Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Important Dates | Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | Stage-II Approval on |
1
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/44305/2020
|
7-5/3-FD/636
|
Gas Distribution Network in Dadra & Nagar Haveli Area (Maliba (HPCL) Petroleum Connectivity, Mahalaxmi Petroleum Connectivity & Khanvel Connectivity)
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.5029
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Jan 2020
|
Stage-I Approval on
|
:
|
12 Oct 2020
|
Compliance Report Submitted by User Agency on
|
:
|
07 Jan 2021
|
|
|
|
19 Nov 2020
|
2
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/151726/2022
|
7-5/3-FD/654
|
Gas Distribution Network in Dadra & Nagar Haveli Area (Kala – Karachgam – Velugam Industrial Area Connectivity & Near Namo Medical Collage Connectivity)
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.3009
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Jan 2022
|
Stage-I Approval on
|
:
|
20 Sep 2023
|
Compliance Report Submitted by User Agency on
|
:
|
26 Oct 2023
|
|
|
|
23 Jan 2024
|
3
|
Dadar & Nagar Haveli
|
FP/DN/Others/16736/2015
|
7-5/3-FD/562
|
Dadra and Nagar Haveli PNG Network : Planning 2015-16
|
Others
|
GUJARAT GAS LIMITED
|
0.6969
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
28 Nov 2015
|
Stage-I Approval on
|
:
|
16 Sep 2016
|
Compliance Report Submitted by User Agency on
|
:
|
25 May 2017
|
|
|
|
18 May 2017
|
4
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/35449/2018
|
7-5/3-FD/622
|
Diversion of Reserved forest land for Construction of an approach road from Chisda to Shelti Vanganpada
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.798
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
28 Aug 2018
|
Stage-I Approval on
|
:
|
19 Aug 2019
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
07 Feb 2020
|
5
|
Dadar & Nagar Haveli
|
FP/DN/Others/29496/2017
|
7-5/3-FD/590
|
Shri Sai (IOCL) Petroleum Connectivity in DNH GA
|
Others
|
GUJARAT GAS LIMITED
|
0.0594
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Sep 2017
|
Stage-I Approval on
|
:
|
16 Apr 2019
|
Compliance Report Submitted by User Agency on
|
:
|
03 Jul 2019
|
|
|
|
05 Nov 2019
|
6
|
Dadar & Nagar Haveli
|
FP/DN/Others/24636/2017
|
7-5/3-FD/575
|
Gas Distribution Network in Amli & Surrounding Area of Dadra & Nagar Haveli
|
Others
|
GUJARAT GAS LIMITED
|
0.3424
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Feb 2017
|
Stage-I Approval on
|
:
|
03 Aug 2017
|
Compliance Report Submitted by User Agency on
|
:
|
14 Mar 2018
|
|
|
|
13 Mar 2018
|
7
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/14983/2015
|
7-5/3-FD/560
|
Development of Vadodara -Mumbai Expressway (Phase-I ) from km 104+700 (km 390+864 of NH8) to Km 378+722 (km 80 of Ahmedabad Vadodara Expressway) in the State of Gujarat, Maharashtra & Union Territory of Dadra & Nagar Haveli (Total length 274.022 km)
|
Road
|
NATIONAL HIGHWAY AUTHORITY OF INDIA-PIU SURAT
|
0.54
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Aug 2015
|
Stage-I Approval on
|
:
|
29 Nov 2016
|
Compliance Report Submitted by User Agency on
|
:
|
13 Aug 2019
|
|
|
|
30 Oct 2018
|
8
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/148752/2021
|
FC-6/GJB-48/2022-GNR
|
Diversion of Forest land for Widening and Strengthening of road stretch from Tinoda to Bindrabin (Ch. 15/8 to 17/4) under State Highway
|
Road
|
EXECUTIVE ENGINEER ROAD DIVISION
|
2.4813
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
26 Oct 2021
|
Stage-I Approval on
|
:
|
21 Dec 2022
|
Compliance Report Submitted by User Agency on
|
:
|
28 Feb 2024
|
|
|
|
10 Oct 2024
|
9
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/124427/2021
|
7-5/3-FD/644
|
Silvassa Spur Pipeline
|
Pipeline
|
PIPELINE INFRASTRUCTURE LIMITED
|
0.1278
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
26 Feb 2021
|
Stage-I Approval on
|
:
|
20 Sep 2021
|
Compliance Report Submitted by User Agency on
|
:
|
24 Dec 2021
|
|
|
|
15 Nov 2021
|
10
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/43020/2019
|
7-5/3-FD/633
|
Construction of Bypass road from Dudhani-Ghodbari Junction to the newly constructed Dudhnai - Kauncha HIgh Level Bridge
