  (i). Proposal No. : FP/RJ/TRANS/36179/2018   (ii). Name of Project for which Forest Land is required : Uprating work of 132 KV S/C Line sanwali road water works - ranoli (with dismantling of existing H-Pole)   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : PROPOSED UPRATING OF TRANSMISSION LINE IS TO ENHANCE THE CAPACITY OF EXISTING 132 KV S/C LINE FROM 132 KV GSS SANWALI ROAD,WATER WORKS TO RANOLI BY DISMANTLING THE EXISTING LINE   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 587.85   (viii). Area of forest land proposed for diversion(in ha.): 3.9836   (ix). Non-forest land required for this project(in ha.): 54.5281   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD SIKAR   (ii). Address1 : SE(T&C), RVPN, Sabalpura Power House, Sikar   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Sikar   (vi). Pin : 332001   (vii). Landmarks : NIL   (viii). Email address : xen.tnc.sikar@rvpn.co.in   (ix). Landline Telephone No. : 257120   (x). Fax No. : NIL   (xi). Mobile No. : 9413393933   (xii). Website (if any) : energy.rajasthan.gov.in/rvpnl   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1Approved13198F.1(82)forest/20150.1920.185627 Oct 201526 Oct 2015
2Approved24446f1(18)forest/20170.31320.313227 Mar 201717 Apr 2018
Total 0.5052 0.4988
  (xiv). Legal status of User Agency : State PSU
A-3. Details of Person Making Application
  (i). First Name: Jagdish   (ii). Middle Name: Prasad   (iii). Last Name: Khichar   (iv). Gender: Male   (v). Designation: XEN   (vi). Address 1: XEN, T N C, RVPN, Sabalpura Power House, Sikar   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Sikar   (x). Tehsil: NIL   (xi). Pin: 332001   (xii). Landmarks: NIL   (xiii). Email Address: xen.tnc.sikar@rvpn.co.in   (xiv). Landline Telephone No.: 257120   (xv). Fax No.: NIL   (xvi). Mobile No.: 9413393933   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Sikar Territorial3.983654.5281
Total3.983654.5281
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Sikar3.983654.5281
Total3.983654.5281
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1DEVIPURA3.28360
2SIKAR0.71.0394
3sanwali00.2
4khichron ka bass00.5
5gokulpura05.51
6Dasa ki dhani03
7Ramu ka bass05
8malkera04.2175
9bajor04.1359
10jujhara02.2
11kairliki dhani02.7
12goriyan03.2
13bhoja ki dhani02.4
14SUJAWAS01.5
15SHERPURA02.1
16jhari ki dhani01.8
17tliokpura01.65
18ranoli05.5
19shishu04.2
20akhepura03.6753
3.9836 54.5281
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1tower foundation aera0.03840.4544
2stringing aera1.331216.0056
3Remaning ROW2.61438.0681
Total 3.9836 54.5281
C. Maps of forest land proposed to be diverted
Division 1. : Sikar Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 3.9836   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.3.9836    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: No   (a). Reason for not providing such map: No alternate route proposed as it is uprating work
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 12   (iii). Temporary Employment(Number of person-days): 1440
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Revised village aera as per EDS 2
2Document Related to Line Establishment
3reply of EDS
4undertaking for cost of plantation
5Topo Sheet of Project (Part-2)
6UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE
7UNDERTAKING FOR NO CHANGES IN STATUTORY POSITION OF DIVERTED FOREST LAND
8UNDERTAKING FOR MINIMUM USE OF FOREST LAND
9UNDERTAKING FORCONSERVATION OF FLORA/FAUNA
10UNDERTAKING FOR MEDICINAL PLANT AMOUNT
11UNDERTAKING FOR PAYMENT OF ANY OTHER COST & CONDITION
12UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
13UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
14UNDERTAKING FOR USE OF FOREST LAND
15Details Of Permanent Employment To Be Generated
16tower drawing
17GAZETTE NOTIFICATION
18COMPLETE TOWER COORDINATE
19TOWER FOUNDATION OF PROJECT
20UNDERTAKING FOR TWO TIME DESEGREGATED OF FOREST LAND
21GOOGLE MAP (BEER DEVIPURA PF)
22GE0 REFERENCE GOOGLE MAP (BEER DEVIPURA PF)
23BAR CHART OF PROJECT
24UNDERTAKING TO PAY THE COST OF PLANTATION
25UNDERTAKING FOR MUCK DISPOSAL
26Geo. Reference Digitised Khasara Map Of Project
27SEGMENT WISE AREA CALCULATION SEET
28Khasarawise Breakup Of Forest Land
29Jamabandi of forest land
30Administrative Sanction
31UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING CONSTRUCTION OF TRANSMISSION LINE
32Village wise area calculation sheet
33reply of EDS-II
34undertaking for any hindrace/diffuclity
35reply of eds 3
36Reply of EDS of DCF
37reply of eds by DFO2
38forest land khasara suchi
39Reply of EDS by DFO
40reply of eds by dfo
41Reply of EDS Raised by Regional Office Lucknow
42Certificate regarding line establishment
43Administrative and Financial Sanction of Line
44NOC obtained from PHED department