FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UK/ROAD/36902/2018   (ii). Name of Project for which Forest Land is required : The Additional land requirement for land slide treatment and muck dumping for Rehabilitation and Upgradation to 2 lane with paved shoulder configuration from existing Km 122.00 (Dharasu Bend) to Km 147.230 (Silkyara Bend) Design chainage 0.00 to Km 24.30) of NH-94 in the state.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Additional land requirement for land slide treatment and muck dumping for this Project. Length of project is 24.300 Km and cost of 23780.00 Lacs. the approximate 8000 population benefited by this project.   (iv). State : Uttarakhand   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 23780   (viii). Area of forest land proposed for diversion(in ha.): 5.969   (ix). Non-forest land required for this project(in ha.): 0.449   (x). Total period for which the forest land is proposed to be diverted(in years): 100
A-2. Details of User Agency
  (i). Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS GOVT OF INDIA NEW DELHI   (ii). Address1 : office of the executive Engineer NH PWD Barkot Uttarakashi   (iii). Address2 : NIL   (iv). State : Uttarakhand   (v). District : Uttarkashi   (vi). Pin : 249141   (vii). Landmark : opp. SBI   (viii). Email address : eenhpwdbarkot.uk@gmail.com   (ix). Landline Telephone No. : 1375-224426   (x). Fax No. : 1375-   (xi). Mobile No. : 9997976809   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Central Government
A-3. Details of Person Making Application
  (i). First Name: Navneet   (ii). Middle Name: NIL   (iii). Last Name: Pandey   (iv). Gender: Male   (v). Designation: executiveengineer   (vi). Address 1: office of the executive Engineer NH PWD Barkot   (vii). Address 2: NIL   (viii). State: Uttarakhand   (ix). District: Uttarkashi   (x). Tehsil: Badkot   (xi). Pin: 249141   (xii). Landmark: opp. SBI   (xiii). Email Address: eenhpwdbarkot.uk@gmail.com   (xiv). Landline Telephone No.: 1737-224426   (xv). Fax No.: NIL   (xvi). Mobile No.: 9997976809   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Uttarkashi5.9690.449
Total5.9690.449
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Uttarkashi5.9690.449
Total5.9690.449
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Dharsu Campartment 2 (Sliding Zone)1.20
2Dharsu Campartment 2,3 (Sliding Zone)1.50
3Dharsu Campartment 3 (Sliding Zone)1.50
4Dharsu Campartment 3 (Kodafadi)1.2180
5kumrada khadd (gewala)0.4080.142
6kumrada khadd (gewala.)0.1430.307
Total 5.969 0.449
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Road00
2Dumping/ Protection wrok5.9690.449
Total 5.969 0.449
C. Maps of forest land proposed to be diverted
Division 1. : Uttarkashi
  (i). Area of forest land proposed to be diverted(in ha.) : 5.969   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.5.969    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: No   (a). Reason for not providing such map: in this stretch we need only extra dumping zone fo
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 93600
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1Cover Page
2Index
3Authority Letter
4Report
5Government Order
6Complete Details of Project Parpatra -1 Part 1 to 5
7Joint Inspection Report
8Digital Map
9Tree Information and Tree Counting of eficative this project
10Land Schedule
11details of Effective Tree for cutting
12certificate Given by Executive Engineer not cutting Baang Tree
13Topo Sheet
14Digital Map
15Geo Map
16Poligen Mapn
17Tree Plantation Cost
18Utilization Certificate
19Bar Chart
20CA Certificate
21Certificate regarding plantation
22NOC given by garam sabha
23Length and width certificate
24alignment rejection certificate
25work not started certificate
26Geological Report
27Task Force Report
28certificate of not disturb animal
29certificate not suitable other land
30No Religious place
31habitation benefit certificate
32other certificates related project
33NPV
34Cost Benefit
35Muck Disposal
36Terms and conditions
37EDS Quarry ans given by Executive Engineer on dated 14-11-2018
38aerial distance certificate
39FRA
40Justification Cerificate
41village commettee kodakhadi
42village commettee Kumarada
43village commettee Gewala
44Answer of EDS quarry on dt.30.09.2019
45Ans of Quarry Letter on dated 02-01-2019
46EDS Quarry ans given by Executive Engineer on dated 22.11.19
47EDS Quarry ans given by Executive Engineer on dated 17.02.2020
48Ans of EDS Quarry dated 25-05-2019
49EDS quarry ans on dt 02/07/19
50Detail of project already submitted Proposal No. FP/UK/ROAD/24549/2017 Stage-I approval 22-09- 2017 and stage-II approval awaited.
51EDS Quarry ans given by Executive Engineer on dated 30-01-2020
52R.C.C Pillar
53Other Important Certificates
54justification for providing project in forest land