|
Road
|
EXECUTIVE ENGINEER ROAD DIVISION
|
0.99
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Nov 2019
|
Stage-I Approval on
|
:
|
27 Apr 2020
|
Compliance Report Submitted by User Agency on
|
:
|
20 Mar 2023
|
|
|
|
08 Jan 2020
|
11
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/44749/2020
|
7-5/3-FD/635
|
Gas Distribution Network in Dadra & Nagar Haveli Area (KLJ Plasticizers Ltd. (Sili) CA-1 Connectivity)
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.2446
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Feb 2020
|
Stage-I Approval on
|
:
|
12 Oct 2020
|
Compliance Report Submitted by User Agency on
|
:
|
07 Jan 2021
|
|
|
|
19 Nov 2020
|
12
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/147607/2021
|
7-2/3-FD/650
|
Gas Distribution Network in Dadra & Nagar Haveli Area (Surangi – Velugam Road, Surangi Connectivity, River crossing at Surangi – Velugam Road, Surangi Connectivity & River crossing at Udhawa – Khanvel
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.0735
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
23 Sep 2021
|
Stage-I Approval on
|
:
|
05 Dec 2022
|
Compliance Report Submitted by User Agency on
|
:
|
31 Dec 2022
|
|
|
|
06 Apr 2023
|
13
|
Dadar & Nagar Haveli
|
FP/DN/WATER/19445/2016
|
7-5/3-FD/565
|
Providing drinking water supply scheme for Gunsa and Bildhari
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.4125
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 May 2016
|
Stage-I Approval on
|
:
|
30 Nov 2017
|
Compliance Report Submitted by User Agency on
|
:
|
08 Feb 2018
|
|
|
|
08 Apr 2020
|
14
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/148523/2021
|
7-5/3-FD/652/
|
Gas Distribution Network in Dadra & Nagar Haveli Area (Anklas – Nagvas village & Looping DNH (PE) Connectivity)
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.0418
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Oct 2021
|
Stage-I Approval on
|
:
|
30 Dec 2022
|
Compliance Report Submitted by User Agency on
|
:
|
27 Jan 2023
|
|
|
|
06 Apr 2023
|
15
|
Dadar & Nagar Haveli
|
FP/DN/WATER/30602/2017
|
DN-034/2017
|
Diversion of protected forest area for the Integrated Water Management Plan WD-II for Dapada , Moti Pati , Vasona & Chikhali village
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.93
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Dec 2017
|
Stage-I Approval on
|
:
|
18 Apr 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
05 Nov 2019
|
16
|
Dadar & Nagar Haveli
|
FP/DN/Others/18995/2016
|
7-5/3-FD/567
|
Dadra & Nagar Haveli PNG Network
|
Others
|
GUJARAT GAS LIMITED
|
0.9756
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Apr 2016
|
Stage-I Approval on
|
:
|
30 Nov 2017
|
Compliance Report Submitted by User Agency on
|
:
|
18 Jan 2018
|
|
|
|
01 Mar 2018
|
17
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/25039/2017
|
7-5/3-FD/576
|
Construction of High Level Bridge connecting Dudhani & Kauncha village across river Damanganga in U.T of Dadra & Nagar Haveli
|
Road
|
EXECUTIVE ENGINEER ROAD DIVISION
|
0.6
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
17 Mar 2017
|
Stage-I Approval on
|
:
|
15 Feb 2018
|
Compliance Report Submitted by User Agency on
|
:
|
20 Aug 2020
|
|
|
|
20 Aug 2018
|
18
|
Dadar & Nagar Haveli
|
FP/DN/SCH/19388/2016
|
FP/DN/SCH/19388/2016
|
Construction of PRE-FAB School in Kauncha Ranpada
|
School
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.056
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
16 May 2016
|
Stage-I Approval on
|
:
|
13 Dec 2016
|
Compliance Report Submitted by User Agency on
|
:
|
22 Mar 2018
|
|
|
|
18 Apr 2018
|
19
|
Dadar & Nagar Haveli
|
FP/DN/Others/26693/2017
|
7-5/3-FD/583/20
|
DRS Spurlines (Steel line) - DNH GA
|
Others
|
GUJARAT GAS LIMITED
|
0.3387
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
16 Jun 2017
|
Stage-I Approval on
|
:
|
15 Feb 2018
|
Compliance Report Submitted by User Agency on
|
:
|
18 Apr 2018
|
|
|
|
03 May 2018
|
20
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/34240/2018
|
7-5/3-FD/612/
|
Diversion of Reserved forest land for Construction of road from Vasda Devipada to Navapada .
