PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : OR-0109/2016
1. Location of the project/Scheme : Orissa
 (i) State / Union Territory : Orissa  (ii) District : Sundargarh  (iii) Forest Division : Bonai  (iv) Area of forest land proposed for lease (in ha.) : 41.144  (v)

Category : Mining
2. Legal status of forest land proposed for lease
S. No. DivisionForest Land(ha.)Legal Status
1Bonai5.397Proposed Reserved Forests (Sec-4 of IFA)
2Bonai26.628Revenue Forest
3Bonai9.119District Level Committee (D.L.C.) Forest
Division 1. : Bonai
3. District wise area proposed for lease in the division
S. No. DistrictArea(ha.)
1Sundargarh41.144
4. Details of Vegetation available in the forest area
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
141.1440.6Eco 1


5. Specific working plan prescription for the forest land proposed for lease :
6. Brief note on vulnerability of the forest area to erosion :
7. Significance of the forest land proposed for lease from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for lease : Fox, Hare Wild Boar, Porcupine, Sloth Bear, Barking Deer, Jackal and different types of Snake and Birds are sometimes seen in the applied area.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for lease is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
8. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
9. Comment as to the reasonability of the extent of the forest land proposed for lease
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : NIL
10. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
11. Whether work in violation is still in progres(Yes/No) : NIL
12. Applicability of special provisions covering scheduled areas
 (i). Whether the project or a thereof is located in a scheduled area : Yes
13. Status of settlement of rights under the Forest Rights Act, 2006 on the forest land proposed for lease
 (i). Whether the process for settlement of rights under the Forest Rights Act, 2006 on the forest land proposed for lease has been completed : Yes
(ii). Upload the copy of FRA :
Additional information Details
S. No. DocumentsRemarks
1 Part-II DDFO, Bonai Division.

14. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
 Nodal OfficerNoNo Data
(Specific recommendation of the Nodal Officer with(Part II,III & Part IV))
15. Specific recommendation of the Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether Nodal Officer agreed
Nodal Officer Recommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
OrissaState SecretaryRecommended26/12/2016 recommended vide letter no 24167 dated 24.12.2016State Govt. OfficerNo Data
Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BhubaneswarHead Office07/07/2017No Data
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BhubaneswarHead Office07/07/2017No Data