Ministry of Environment,Forest and Climate Change
Government of India
Uttarakhand
State Forest Department
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Uttarakhand FP/UK/ROAD/8880/2014 1(94)/15 Chinyalisaur to Kot-Bagi motor Road from Km. 7.00 to Km. 10.00 till kot village Road PMGSY ID UTTARKASHI 0.262 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 26 Dec 2014
Stage-I Approval on : 17 Apr 2015
Compliance Report Submitted by User Agency on : 23 Aug 2023
2 Uttarakhand FP/UK/ROAD/8571/2014 1(96)/15 construction of chinyalisaur jogath motor road to Bagodi motor Road Road PMGSY ID UTTARKASHI 1.319 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 16 Dec 2014
Stage-I Approval on : 21 Apr 2015
Compliance Report Submitted by User Agency on : 26 Apr 2022
3 Uttarakhand FP/UK/ROAD/9574/2015 1(114)/15 Nakuri Singot Motor Road To Paab Motor Road Road PMGSY ID UTTARKASHI 1.092 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 23 Jan 2015
Stage-I Approval on : 02 May 2015
Compliance Report Submitted by User Agency on : 12 Jul 2023
4 Uttarakhand FP/UK/ROAD/10540/2015 8B/UCP/06/65/2015-FC Const. of Remaining part Jasoli-Kanda Motor Road under State Sector Road PUBLIC WORK DEPARTMENT 0.665 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 27 Feb 2015
Stage-I Approval on : 27 Oct 2015
Compliance Report Submitted by User Agency on : 20 Jun 2024
5 Uttarakhand FP/UK/ROAD/10294/2015 1(490)/2015 Manaldura to Nanankoti Motor Road Road PUBLIC WORKS DEPARTMENT 2.7 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 23 Feb 2015
Stage-I Approval on : 03 Nov 2015
Compliance Report Submitted by User Agency on : 29 Aug 2024
6 Uttarakhand FP/UK/ROAD/10924/2015 8B/UCP/06/105/2015-FC Construction of Motor Road from Km. 1 of Mahavidhyalaya Talwari to Government Inter Collage Talwari. Road PUBLIC WORK DEPARTMENT 0.708 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 15 Mar 2015
Stage-I Approval on : 22 Feb 2016
Compliance Report Submitted by User Agency on : 02 May 2024
7 Uttarakhand FP/UK/ROAD/10168/2015 8B/UCP/06/170/2015 Sanglakoti - Bhedgoun - Gudinda Motor Road upto Tilkholi - Jajedi Road PUBLIC WORK DEPARTMENT 1.796 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 16 Feb 2015
Stage-I Approval on : 21 Jun 2016
Compliance Report Submitted by User Agency on : 26 Jun 2024
8 Uttarakhand FP/UK/Others/13110/2015 1(118)/2016 THANA GHANSALI Others S.P OFFICE TEHRI 0.2 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 19 Jun 2015
Stage-I Approval on : 20 Jul 2016
Compliance Report Submitted by User Agency on : 13 Mar 2024
9 Uttarakhand FP/UK/ROAD/14471/2015 8B/UCP/06/6/2016/FC/914 Basola-Bagdiyalgaoun-samaya motor road Road PWD 3.132 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 05 Aug 2015
Stage-I Approval on : 06 Sep 2016
Compliance Report Submitted by User Agency on : 15 Jul 2024
10 Uttarakhand FP/UK/ROAD/18222/2016 8B/UCP/06/73/2016/FC/926 Construction of Maalai to Bhatkwali Motor Road under PMGSY Road RES PMGSY KARANPERAYAG 3.376 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 01 Mar 2016
Stage-I Approval on : 08 Sep 2016
Compliance Report Submitted by User Agency on : 02 Mar 2024
11 Uttarakhand FP/UK/ROAD/8986/2014 8B/UCP/06/118/2015-FC/934 Extension of Kunnigard Hiruli Bazar Motor Road Upto Rampur Chaukhutiya Road PUBLIC WORK DEPARTMENT 1.35 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 30 Dec 2014
Stage-I Approval on : 09 Sep 2016
Compliance Report Submitted by User Agency on : 20 May 2024