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.21
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jun 2018
|
Stage-I Approval on
|
:
|
01 Apr 2019
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
05 Nov 2019
|
21
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/34241/2018
|
7-5/3-FD/613
|
Diversion of Reserved forest land for the Construction of road from Bildhari Patelpada to Ruimal
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.87
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jun 2018
|
Stage-I Approval on
|
:
|
05 Dec 2019
|
Compliance Report Submitted by User Agency on
|
:
|
30 Jun 2020
|
|
|
|
19 Mar 2020
|
22
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/26670/2017
|
DN-014/2017
|
Construction of approach road from Ghodbari Main road to Uplapada
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.36
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jun 2017
|
Stage-I Approval on
|
:
|
03 May 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
30 Oct 2018
|
23
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/26674/2017
|
7-5/3-FD/585/44
|
Construction of approach road from Dudhani Ruipada main road to Tokerpada
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.237
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jun 2017
|
Stage-I Approval on
|
:
|
03 May 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
20 Dec 2018
|
24
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/26672/2017
|
7-5/3-FD/584/61
|
Construction of approach road from Karchond Vansda Main road to Umarmatha
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.684
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jun 2017
|
Stage-I Approval on
|
:
|
30 Nov 2017
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
20 Dec 2018
|
25
|
Dadar & Nagar Haveli
|
FP/DN/TRANS/108286/2020
|
6-DNB089/2021-BHO
|
Construction of 220 kV D/C Vapi-II – Sayali Transmission Line
|
Transmission Line
|
VAPI II-NORTH LAKHIMPUR TRANSMISSION LIMITED
|
4.6135
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Dec 2020
|
Stage-I Approval on
|
:
|
07 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
02 Nov 2022
|
|
|
|
20 Mar 2024
|
26
|
Dadar & Nagar Haveli
|
FP/DN/WATER/30820/2017
|
DN-035/2017
|
Diversion of protected forest area for the Integrated Water Management Plan WD-II for Falandi , Galonda and Umarkui village.
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.82
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Dec 2017
|
Stage-I Approval on
|
:
|
18 Apr 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
01 Jan 2019
|
27
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/40212/2019
|
7-5/3-FD/632/
|
Bhilosa Industries Connectivity
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.323
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 May 2019
|
Stage-I Approval on
|
:
|
22 Jan 2020
|
Compliance Report Submitted by User Agency on
|
:
|
07 Jan 2021
|
|
|
|
12 Mar 2020
|
28
|
Dadar & Nagar Haveli
|
FP/DN/WATER/30803/2017
|
DN-037/2017
|
Diversion of protected forest area for the Integrated Water Management Plan WD-II for Mota Randha, Nana Randha and Bonta village
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.89
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Dec 2017
|
Stage-I Approval on
|
:
|
18 Apr 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
08 May 2020
|
29
|
Dadar & Nagar Haveli
|
FP/DN/WATER/30806/2017
|
DN-036/2017
|
Diversion of protected forest area for the Integrated Water Management Plan WD-II for Silli , Kilvani & Galonda village
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.81
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Dec 2017
|
Stage-I Approval on
|
:
|
18 Apr 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
05 Nov 2019
|
30
|
Dadar & Nagar Haveli
|
FP/DN/Others/35331/2018
|
7-5/3-FD/623
|
Dapada & Chinchpada Village Connectivity in DNH GA
|
Others
|
GUJARAT GAS LIMITED
|
0.244
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Aug 2018
|
Stage-I Approval on
|
:
|
06 Aug 2019
|
Compliance Report Submitted by User Agency on
|
:
|
26 Jul 2023
|
|
|
|
22 Oct 2019
|
31
|
Dadar & Nagar Haveli
|
FP/DN/Others/21886/2016
|
FP/DN/Others/21886/2016
|
Gas Distribution Network in Naroli & Surrounding Area of Dadra & Nagar Haveli
|
Others
|
GUJARAT GAS LIMITED
|
0.8819
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
13 Oct 2016
|
Stage-I Approval on
|
:
|
16 Jan 2018
|
Compliance Report Submitted by User Agency on
|
:
|
14 Mar 2018
|
|
|
|
13 Mar 2018
|
32
|
Dadar & Nagar Haveli
|
FP/DN/Others/21865/2016
|
7-5/3-FD/570
|
Gas Distribution Network in Dadra & Surrounding Area of Dadra & Nagar Haveli
|
Others
|
GUJARAT GAS LIMITED
|
0.3824
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
12 Oct 2016
|
Stage-I Approval on
