Ministry of Environment,Forest and Climate Change
Government of India
Jammu and Kashmir
State Forest Department
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Jammu and Kashmir FP/JK/ROAD/51130/2020 9-JKC-019/2022-Jammu Construction of Motorable Road Ikhala Block Boundary Kishtwar to Lopara Road part -II Road CHIEF ENGINEER PMGSY (JKRRDA) JAMMU 5.9312 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Oct 2020
Stage-I Approval on : 21 Oct 2022
Compliance Report Submitted by User Agency on : 15 Mar 2023
02 Apr 2025
2 Jammu and Kashmir FP/JK/ROAD/46676/2020 FST-Land0FC/1/2021-02 Construction of Road Neota to manwah Dispensary in Km 9th and 10th Road R&B DEPARTMENT JAMMU 0.225 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Jun 2020
Stage-I Approval on : 09 Sep 2021
Compliance Report Submitted by User Agency on : 08 Nov 2024
16 Feb 2025
3 Jammu and Kashmir FP/JK/ROAD/150559/2021 FST-land0FC/76/2022-02 CONSTRUCTION OF ROAD FROM KHADWAL TO BHATTI TALAB, LENGTH = 1.50 KM Road ASSTT. EXECUTIVE ENGINEER PWD(R&B) SUB DIVISION MAJALTA 0.58 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Dec 2021
Stage-I Approval on : 30 Sep 2022
Compliance Report Submitted by User Agency on : 05 Sep 2024
16 Feb 2025
4 Jammu and Kashmir FP/JK/TRANS/44317/2020 9-JKB-014/2021-Jammu Re-routing of 400 KV S/C Dulhasti-Kishenpur TL Transmission Line POWERGRID CORPORATION OF INDIA LIMITED BATOTE 1.54 APPROVED
Proposal received(at Nodal Officer)electronically on : 03 Mar 2020
Stage-I Approval on : 30 Jul 2021
Compliance Report Submitted by User Agency on : 24 Nov 2022
12 Dec 2024
5 Jammu and Kashmir FP/JK/ROAD/44818/2020 9-JKC-085/2021-Jammu Construction of road Cl-9 SBA specification (Defence Road)from Km 0.00 to Km 13.41 Pharkian Gali- Puthkhan Gali by BRO. Road HQ 109 ROAD CONSTRUCTION COY (P) BEACON 22.445 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Feb 2020
Stage-I Approval on : 20 Jan 2022
Compliance Report Submitted by User Agency on : 13 Apr 2023
03 Dec 2024
6 Jammu and Kashmir FP/JK/ROAD/146404/2021 9-JKC-002/2022-JAMMU Upgradation of road from Thial to Chountra Mata KM 6th RD 500 to KM 19th RD 500. Road AEE PWD (R&B) SUB DIVISION MAJALTA 5.6 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Aug 2021
Stage-I Approval on : 12 Jan 2023
Compliance Report Submitted by User Agency on : 17 Sep 2024
13 Nov 2024
7 Jammu and Kashmir FP/JK/TRANS/152211/2022 9-JKC-038/2022-Jammu Construction of LILO of 220 KV Udhampur-Gladni Transmission Line at Nagrota GSS Transmission Line JAMMU AND KASHMIR STATE POWER TRANSMISSION COMPANY LIMITED 11.2525 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Feb 2022
Stage-I Approval on : 06 Dec 2022
Compliance Report Submitted by User Agency on : 12 Jun 2024
20 Sep 2024
8 Jammu and Kashmir FP/JK/OFC/152115/2022 9-JKA-005/2023-Jammu Laying of OFC Cable From Badherwaha, Chinta to Kondlu via Jai Ghati Optical Fibre Cable VINDHYA TELELINKS LTD 0.9343 APPROVED
Proposal received(at Nodal Officer)electronically on : 08 Feb 2022
Stage-I Approval on : 11 Apr 2023
Compliance Report Submitted by User Agency on : 22 Sep 2023
24 Jun 2024
9 Jammu and Kashmir FP/JK/ROAD/156314/2022 9-JKA-055/2022-Jammu Construction of Lali Dabbar to Tote road Phase III, length=2.00 kms (Under NABARD) Road ASSTT. EXECUTIVE ENGINEER PWD(R&B) SUB DIVISION MAJALTA 0.7022 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Jun 2022
Stage-I Approval on : 29 Oct 2022
Compliance Report Submitted by User Agency on : 13 Oct 2023
06 Dec 2023
