List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 West Bengal FP/WB/TRANS/34435/2018 FR/O/L/10T-9/2018 765kV D/C (Hexa) Ranchi- Medinipur Transmission Line (WB) Transmission Line POWERGRID MEDINIPUR JEERAT TRANSMISSION LIMITED 17.876 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Jun 2018
Stage-I Approval on : 18 Jan 2019
Compliance Report Submitted by User Agency on : 21 Aug 2019
26 Aug 2020
2 West Bengal FP/WB/ROAD/30060/2017 5-WBC101/2018-BHU Construction of twin 2-lane ROB and its approaches in replacement of existing Level Crossing Gate No.KA-38 (Railway Km.165/21-165/23) between Chandrakona Road and Garbeta Station in Kadamdiha at Km. 159.448 of NH-60 in the State of West Bengal. Road NH WING OF PUBLIC WORKS ROADS DIRECTORATE GOVT OF WEST BENGAL 9.533 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Nov 2017
Stage-I Approval on : 25 Jun 2018
Compliance Report Submitted by User Agency on : 23 Feb 2022
26 Apr 2022
3 West Bengal FP/WB/ROAD/32306/2018 For/O/L/10T-09/2014 Proposal for diversion of 1.997 hec. of forest land in favour of NHIDCL for Construction of 1000 mtr. length viaduct at Rangpo between Km 51.100 to Km 53.900 on Sevoke-Gangtok Road (NH-31A, new NH-10) under Kalimpong Forest Division. Road MORTH (NHIDCL) 1.997 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Feb 2018
Stage-I Approval on : 05 Jul 2018
Compliance Report Submitted by User Agency on : 09 Dec 2021
08 Jun 2023
4 West Bengal FP/WB/Pipeline/150496/2021 IRO/KOL/WB/Pipeline/150496/2021 Haldia Durgapur underground LPG Pipeline Project Pipeline Indian Oil Corporation Limited (Pipelines Division) 0.0262 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Dec 2021
Stage-I Approval on : 23 Jun 2022
Compliance Report Submitted by User Agency on : 06 Feb 2023
02 Mar 2023
5 West Bengal FP/WB/HYD/8214/2014 8-51/2017-FC 1000 MW TURGA PUMPED STORAGE PROJECT Hydel WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 234 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Feb 2017
Stage-I Approval on : 12 Apr 2018
Compliance Report Submitted by User Agency on : 23 May 2022
13 Oct 2022
6 West Bengal FP/WB/Others/42866/2019 5-WBB111/2020-BHU Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Underground Project of GAIL- Others GAIL INDIA LIMITED 0.645 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Nov 2019
Stage-I Approval on : 07 Sep 2020
Compliance Report Submitted by User Agency on : 13 Sep 2021
13 Apr 2022
7 West Bengal FP/WB/Others/7248/2014 5-WBC087/2014-BHU Raniganj Coal Bed Methane Project Others ESSAR OIL AND GAS EXPLORATION AND PRODUCTION LIMITED 18.4321 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Sep 2014
Stage-I Approval on : 02 Feb 2016
Compliance Report Submitted by User Agency on : 21 Nov 2023
01 Jan 2024
8 West Bengal FP/WB/TRANS/51250/2020 WB/TRANS-86/2021/FC Construction of 220 KV Double Circuit Transmission Line from Parulia Substation to Burdwan substation of Damodar Valley Corporation Transmission Line DAMODAR VALLEY CORPORATION 2.131 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Oct 2020
Stage-I Approval on : 04 Feb 2022
Compliance Report Submitted by User Agency on : 07 Nov 2022
03 Mar 2023