|
:
|
20 Jul 2017
|
Compliance Report Submitted by User Agency on
|
:
|
18 Jan 2018
|
|
|
|
01 Mar 2018
|
33
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/149192/2021
|
F.No. 7-2/3-FD/651
|
Gas Distribution Network in Dadra & Nagar Haveli Area (Mandoni Connectivity)
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.426
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
11 Nov 2021
|
Stage-I Approval on
|
:
|
19 May 2022
|
Compliance Report Submitted by User Agency on
|
:
|
13 Sep 2022
|
|
|
|
14 Sep 2022
|
34
|
Dadar & Nagar Haveli
|
FP/DN/TRANS/145817/2021
|
7-5/3-FD/645/
|
Erection of underground 11 KV transmission line of M/s Jai Corp Ltd
|
Transmission Line
|
JAI CORP LTD
|
0.135
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
10 Aug 2021
|
Stage-I Approval on
|
:
|
24 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
25 Jan 2022
|
|
|
|
06 Apr 2023
|
35
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/33515/2018
|
7-5/3-FD/609
|
Diversion of Reserved forest land for the Construction of approach road from Bedpa Kalsemal to Maharasthra Border
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.618
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 May 2018
|
Stage-I Approval on
|
:
|
11 Jun 2019
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
07 Feb 2020
|
36
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/33510/2018
|
7-5/3-FD/610
|
Diversion of Reserved forest land for the Construction of an approach road from Sindoni Loharmal Tetmal to Tornachimal
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.294
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 May 2018
|
Stage-I Approval on
|
:
|
03 Jan 2019
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
08 Jun 2019
|
37
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/33504/2018
|
7-5/3-FD/611
|
Construction of approach road from Sindoni Patelpada to Samashan
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.15
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 May 2018
|
Stage-I Approval on
|
:
|
01 Jan 2019
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
05 Dec 2019
|
38
|
Dadar & Nagar Haveli
|
FP/DN/Pipeline/47191/2020
|
7-5/3-FD/637
|
Gas Distribution Network in Dadra & Nagar Haveli Area (Rockwool India Ltd. Connectivity)
|
Pipeline
|
GUJARAT GAS LIMITED
|
0.167
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Jul 2020
|
Stage-I Approval on
|
:
|
25 May 2022
|
Compliance Report Submitted by User Agency on
|
:
|
13 Sep 2022
|
|
|
|
14 Sep 2022
|
39
|
Dadar & Nagar Haveli
|
FP/DN/VELEC/30058/2017
|
DN-027/2017
|
Erection of 100KVA Transformer center with HT line at village Sindoni-Loharmal
|
Village Electricity
|
DNHPDCL
|
0.91
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
07 Nov 2017
|
Stage-I Approval on
|
:
|
26 Jul 2018
|
Compliance Report Submitted by User Agency on
|
:
|
25 Jun 2024
|
|
|
|
08 Aug 2024
|
40
|
Dadar & Nagar Haveli
|
FP/DN/VELEC/30117/2017
|
6-DNC051/2018-BHO
|
Extension of 11kV HT line express feeder from 66/11kV Khanvel Sub-station to Dudhani Char Rasta (under Sansad Adarsh Gram Yojana)
|
Village Electricity
|
DNHPDCL
|
5.8275
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
07 Nov 2017
|
Stage-I Approval on
|
:
|
31 Aug 2020
|
Compliance Report Submitted by User Agency on
|
:
|
29 Aug 2023
|
|
|
|
26 Oct 2023
|
41
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/35775/2018
|
6-DNC053/2021-BHO
|
Diversion of roadside protected forest land for Widening of road from Khanvel Chowk upto Khedpa Border (Ch 19/6 to 40/8)
|
Road
|
EXECUTIVE ENGINEER ROAD DIVISION
|
23.32
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Sep 2018
|
Stage-I Approval on
|
:
|
20 Apr 2022
|
Compliance Report Submitted by User Agency on
|
:
|
19 Aug 2023
|
|
|
|
25 Oct 2023
|
42
|
Dadar & Nagar Haveli
|
FP/DN/Others/35702/2018
|
7-5/3-FD/624/
|
Gas Distribution network for Chikhli, Surangi, Khadoli, Khanvel, Kala & Kherdi Village Surrounding Area Dadra and Nagar Haveli
|
Others
|
GUJARAT GAS LIMITED
|
0.7608
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Sep 2018
|
Stage-I Approval on
|
:
|
08 Aug 2019
|
Compliance Report Submitted by User Agency on
|
:
|
27 Dec 2019
|
|
|
|
07 Jan 2020
|
43
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/26018/2017
|
7-5/3-FD/579
|
Construction of approach road from Chisda Akharmal to Murdulpada and Khokharpada
|
Road
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.78
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 May 2017
|
Stage-I Approval on
|
:
|
15 Feb 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
30 Oct 2018
|
44
|
Dadar & Nagar Haveli
|
FP/DN/WATER/30609/2017
|
DN-038/2017
|
Diversion of protected forest area for the Integrated Water Management Plan WD-II for Umarkui , Saily and Rakholi village.