10 Jammu and Kashmir FP/JK/OFC/155186/2022 9-JKA-022/2023-Jammu Laying of Aerial OFC in Udhampur Chulna road Optical Fibre Cable JIO DIGITAL FIBER PRIVATE LIMITED 0.7768 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 May 2022
Stage-I Approval on : 22 May 2023
Compliance Report Submitted by User Agency on : 10 Jul 2023
28 Oct 2023
11 Jammu and Kashmir FP/JK/ROAD/151949/2022 9-JKA-045/2022-Jammu Construction of road from Peerah (NHAI) to Kameti Road PWD R&B JAMMU 0.99 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Feb 2022
Stage-I Approval on : 07 Dec 2022
Compliance Report Submitted by User Agency on : 15 Apr 2023
17 Oct 2023
12 Jammu and Kashmir FP/JK/ROAD/151949/2022 9-JKA-045/2022-Jammu Construction of road from Peerah (NHAI) to Kameti Road PWD R&B JAMMU 0.99 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Feb 2022
Stage-I Approval on : 07 Dec 2022
Compliance Report Submitted by User Agency on : 15 Apr 2023
17 Oct 2023
13 Jammu and Kashmir FP/JK/ROAD/150343/2021 9-JKB-022/2022-Jammu Construction Of Road from Ramakunda To Gool Road PWD R&B JAMMU 3.27 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Dec 2021
Stage-I Approval on : 12 Oct 2022
Compliance Report Submitted by User Agency on : 30 Mar 2023
12 Oct 2023
14 Jammu and Kashmir FP/JK/ROAD/152729/2022 9-JKB-037/2022-Jammu 4 Laning of Nasri-Ramban Section of NH 44 (old NH1A) at CRITICAL LOCATIONS between km 130 and km 151 in the UT of Jammu & Kashmir Road NATIONAL HIGHWAY AUTHORITY OF INDIA 3.4482 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Feb 2022
Stage-I Approval on : 25 Oct 2022
Compliance Report Submitted by User Agency on : 06 Feb 2023
18 Jul 2023
15 Jammu and Kashmir FP/JK/Others/153363/2022 9-JKA-040/2022-Jammu Temporary permission of installation of Hot mix plant and crusher plant for Widening and Strengthening of the existing approach road from Digdole to Bajmasta in Connection with construction of new Adit at Urnihal to the tunnel T49A on Katra Banihal Section of USBRL Project. Others R. K. INFRACORP PRIVATE LIMITED 0.2421 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Mar 2022
Stage-I Approval on : 30 Aug 2022
Compliance Report Submitted by User Agency on : 18 May 2023
18 Jul 2023
16 Jammu and Kashmir FP/JK/TRANS/140816/2021 9-JKC-069/2021-Jammu Re routing of 400kV Single Circuit Dulhasti-Kishenpur Transmission Line at Drabshalla in district Kishtwar Transmission Line POWERGRID CORPORATION OF INDIA LIMITED BATOTE 6.003 APPROVED
Proposal received(at Nodal Officer)electronically on : 09 Apr 2021
Stage-I Approval on : 27 Sep 2021
Compliance Report Submitted by User Agency on : 16 Jun 2023
12 Jul 2023
17 Jammu and Kashmir FP/JK/ROAD/47867/2020 9-JKA-059/2021-JAMMU Construction of road from Lali Dhabar via Sergali Pauni (Dhengidhar) to village Tote Phase 2nd under NABARD Loan Assistance (L= 2.0 km) Road EXECUTIVE ENGINEER PWD(R AND B) DIVISION UDHAMPUR 0.644 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Jul 2020
Stage-I Approval on : 18 Aug 2021
Compliance Report Submitted by User Agency on : 13 Sep 2022
05 Apr 2023
18 Jammu and Kashmir FP/JK/ROAD/146042/2021 9-JKC-034/2022-Jammu Development of Package-17 (KM 515+000 to KM 566+475) of Phase-II of Delhi-Katra Expressway Road NATIONAL HIGHWAY AUTHORITY OF INDIA 36.2511 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Aug 2021
Stage-I Approval on : 26 Oct 2022
Compliance Report Submitted by User Agency on : 10 Feb 2023
05 Apr 2023
19 Jammu and Kashmir FP/JK/OFC/144255/2021 9-JKA-030/2022-Jammu Underground & Aerial Cabling from Bhandarkot - Hynen , Marwah Forest Div, Kishtwar District by Jio Digital Fibre Pvt Ltd. Optical Fibre Cable JIO DIGITAL FIBER PRIVATE LIMITED 0.8177 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Jun 2021
