FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/37354/2018   (ii). Name of Project for which Forest Land is required : Construction of 220 kV D/C Gajner -Chhatargarh Transmission Line, District - Bikaner, Rajasthan".   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 220 kV D/C Gajner -Chhatargarh Line is essential for evacuation of RE power and to enhance reliability & stability of power supply in the area.   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 4830   (viii). Area of forest land proposed for diversion(in ha.): 8.8422   (ix). Non-forest land required for this project(in ha.): 280.6778   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD BIKANER   (ii). Address1 : 66 KV GSS Premises, Sagar Road, Bikaner   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Bikaner   (vi). Pin : 334001   (vii). Landmark : Nera Sangalpura Bus Stand   (viii). Email address : se.tnc.bkn@rvpn.co.in   (ix). Landline Telephone No. : 151-2226270   (x). Fax No. : 151-   (xi). Mobile No. : 9414061002   (xii). Website (if any) : energy.rajasthan.gov.in/rvpnl   (xiii). Legal status of User Agency : State PSU
A-3. Details of Person Making Application
  (i). First Name: Ajay   (ii). Middle Name: Kumar   (iii). Last Name: Malhotra   (iv). Gender: Male   (v). Designation: XEN   (vi). Address 1: 66 KV GSS Premises, Sagar Road, Bikaner   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Bikaner   (x). Tehsil: NIL   (xi). Pin: 334001   (xii). Landmark: Near Sangalpura Bus Stand   (xiii). Email Address: xen.cm.bikaner@gmail.com   (xiv). Landline Telephone No.: 151-2226272   (xv). Fax No.: NIL   (xvi). Mobile No.: 9414061376   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1ApprovedFP/RJ/TRANS/12376/20158B/RJ/04/44/2015/F.C./41922.398322.398323 Aug 201617 Sep 2018
2InprincipleFP/RJ/TRANS/19489/20168B/RJ/04/08/2017/F.C./23435.429135.429128 Aug 2017
3InprincipleFP/RJ/TRANS/22004/20168B/RJ/04/09/2017/F.C./24116.4816.4830 Aug 2017
Total 74.3074 74.3074
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bikaner Territorial0.070254.4868
2.DCF STII BIKANER1.3322160.9393
3.Chhatargarh Territorial7.439865.2517
Total8.8422280.6778
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bikaner8.8422280.6778
Total8.8422280.6778
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Gajner0.070214.1788
2Sharah Bhiyanimani011.777
3Jaimalsar1.332244.5205
4Kawni040.5378
5Bandarewala012.425
6Karnisar Bhatiyan031.514
7Sardarpura020.79
8Moti Garh035.1225
9Satasar040.292
103 A W M0.0920
112 A W M0.0940
122 C H M0.70160
131 C H M0.35020
14Chhattargarh6.20229.5202
Total 8.8422 280.6778
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower Foundation Area0.998.1
2Stringing Area4.3623151.4321
3Remaining ROW3.4899121.1456
Total 8.8422 280.6777
C. Maps of forest land proposed to be diverted
Division 1. : Chhatargarh Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 7.4398   (ii). Nature of the Project: Linear   (b). No. of Segments : Three
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.1.0518    View File
2.0.186    View File
3.6.202    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Bikaner Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 0.0702   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.0702    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 3. : DCF STII BIKANER
  (i). Area of forest land proposed to be diverted(in ha.) : 1.3322   (ii). Nature of the Project: Linear   (b). No. of Segments : Three
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.3506    View File
2.0.1778    View File
3.0.8038    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 17   (iii). Temporary Employment(Number of person-days): 25000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Administrative and Financial Sanction.
2Notification 220 kV Gajner Chhattargarh Tr Line.
3Tower and Tower Foundation Drawing 220 kv.
4NOC BRO.
5NOC IGNP.
6NOC PWD.
7Khasra Map and Jamabandi.
8EDS Reply Letter dated 08.01.2019
9CERTIFICATE FOR MINIMUM USE OF FOREST LAND.
10TWO TIME DEGRADED FOREST LAND UNDERTAKING.
11UNDERTAKING FOR CONSERVATION OF FLORA FAUNA DURING TRANSMISSION LINE.
12UNDERTAKING FOR FRA CERTIFICATE.
13Undertaking for Muck Disposal Plan.
14UNDERTAKING FOR NO CHANGES IN STATUTORY POSITION OF DIVERTED FOREST LAND.
15UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE.
16UNDERTAKING FOR PAYMENT OF ANY OTHER COST AND CONDITION.
17UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION.
18Undertaking for Payment of Cost of Medicinal Plant under Transmission line.
19UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF Forest Land.
20UNDERTAKING FOR SUBMISSION OF MISSING OR REQUIRED ADDITIONAL DOCUMENTS.
21Undertaking for Use of Any Material From Forest Land.
22UNDERTAKING FOR USE OF FOREST LAND.
23Undertaking to Pay the Cost of Plantation.
24Details of Permanent Employment to be generated.
25COMPLETE ALIGNMENT TOWER COORDINATES.
26Component Wise Area Calculation Sheet.
27Division wise Village location sheet.
28Village Wise Area Calculation Sheet.
29Segment wise Area Calculation Sheet.
30Bar chart Status.
31Georeferenced Digital Map with Coordinates Bikaner Territorial (Segment 1)
32Georeferenced Digital Map with Coordinates DCF STII Bikaner (Segment 2_3_4)
33Georeferenced Digital Map with Coordinates Chhatargarh Territorial (Segment 5_6_7).
34Georeferenced Digital Map Total Alignment 50000 scale.
35Georeferenced Toposheet Map Total Alignment 50000 scale.
36Alternative Route Map and Route Analysis.