-III-10324 Diversion of 0.7934 hac. of Forest Land for construction of 2 Lane ROB on LC No. – 114 on Mandi Adampur to Daroli Road at Adampur in Distt. - Hisar (HR). Road PROVINCIAL DIVISION PWD B&R BR., HISAR 0.7934 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 18 Jan 2022
Stage-I Approval on : 06 Jul 2022
Compliance Report Submitted by User Agency on : 16 Jan 2025
4 Haryana FP/HR/ROAD/51036/2020 9-HRB092-2021-CHA For 4-Lanning of Hisar-Mangali Sharwa road from RD 0.00 to 2.730 Road EXECUTIVE ENGINEER HISAR 3.646 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 28 Oct 2020
Stage-I Approval on : 25 Jun 2021
Compliance Report Submitted by User Agency on : 28 Apr 2026
5 Haryana FP/HR/TRANS/10230/2015 5118 220 kv D/C Deepalpur to sector-6 Sonipat Transmission line Transmission Line HARYANA VIDYUT PRASARAN NIGAM LIMITED 0.18375 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 20 Feb 2015
Stage-I Approval on : 25 Jan 2016
Compliance Report Submitted by User Agency on : 07 Dec 2025
6 Haryana FP/HR/TRANS/119706/2021 10042 Construction of 02 No. new 66 KV Towers for new 33 KV Rampur-Chhouli line emanating from 220 KV Sub Station Rampur Kamboj at Crossing of SOM River Transmission Line UHBVN YAMUNA NAGAR 0.089 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 16 Jan 2021
Stage-I Approval on : 23 Nov 2021
Compliance Report Submitted by User Agency on : 24 Dec 2025
7 Haryana FP/HR/TRANS/12621/2015 D-III-6450 400 KV DC Kirori- Jind Transmission Line Transmission Line HARYANA VIDYUT PRASARAN NIGAM LTD 0.3328 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 14 May 2015
Stage-I Approval on : 31 Mar 2016
Compliance Report Submitted by User Agency on : 27 Feb 2026
8 Haryana FP/HR/TRANS/42546/2019 9572 66 KV D/C Line From 220 KV S/Stn. Tepla to Proposed 66 KV S/stn 12 Cross Road Ambala Cantt. Transmission Line HVPNL AMBALA 0.603 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 19 Oct 2019
Stage-I Approval on : 18 Nov 2020
Compliance Report Submitted by User Agency on : 10 Jun 2024
9 Haryana FP/HR/TRANS/8437/2014 6211 Construction of 220KV Double Circuit Line from 220KV Substation A-5 to A-4 Substation Faridabad. Transmission Line HVNPL FARIDABAD 0.441 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 05 Dec 2014
Stage-I Approval on : 05 Jan 2019
Compliance Report Submitted by User Agency on : 08 Apr 2026
Please wait ...