Stage-I Approval on : 28 Jul 2022
Compliance Report Submitted by User Agency on : 07 Nov 2022
27 Feb 2023
20 Jammu and Kashmir FP/JK/ROAD/152548/2022 9-JKA-033/2022-Jammu Up-gradation to existing 2-lane highway to 4-lane with Paved Shoulder configuration (NH 144A) from kin. 26.350 (Khati Chowk) to kin. 30.097 (Hanuman Chowk) of Jammu-Akhnoor section in the UT of Jammu and Kashmir Road NHIDCL_JAMMU 0.349 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Feb 2022
Stage-I Approval on : 31 Aug 2022
Compliance Report Submitted by User Agency on : 10 Dec 2022
16 Feb 2023
21 Jammu and Kashmir FP/JK/Others/153316/2022 9-JKA-039/2022-Jammu Installation of Mobile Tower at Jajot Kandu Others RELIANCE JIO INFOCOMM LTD 0.01 APPROVED
Proposal received(at Nodal Officer)electronically on : 09 Mar 2022
Stage-I Approval on : 25 Aug 2022
Compliance Report Submitted by User Agency on : 10 Nov 2022
20 Dec 2022
22 Jammu and Kashmir FP/JK/ROAD/144002/2021 9-JKC-066/2021-Jammu Construction of Main Approach Road from TunnelT14P1 to TunnelT14 Adit (USBRL Project) Road NORTHERN RAILWAY 8.81 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Jun 2021
Stage-I Approval on : 13 Aug 2021
Compliance Report Submitted by User Agency on : 04 Jun 2022
28 Oct 2022
23 Jammu and Kashmir FP/JK/ROAD/145108/2021 9-JKC-093/2021-Jammu 4 Laning of Ramban Banihal Section of NH 44 (old NH1A) at CRITICAL LOCATIONS between km 151 and km 187 in the UT of Jammu & Kashmir Road NATIONAL HIGHWAY AUTHORITY OF INDIA 78.3877 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Jul 2021
Stage-I Approval on : 15 Feb 2022
Compliance Report Submitted by User Agency on : 20 May 2022
26 Oct 2022
24 Jammu and Kashmir FP/JK/ROAD/142566/2021 9-JKB090-2021-JAMMU Development of Package-15 (KM 468+100 to KM 503+250) of Phase-II of Delhi-Katra Expressway Road NATIONAL HIGHWAY AUTHORITY OF INDIA 1.9891 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 May 2021
Stage-I Approval on : 28 Dec 2021
Compliance Report Submitted by User Agency on : 10 Jun 2022
30 Aug 2022
25 Jammu and Kashmir FP/JK/ROAD/143808/2021 9-JKB-004/2022-Jammu Construction and Upgradation to 2-lane with paved shoulder from Km. 80.675 (Start of Kishtwar bypass) to Km 95+550 (end of Helmet top bypass) of length 14.875 Km & link road from 0+000 to 1.871 of length=1.871 km total length = 16.746 km (including link road) on khellani- kishtwar-chattroo-khanabal section of NH-244 in jammu and kashmir Road PMU KISHTWAR, NHIDCL 2.65072 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Jun 2021
Stage-I Approval on : 18 Apr 2022
Compliance Report Submitted by User Agency on : 08 Jun 2022
23 Aug 2022
26 Jammu and Kashmir FP/JK/Others/142143/2021 9-JKA-080/2021-Jammu Temporary Establishment of Crusher Plant for construction of Khellani Tunnel Project Others APCO INFRATECH PVT LTD 0.3533 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 May 2021
Stage-I Approval on : 17 Dec 2021
Compliance Report Submitted by User Agency on : 05 Mar 2022
28 Jul 2022
27 Jammu and Kashmir FP/JK/ROAD/143629/2021 9-JKB-082/2021-Jammu Construction & Upgradation to 2 lane with paved shoulder from Design Km. 67.805 (at the end of Km 83rd tunnel near Dhrabshala) to Km 80.675 (Dulhasti) 12.87 Km length on Khellani-Kishtwar-Chattroo sec Road PMU KISHTWAR, NHIDCL 3.5183 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Jun 2021
Stage-I Approval on : 24 Jan 2022