12 Uttarakhand FP/UK/ROAD/8483/2014 8B/UCP/06/184/2015/ FC Vinyak-Rikhar Kotiyag Motor Road Road PUBLIC WORK DEPARTMENT 2.7 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 08 Dec 2014
Stage-I Approval on : 18 Oct 2016
Compliance Report Submitted by User Agency on : 20 May 2024
13 Uttarakhand FP/UK/ROAD/11292/2015 8B/UCP/06/222/2015 Construction of Farsali Palli To Kharkanatoli Road PMGSY 8.931 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 26 Mar 2015
Stage-I Approval on : 14 Mar 2017
Compliance Report Submitted by User Agency on : 07 Sep 2024
14 Uttarakhand FP/UK/ROAD/9364/2015 8B/UCP/06/112/2015/FC Construction of BAYELA NAD Motor Road Road PUBLIC WORK DEPARTMENT 4.417 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 16 Jan 2015
Stage-I Approval on : 07 Sep 2017
Compliance Report Submitted by User Agency on : 28 Dec 2023
15 Uttarakhand FP/UK/ROAD/9783/2015 8B/UCP/06/119/2016/FC Construction of Koti Band to Ghathora Motor Road and 2 R.C.C. Bridge in district Chamoli Road PUBLIC WORKS DEPARTMENT 1.099 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 31 Jan 2015
Stage-I Approval on : 07 Sep 2017
Compliance Report Submitted by User Agency on : 08 May 2024
16 Uttarakhand FP/UK/ROAD/13374/2015 8B/UCp/06/226/2015/FC Construction of Kapkot Karmi Motor Road to Toli Motor Road Road PMGSY 4.734 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 20 Jun 2015
Stage-I Approval on : 22 Sep 2017
Compliance Report Submitted by User Agency on : 13 Aug 2024
17 Uttarakhand FP/UK/ROAD/12466/2015 8B/UCP/06/101/2015/FC Wheel Kulwan to Juna State Missing link motor road in District Bageshwar Road PROVINCIAL DIVISION PWD BAGESHWAR 0.91 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 12 May 2015
Stage-I Approval on : 22 Sep 2017
Compliance Report Submitted by User Agency on : 05 Aug 2024
18 Uttarakhand FP/UK/ROAD/10583/2015 8B/UCP/06/202/2015 construction of new motor road of name from baula to srikot Road PUBLIC WORKS DEPARTMENT GOPESHWAR UTTARAKHAND 0.32 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 01 Mar 2015
Stage-I Approval on : 11 Oct 2017
Compliance Report Submitted by User Agency on : 28 Jun 2024
19 Uttarakhand FP/UK/ROAD/8636/2014 8B/UCP/06/08/2015/FC BAURPUL_HANUMANDIR_CHHOTIHALDWANI_GANESH JOSHI ke khet tak Marg. Road EXECUTIVE ENGINEER CD PWD HALDWANI 0.8888 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 16 Dec 2014
Stage-I Approval on : 12 Jan 2018
Compliance Report Submitted by User Agency on : 19 Jul 2024
20 Uttarakhand FP/UK/ROAD/10762/2015 8B/UCP/06/40/2016 Construction of Bungidhar Mehalchauri Bachhuwaban MR, km-25 to Syuni Talli Motor Road under PMGSY Road RES PMGSY KARANPERAYAG 2.73 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 01 May 2015
Stage-I Approval on : 22 Jan 2018
Compliance Report Submitted by User Agency on : 25 May 2024
21 Uttarakhand FP/UK/ROAD/16103/2015 8B/UCP/06/91/2016/FC Extension of Ganiadoli Tana Vishalkote motor road via Taraswar, Kothiya and Doni. Road EXECUTIVE ENGINEER 0.9 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 11 Feb 2016
Stage-I Approval on : 22 Jan 2018
Compliance Report Submitted by User Agency on : 01 May 2024
22 Uttarakhand FP/UK/ROAD/28731/2017 1(26)/2018 new construction of Harethi-Jineth to Patara-Syalna motor road. Road EXECUTIVE ENGINEER PD PWD UTTARKASHI 0.874 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 26 Aug 2017
Stage-I Approval on : 23 Feb 2018
Compliance Report Submitted by User Agency on : 20 Jul 2024