9 West Bengal FP/WB/OFC/146241/2021 IRO/KOL/WB/OFC/146241/2021 Proposal of Diversion of 0.0348 Ha of forest land in favour of Reliance Jio Infocomm Ltd THROUGH KHARIARBANDAR FOREST COMPARTMENT ALONG NH-31(R o W ) AND VILLAGE ROAD UNDER JALPAIGURI FOREST DIVISION Optical Fibre Cable Jio Digital Fibre Private Limited 0.0348 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Aug 2021
Stage-I Approval on : 22 Aug 2022
Compliance Report Submitted by User Agency on : 19 Dec 2023
23 Apr 2024
10 West Bengal FP/WB/Pipeline/141208/2021 WB/PFO-81/2021/FC CGS Jamshedpur, WB Pipeline Project, JHBDPL Pipeline GAIL INDIA LIMITED 5.7333 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Apr 2021
Stage-I Approval on : 25 Apr 2022
Compliance Report Submitted by User Agency on : 08 Dec 2022
13 Feb 2023
11 West Bengal FP/WB/Pipeline/141208/2021 WB/PFO-81/2021/FC CGS Jamshedpur, WB Pipeline Project, JHBDPL Pipeline GAIL INDIA LIMITED 5.7333 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Apr 2021
Stage-I Approval on : 25 Apr 2022
Compliance Report Submitted by User Agency on : 08 Dec 2022
13 Feb 2023
12 West Bengal FP/WB/Others/34346/2018 IRO/KOL/WB/Others/34346/2018 Installation of Mobile Tower at Dungdungia-2 Compartment, Lepchajagat Beat, Ghoomsimana Range of Reliance Jio Infocomm Limited Others Jio Digital Fibre Private Limited 0.01 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Jul 2018
Stage-I Approval on : 04 Nov 2022
Compliance Report Submitted by User Agency on : 16 Mar 2023
19 Jun 2023
13 West Bengal FP/WB/RAIL/47649/2020 WB-SRBG-09/2021/FC SIVOK-RANGPO NEW BG RAIL PROJECT Railway NORTH EAST FRONTIER RAILWAY 13.512 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Jul 2020
Stage-I Approval on : 13 Jul 2021
Compliance Report Submitted by User Agency on : 20 Jun 2022
22 Sep 2023
14 West Bengal FP/WB/Others/26270/2017 FR/O/L/10T-5/2019 KARMATHIRTHA Others BDO RAJGANJ 0.03339 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Jul 2018
Stage-I Approval on : 23 Dec 2019
Compliance Report Submitted by User Agency on : 12 Jun 2020
08 Sep 2020
15 West Bengal FP/WB/OFC/152570/2022 IRO/KOL/WB/OFC/152570/2022 Proposal of Laying of OFC Cable along the uphill side(RoW) of the existing Kalijhora/ Mahaldiram via Latpancher from over a stretch of 19.1 Km passes through forest area of Kurseong Forest Div Optical Fibre Cable Jio Digital Fibre Private Limited 0.764 Pending at DFO for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 18 Feb 2022
Stage-I Approval on : 22 Nov 2022
Compliance Report Submitted by User Agency on : 29 Jun 2023
16 West Bengal FP/WB/RAIL/40708/2019 5-WBC110/2020-BHU SIVOK RANGPO NEW BG RAIL LINE PROJECT Railway NORTH EAST FRONTIER RAILWAY 12.3786 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Jun 2019
Stage-I Approval on : 07 Sep 2020
Compliance Report Submitted by User Agency on : 20 Jun 2022
22 Nov 2023
17 West Bengal FP/WB/RAIL/47293/2020 IRO/KOL/WB/RAIL/47293/2020 SIVOK RANGPO NEW BG RAIL LINE PROJECT Railway NORTH EAST FRONTIER RAILWAY 1.75 Pending at DFO for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 17 Jan 2022
Stage-I Approval on : 16 Jun 2022
Compliance Report Submitted by User Agency on : 07 Sep 2023
18 West Bengal FP/WB/TRANS/26667/2017 FR/O/L/10T-9/2017 Construction of new 33 KV Incoming Line for Pirakata 33/11 KV Substation Transmission Line PASCHIM MEDINIPUR RE PROJECT WBSEDCL 3.7728 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 16 Jun 2017
Stage-I Approval on : 05 Sep 2017
Compliance Report Submitted by User Agency on : 06 Dec 2022
