FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/35469/2018   (ii). Name of Project for which Forest Land is required : Construction of Lilo from 132 KV S/C Aklera-Manohar Thana Line at Proposed 220 kv GSS Aklera   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : LILO from 132 KV S/C Aklera-Manohar Thana Line to Proposed 220 kV GSS Aklera will facilitate 132 kV interconnections at 220 kV Aklera GSS and feed load of Aklera & Manohar Thana   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 2.7124   (viii). Area of forest land proposed for diversion(in ha.): 2.241   (ix). Non-forest land required for this project(in ha.): 22.14   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD KOTA   (ii). Address1 : SE(T&C), RVPN, SAKATPURA, KOTA   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Kota   (vi). Pin : 324006   (vii). Landmark : NIL   (viii). Email address : se.tnc.kota@rvpn.co.in   (ix). Landline Telephone No. : 744-2370084   (x). Fax No. : 744-   (xi). Mobile No. : 9413382702   (xii). Website (if any) : energy.rajasthan.gov.in/rvpnl   (xiii). Legal status of User Agency : State PSU
A-3. Details of Person Making Application
  (i). First Name: Rajendra   (ii). Middle Name: Kumar   (iii). Last Name: Chawla   (iv). Gender: Male   (v). Designation: XEN   (vi). Address 1: Executive Engineer T and C, RVPN, Sakatpura, Kota   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Kota   (x). Tehsil: NIL   (xi). Pin: 324006   (xii). Landmark: NIL   (xiii). Email Address: xen.tnc.kota@rvpn.co.in   (xiv). Landline Telephone No.: 744-2370086   (xv). Fax No.: NIL   (xvi). Mobile No.: 9414061465   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/RAJ/TRANS/19845/20168B/RJ/04/03/2017/FC3.9423.94230 Mar 2017
2ApprovedFP/RJ/TRANS/18259/20168B/RAJ/04/7/2017/FC19.743219.743228 Jul 201715 Feb 2018
Total 23.6852 23.6852
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Jhalawar Territorial2.24122.14
Total2.24122.14
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Jhalawar2.24122.14
Total2.24122.14
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Lapsiya02.943
2Khanpuriya03.8718
3Binda03.105
4Ugani01.215
5Ugena01.89
6Devri kalan2.2410
7Devri khurd04.86
8Kotra04.2552
Total 2.241 22.14
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower Foundation Area0.01080.108
2Stringing Area0.57025.632
3Remaining ROW Area1.6616.4
Total 2.241 22.14
C. Maps of forest land proposed to be diverted
Division 1. : Jhalawar Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 2.241   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.2.241    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 12   (iii). Temporary Employment(Number of person-days): 1600
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1COMPARATIVE STATEMENT OF ALTERNATIVE ROUTE
2Foundation Drawing
3Tower Drawing
4UNDERTAKING FOR NO CHANGE S IN STATUTORY POSITION OF DIVERTED FOREST LAND
5ADMINISTRATIVE AND FINANCIAL SANCTION
6DIGITAL MAP SHOWING FOR REQUIRED FOREST LAND COORDINATE AND PROPOSED 132 KV D/C TRANSMISSION LINE ALINGNMENT
7GOOGLE IMAGERY MAP SHOWING FOR FOREST BOUNDARY AND PROPOSED 132 KV D/C TRANSMISSION LINE ALINGNMENT
8Alternative Digital Map
9UNDERTAKING FOR FRA CERTIFICATE
10Joint inspection report
11Eds Reply letter
12Reply Letter 24.10.2018
13Gazette Notification
14Jamabandi copy
15Khasra Map
16CERTIFICATE FOR MINIMUM USE OF FOREST LAND
17UNDERTAKING FOR CONSERVATION OF FLORA-FAUNA DURING CONSTRUCTION OF TRANSMISSION LINE
18UNDERTAKING FOR MEDICIANAL PLANTS
19UNDERTAKING FOR MUCK DISPOSAL
20UNDERTAKING FOR PAYMENT OF ANY OTHER COST & CONDITION
21UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
22UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
23UNDERTAKING FOR TWO TIME DEGRADED FOREST LAND
24UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING CONSTRUCTION OF TRANSMISSION LINE
25UNDERTAKING FOR USE OF FOREST LAND
26Village Wise area calculation sheet
27BAR CHART
28Complete Tower Location Coordinates
29Component Wise Area Calculation Sheet
30Forest Land Khasra List Village Devri Kalan
31Segment Wise Area Calculation Sheet
32MAP SHOWING FOR GEO-REFERENCED SURVEY OF INDIAT TOPOSHEET WITH FOREST BOUNDARY AND PROPOSED 132 KV D/C TRANSMISSION LINE ALINGNMENT SCALE 1:50,000
33Alternative Google Map
34Authorization letter
35Copy of gram sabha meeting for FRA
36Employment Justification
37Alternative Toposheet Map SCALE 1:50000
38MAP SHOWING FOR REVENUE KHASRA MAP WITH PROPOSED 132 KV TRANSMISSION LINE ALINGNMENT
39Zoomed Digital Map For required forest land coordinate and proposed Alignment
40EDS REPLY LETTER-11-02-2019
41CA topo sheet
42EDS Reply 21.08.19
43Submitted the 2 more hard copy of proposal in DCF Office on Date 02.11.2018
44Work order 132KV line
45Hard copy Slip
46EDS Reply 08.11.2019
47Work order 220KV line
48AUTHORIZATION CERTIFICATE RAJEEV KUMAR
49EDS REPLY LETTER -03-12-2018
5019.02.2019 EDS reply
51EDS REPLY 26-02-2019
52eds reply 132 aklera 10-05-2019