23 Uttarakhand FP/UK/ROAD/11434/2015 8B/UCP/06/262/2015/FC Construction of Banlekh Maudiyar Gwatoli Motor road (12.00 km) under SCP Road PWDKAPKOT 4.41 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 01 Apr 2015
Stage-I Approval on : 02 Aug 2018
Compliance Report Submitted by User Agency on : 07 May 2024
24 Uttarakhand FP/UK/ROAD/20189/2016 8B/UCP/06/15/2018 Construction of Sarkot-Devsari Motor Road. Road PUBLIC WORK DEPARTMENT 5.964 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 24 Jun 2016
Stage-I Approval on : 21 Aug 2018
Compliance Report Submitted by User Agency on : 29 Sep 2023
25 Uttarakhand FP/UK/ROAD/9917/2015 8B/UCP/06/277/2015/FC Construction of Leti-Riyasi to Tarkuli M/R under PMGSY. Road PMGSY 4.98 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 06 Feb 2015
Stage-I Approval on : 03 Oct 2018
Compliance Report Submitted by User Agency on : 01 Aug 2024
26 Uttarakhand FP/UK/ROAD/10925/2015 8B/UCP/06/229/2015/FC sonala kandara to kanchula gain M/R Road PUBLIC WORKS DEPARTMENT GOPESHWAR UTTARAKHAND 4 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 15 Mar 2015
Stage-I Approval on : 12 Oct 2018
Compliance Report Submitted by User Agency on : 29 Jun 2024
27 Uttarakhand FP/UK/ROAD/13205/2015 8B/UCP/06/292/2015/FC Sauda Dwara to Chamoli Chawk Motar Road Road PUBLIC WORK DEPARTMENT 3.01 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 12 Jun 2015
Stage-I Approval on : 29 Oct 2018
Compliance Report Submitted by User Agency on : 26 Apr 2024
28 Uttarakhand FP/UK/ROAD/10146/2015 8B/UCP/06/263/2015/FC Bhandeli Bend (Thalisain) To Jakhola Motor Road, KM 9.500 Under PMGSY Road PMGSY BAIJRO 4.75 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 15 Feb 2015
Stage-I Approval on : 07 Jan 2019
Compliance Report Submitted by User Agency on : 11 Apr 2024
29 Uttarakhand FP/UK/ROAD/20937/2016 1(225) Construction of Road in village Rainapur Girdhari Lal Farm to Turanmajra in District Dehradun. Road PUBLIC WORK DEPARTMENT 0.6 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 28 Jul 2018
Stage-I Approval on : 02 Jan 2019
Compliance Report Submitted by User Agency on : 20 Jun 2024
30 Uttarakhand FP/UK/ROAD/12309/2015 8B/UCP/06/224/2015/FC DHANKRI KHAL TOK TWO CHOKI KHAL VIA KASANA VICHALA M/R Road PWD 1.08 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 30 Apr 2015
Stage-I Approval on : 21 Jan 2019
Compliance Report Submitted by User Agency on : 14 May 2024
31 Uttarakhand FP/UK/ROAD/16778/2015 8B/UCP/06/13/2018/FC Devinagar (Dhampur)-Tusrera-Thanga motor road in District-Bageshwar Road PROVINCIAL DIVISION PWD BAGESHWAR 4.4905 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 02 Dec 2015
Stage-I Approval on : 18 Feb 2019
Compliance Report Submitted by User Agency on : 02 Aug 2024
32 Uttarakhand FP/UK/ROAD/27734/2017 8B/UCP/06/54/2019/FC Construction of Tharali to Paingarh Motor Road under PMGSY. Road RES PMGSY KARANPERAYAG 4.812 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 07 Feb 2019
Stage-I Approval on : 02 Jul 2019
Compliance Report Submitted by User Agency on : 17 Feb 2024
33 Uttarakhand FP/UK/ROAD/27732/2017 8B/UCP/06/64/2019/FC Construction of Tharali Kurar Motor Road, km-15 to Gummar Lagga Gerur Link Motor Road under PMGSY in phase-XVI Road RES PMGSY KARANPERAYAG 1.825 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 18 Dec 2018
Stage-I Approval on : 17 Dec 2019
Compliance Report Submitted by User Agency on : 12 Sep 2024