19 West Bengal FP/WB/TRANS/16943/2015 5-WBC093/2016-BHU 400kV D/C PURULIA-RANCHI TRANSMISSION LINE (PURULIA & KHARAGPUR TRANSMISSION COMPANY LIMITED) Transmission Line PURULIA KHARAGPUR TRANSMISSION COMPANY LIMITED 12.288 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Dec 2015
Stage-I Approval on : 22 Sep 2016
Compliance Report Submitted by User Agency on : 16 Jul 2018
28 Sep 2018
20 West Bengal FP/WB/MIN/17602/2016 8-45/2018-FC Gangaramchak & Gangaramchak-Bhadulia Coal Mine ( Open cast ) Mining THE WEST BENGAL POWER DEVELOPMENT CORPORATION LIMITED 101.77 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 May 2017
Stage-I Approval on : 29 Oct 2018
Compliance Report Submitted by User Agency on : 20 Feb 2019
10 Apr 2019
21 West Bengal FP/WB/TRANS/9287/2015 5-WBC092/2016-BHU Construction of 400kv Punatsangchu Alipurduaraar transmission line Transmission Line POWERGRID CORPORATION OF INDIA LTD 16.39 APPROVED
Proposal received(at Nodal Officer)electronically on : 13 Jan 2015
Stage-I Approval on : 22 Jun 2016
Compliance Report Submitted by User Agency on : 16 Oct 2017
22 Nov 2017
22 West Bengal FP/WB/ROAD/37617/2018 FR/O/L/10T-02/2019 Realignment, Rehabilitation and Upgrading to 2 lane with paved shoulders configuration of Bagrakot to Kafer (Length of Project Km 0+000 to Km 40+000) & Kafer to Reshi border (Length Km 40+000 to Km 61+250 & Km 76+600 to Km 98+595) of NH-717A in West Bengal State Under Package-IV & Package-V Programme. Road MORTH (NHIDCL) 116.001 APPROVED
Proposal received(at Nodal Officer)electronically on : 12 Dec 2018
Stage-I Approval on : 20 Feb 2019
Compliance Report Submitted by User Agency on : 14 Mar 2020
19 Feb 2021
23 West Bengal FP/WB/ROAD/26127/2017 5-WBB096/2017-BHU Construction of twins 2-lane ROB and its approaches in replacement of level crossing at Km. 652.600 on NH-31 (Railway Km. 20/7-8) between Neora & Lataguri at Lataguri in the state of West Bengal. Road NH WING OF PUBLIC WORKS ROADS DIRECTORATE GOVT OF WEST BENGAL 4.031 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 May 2017
Stage-I Approval on : 20 Sep 2017
Compliance Report Submitted by User Agency on : 26 Jun 2018
21 Dec 2018
24 West Bengal FP/WB/Others/40606/2019 5-WBB105/2019-BHU Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Underground Project of GAIL Others GAIL INDIA LIMITED 2.7279 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Jun 2019
Stage-I Approval on : 01 Jan 2020
Compliance Report Submitted by User Agency on : 18 Sep 2020
24 Dec 2020
25 West Bengal FP/WB/VELEC/34640/2018 FR//O/L/10T-06/2019 DDUGJY Village Electricity JALPAIGURI RE PROJECT WBSEDCL 0.9 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Jul 2018
Stage-I Approval on : 19 Mar 2021
Compliance Report Submitted by User Agency on : 03 Sep 2021
02 Sep 2021
26 West Bengal FP/WB/Others/43857/2020 WB/PFD-49/2021/FC Development of a Tourism Complex in Murguma Others DISTRICT MAGISTRATE, PURULIA 0.99 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Jan 2020
Stage-I Approval on : 04 Feb 2022
Compliance Report Submitted by User Agency on : 23 Mar 2022
27 Apr 2022
27 West Bengal FP/WB/WATER/152151/2022 IRO/KOL/WB/Water/152151/2022 Construction of water reservoir for water supply project within Darjeeling Municipality Under AMRUT. Drinking Water DARJEELING MUNICIPALITY 0.0378 APPROVED
Proposal received(at Nodal Officer)electronically on : 09 Feb 2022