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.74
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Dec 2017
|
Stage-I Approval on
|
:
|
18 Apr 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
08 Apr 2020
|
45
|
Dadar & Nagar Haveli
|
FP/DN/WATER/30601/2017
|
DN-033/2017
|
Diversion of protected forest area for the Integrated Water Management Plan WD-II for Morkhal and Kilvani village
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.78
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Dec 2017
|
Stage-I Approval on
|
:
|
18 Apr 2018
|
Compliance Report Submitted by User Agency on
|
:
|
03 Dec 2019
|
|
|
|
05 Nov 2019
|
46
|
Dadar & Nagar Haveli
|
FP/DN/Others/32949/2018
|
7-5/3-FD/630
|
Proposal for laying OFC for Reliance Jio Infocomm Limited 4G Dadra Nagar Haveli District
|
Others
|
RELIANCE JIO INFOCOMM LTD
|
4.23
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Apr 2018
|
Stage-I Approval on
|
:
|
06 Mar 2020
|
Compliance Report Submitted by User Agency on
|
:
|
31 Aug 2020
|
|
|
|
14 Jan 2020
|
47
|
Dadar & Nagar Haveli
|
FP/DN/Others/30063/2017
|
7-5/3-FD/596
|
Athola Connectivity - DNH GA 2017-18
|
Others
|
GUJARAT GAS LIMITED
|
0.202
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
04 Nov 2017
|
Stage-I Approval on
|
:
|
16 Apr 2019
|
Compliance Report Submitted by User Agency on
|
:
|
03 Jul 2019
|
|
|
|
05 Nov 2019
|
48
|
Dadar & Nagar Haveli
|
FP/DN/Others/149878/2021
|
7-2/3-FD/653
|
Bhilosa Private Limited Pipeline
|
Others
|
GUJARAT STATE PETRONET LTD
|
0.4098
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
04 Dec 2021
|
Stage-I Approval on
|
:
|
31 May 2022
|
Compliance Report Submitted by User Agency on
|
:
|
02 Jul 2024
|
|
|
|
07 Nov 2023
|
49
|
Dadar & Nagar Haveli
|
FP/DN/ROAD/36313/2018
|
7-5/3-FD/629
|
Diversion of protected forest land for the widening of existing 4 lane to 6 lane road stretch on Silvassa - Naroli road under Beautification & strenghthening of road including up gradation of storm wa
|
Road
|
EXECUTIVE ENGINEER ROAD DIVISION
|
0.772
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Oct 2018
|
Stage-I Approval on
|
:
|
24 Dec 2019
|
Compliance Report Submitted by User Agency on
|
:
|
06 Apr 2023
|
|
|
|
06 Apr 2023
|
50
|
Dadar & Nagar Haveli
|
FP/DN/WATER/30019/2017
|
7-5/3-FD/595
|
Diversion of protected forest area for the Integrated Water Management Plan WD-III for Amboli , Kala, Karachgam , Kherdi , Parzai & Dolara village
|
Drinking Water
|
EXECUTIVE ENGINEER PWD III IRRIGATION DISTRICT PANCHAYAT DADRA AND NAGAR HAVELI
|
0.997
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Nov 2017
|
Stage-I Approval on
|
:
|
05 Dec 2019
|
Compliance Report Submitted by User Agency on
|
:
|
31 Jul 2023
|
|
|
|
23 Oct 2020
|
|