34 Uttarakhand FP/UK/ROAD/28915/2017 8B/UCP/06/114/2018/FC Bageshwar Kapkot Tejam MR Km 57 to Badhi Panyali MR Road PMGSY 3.42 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 27 Aug 2017
Stage-I Approval on : 09 Jun 2020
Compliance Report Submitted by User Agency on : 25 Sep 2024
35 Uttarakhand FP/UK/ROAD/38079/2019 8B/UCP/06/111/2019/FC Construction of Dhurmakudi km.2.00 to Mokhmalla Motor Road Road PMGSY 3.275 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 18 Feb 2019
Stage-I Approval on : 07 Aug 2020
Compliance Report Submitted by User Agency on : 05 Oct 2024
36 Uttarakhand FP/UK/ROAD/41895/2019 1(116)/2020 Construction of Chopta to Dadugad Motor Road. Road PUBLIC WORK DEPARTMENT 0.404 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 05 Sep 2019
Stage-I Approval on : 02 Sep 2020
Compliance Report Submitted by User Agency on : 12 Jul 2024
37 Uttarakhand FP/UK/ROAD/15129/2015 8B/UCP/06/202/2016/FC Jamrani bend to belwal gaon motor road and 18 mtr span R.C.C Motor Bridge Road CONSTRUCTION DIVISION PWD ALMORA 0.972 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 26 Nov 2015
Stage-I Approval on : 10 Sep 2020
Compliance Report Submitted by User Agency on : 23 Jul 2024
38 Uttarakhand FP/UK/ROAD/45667/2020 8B/UCP/06/101/2020/FC Kalimati Chittor Ghaishen to Upper talai Road PUBLIC WORK DEPARTMENT 1.5225 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 02 Jun 2020
Stage-I Approval on : 30 Sep 2020
Compliance Report Submitted by User Agency on : 05 Apr 2024
39 Uttarakhand FP/UK/ROAD/38048/2019 8B/UCP/06/42/2020/FC C/o Naugaon to Kanarichhina Motor road distt almora Road CONSTRUCTION DIVISION PWD ALMORA 1.377 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 04 Jan 2019
Stage-I Approval on : 30 Sep 2020
Compliance Report Submitted by User Agency on : 23 Jul 2024
40 Uttarakhand FP/UK/ROAD/34286/2018 8B/UCP/06/31/2020/FC Gangani To Bhangeli Motor Road. Road PMGSY ID UTTARKASHI 1.316 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 20 Jun 2018
Stage-I Approval on : 09 Oct 2020
Compliance Report Submitted by User Agency on : 27 Aug 2024
41 Uttarakhand FP/UK/ROAD/43073/2019 1(128)/2020 Dhundsir Shivalya Link Motor road Road PWD 0.566 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 07 Dec 2019
Stage-I Approval on : 13 Oct 2020
Compliance Report Submitted by User Agency on : 03 May 2023
42 Uttarakhand FP/UK/ROAD/39862/2019 1(150)/2020 Construction of Gwaldam to Center School Motor Road. Road PUBLIC WORK DEPARTMENT 0.981 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 15 Apr 2019
Stage-I Approval on : 13 Oct 2020
Compliance Report Submitted by User Agency on : 18 Jul 2024
43 Uttarakhand FP/UK/ROAD/18882/2016 1(153)/2020 Timiltona Aarusari Virot Bhemitola Talayi Motor Road. Road EXECUTIVE ENGINEER 0.945 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 02 May 2016
Stage-I Approval on : 22 Dec 2020
Compliance Report Submitted by User Agency on : 19 Jan 2024
44 Uttarakhand FP/UK/ROAD/50755/2020 1(216)/2020 Gaumukh to Village Dobh (Patiyon) Motor road Road PWD 0.095 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 22 Oct 2020
Stage-I Approval on : 31 Jan 2021
Compliance Report Submitted by User Agency on : 21 Dec 2023
45 Uttarakhand FP/UK/WATER/40701/2019 8-16/2020-FC SONG DAM DRINKING WATER PROJECT Drinking Water INFRASTRUCTURE (REHAB)DIVISION RISHIKESH, DEHRADUN 127.6712 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 24 Jun 2019
Stage-I Approval on : 05 Jan 2021
Compliance Report Submitted by User Agency on : 08 May 2024