Compliance Report Submitted by User Agency on : 20 Apr 2022
22 Jul 2022
28 Jammu and Kashmir FP/JK/Others/152416/2022 9-JKA-018/2022-Jammu HH-44 Realignment project-Diversion of 0.442 forest land for installation of Crusher plant, Batching plant, magazine, HSD Pump, Labour Hut Others CEIGALL INDIA LIMITED 0.442 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Feb 2022
Stage-I Approval on : 05 May 2022
Compliance Report Submitted by User Agency on : 31 May 2022
07 Jul 2022
29 Jammu and Kashmir FP/JK/QRY/50085/2020 9-JKA-067/2021-Jammu AGE Patel JV, USBRL Project T-15 & T-14 Quarrying M/S AGE PATEL JV 0.993 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Sep 2020
Stage-I Approval on : 16 Nov 2021
Compliance Report Submitted by User Agency on : 14 Mar 2022
26 May 2022
30 Jammu and Kashmir FP/JK/SCH/143125/2021 9-JKB-071/2021-Jammu Diversion of 3.54 Ha. of forest land for construction of Degree College Ramkot (Billawar) School DIRECTOR HIGHER EDUCATION DEPARTMENT 3.54 APPROVED
Proposal received(at Nodal Officer)electronically on : 05 Jun 2021
Stage-I Approval on : 02 Nov 2021
Compliance Report Submitted by User Agency on : 06 Apr 2022
26 May 2022
31 Jammu and Kashmir FP/JK/Others/141018/2021 9-JKB-053/2021-Jammu PAKAL DUL HYDRO ELECTRIC POWER PROJECT Others LARSEN & TOUBRO LIMITED HEAVY CIVIL INFRA IC 3.01 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Apr 2021
Stage-I Approval on : 05 Jan 2022
Compliance Report Submitted by User Agency on : 12 Feb 2022
23 Mar 2022
32 Jammu and Kashmir FP/JK/ROAD/48822/2020 9-JKB-013/2021-Jammu Construction of Project Goha - Khellani two lane with paved shoulder Km 12+850 to 20+300 (Design Length 7.45 km) in the union territory of Jammu and Kashmir Package-IA Road PMU KISHTWAR, NHIDCL 5.325 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Aug 2020
Stage-I Approval on : 25 Jun 2021
Compliance Report Submitted by User Agency on : 12 Aug 2021
09 Mar 2022
33 Jammu and Kashmir FP/JK/ROAD/47304/2020 9-JKC-18/2021-Jammu Diversion of 5.146 ha. Forest Land for Additional ROW Requirement for Development of Two Bridges located at Km- 2+250 to Km- 3+450 and Km- 10+100 to 10+560 of Chenani - Sudhmahadev Road (NH- 244) Road NHIDCL_JAMMU 5.146 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Jul 2020
Stage-I Approval on : 21 Jun 2021
Compliance Report Submitted by User Agency on : 24 Aug 2021
31 Jan 2022
34 Jammu and Kashmir FP/JK/ROAD/141548/2021 9-JKB-052/2021-JAMMU Construction of Road upto TRT outlet, Kwar HEP Kishtwar Road CVPP (P) L 2.4 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Apr 2021
Stage-I Approval on : 15 Jul 2021
Compliance Report Submitted by User Agency on : 12 Aug 2021
27 Jan 2022
35 Jammu and Kashmir FP/JK/ROAD/48999/2020 9-JKC002-2021-CHA Approach road with Avalanches Protection Works from Z-morh Tunnel East Portal to Zojila Tunnel West Portal in Ganderbal district of J&K Road NHIDCL PMU- SONAMARG 49.5904 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Aug 2020
Stage-I Approval on : 22 Feb 2021
Compliance Report Submitted by User Agency on : 26 Mar 2021
08 May 2021
36 Jammu and Kashmir FP/JK/ROAD/44916/2020 9-JKB501-2020-CHA Construction of Bi-directional tunnel at km 83 of length 495 m including approach road of 664 m and a Major Bridge of 110 m from km 82+675 to km 82+925 on NH – 244 in Jammu & Kashmir on EPC mode. Road PIU KHELLANI, NHIDCL 1.2 APPROVED
Proposal received(at Nodal Officer)electronically on : 05 Mar 2020
Stage-I Approval on : 13 Aug 2020
Compliance Report Submitted by User Agency on : 25 Sep 2020
01 Dec 2020
Please wait ...