Stage-I Approval on : 28 Jul 2022
Compliance Report Submitted by User Agency on : 07 Feb 2023
06 Mar 2023
28 West Bengal FP/WB/OFC/145633/2021 IRO/KOL/WB/OFC/145633/2021 Proposal of Diversion of 0.224 Ha of forest land in favour of Reliance Jio Infocomm Ltd along Hill Cart Road from Sepoidhura to 8th Mile for Rollout of 4G Services under Kurseong Division Optical Fibre Cable Jio Digital Fibre Private Limited 0.224 Pending at DFO for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 06 Aug 2021
Stage-I Approval on : 20 Sep 2022
Compliance Report Submitted by User Agency on : 29 Jun 2023
29 West Bengal FP/WB/Others/32874/2018 IRO/KOL/WB/Others/32874/2018 Roll Out of 4th Generation (4G) Broadband Services in West Bengal in Hanuman Jhora Others Jio Digital Fibre Private Limited 0.0225 APPROVED
Proposal received(at Nodal Officer)electronically on : 06 Apr 2018
Stage-I Approval on : 20 Sep 2022
Compliance Report Submitted by User Agency on : 24 Feb 2023
07 Jun 2023
30 West Bengal FP/WB/Others/32953/2018 IRO/KOL/FC/98/BSF/2022 KLP RADHABARI FOR ESTABLISHMENT OF BN HQ Others COMMANDANTKLP RADHABARI 12.5 APPROVED
Proposal received(at Nodal Officer)electronically on : 06 Apr 2018
Stage-I Approval on : 18 Jul 2022
Compliance Report Submitted by User Agency on : 23 Jan 2024
25 Apr 2024
31 West Bengal FP/WB/Others/32965/2018 IRO/KOL/WB/Others/32965/2018 Roll Out of 4th Generation (4G) Broadband Services in West Bengal in Dowhill Others Jio Digital Fibre Private Limited 0.0144 Pending at DFO for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 06 Apr 2018
Stage-I Approval on : 20 Sep 2022
Compliance Report Submitted by User Agency on : 29 Jun 2023
32 West Bengal FP/WB/Others/26946/2017 5-WBB102/2018-BHU Augmentation of Paradip-Haldia-Durgapur LPG Pipeline and its extension up to Patna and Muzaffarpur Others Indian Oil Corporation Limited (Pipelines Division) 0.562 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Jul 2017
Stage-I Approval on : 05 Nov 2018
Compliance Report Submitted by User Agency on : 29 Mar 2019
07 Jun 2019
33 West Bengal FP/WB/Others/22966/2016 5-WBC094/2017-BHU "Mega Tourism Project" at Tarapith Others DISTRICT COLLECTOR BIRBHUM 14.682 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Jan 2017
Stage-I Approval on : 22 Mar 2018
Compliance Report Submitted by User Agency on : 27 Jan 2023
10 Mar 2023
34 West Bengal FP/WB/TRANS/34478/2018 FR/O/L/10T-8/2018 LOOP OUT OF 400KV D/C CHANDITALA KHARAGPUR TRANSMISSION LINE AT 765/400KV MEDINIPUR SUBSTATION (WB) Transmission Line POWERGRID MEDINIPUR JEERAT TRANSMISSION LIMITED 0.497 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Jul 2018
Stage-I Approval on : 18 Jan 2019
Compliance Report Submitted by User Agency on : 21 Aug 2019
26 Aug 2020
35 West Bengal FP/WB/RAIL/19711/2016 5-WBB109/2020-BHU SIVOK RANGPO NEW BROAD GAUGE RAIL LINE Railway NORTH EAST FRONTIER RAILWAY 0.9294 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Jul 2016
Stage-I Approval on : 31 Jul 2020
Compliance Report Submitted by User Agency on : 20 Jun 2022
06 Sep 2024
36 West Bengal FP/WB/OFC/141578/2021 IRO/KOL/WB/OFC/141578/2021 Optical fiber cable laying Optical Fibre Cable TELESONIC NETWORK LTD. 0.4278 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Aug 2021
Stage-I Approval on : 17 Jan 2023
Compliance Report Submitted by User Agency on : 14 Mar 2023
20 Apr 2023