FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/22004/2016   (ii). Name of Project for which Forest Land is required : 132 KV S/C Chattargarh – Khajuwala Transmission Line”   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To meet out the load growth in the area and improve the existing system parameters it is proposed to create a 132 KV GSS at Chhatargarh of capacity 20/25 MVA which is at the load centre, by laying 50 Km 132 KV S/C line from Khajuwala to Proposed 132 KV GSS at Chhattargarh.   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 804   (viii). Area of forest land proposed for diversion(in ha.): 16.48   (ix). Non-forest land required for this project(in ha.): 120.45   (x). Total period for which the forest land is proposed to be diverted(in years): 35
A-2. Details of User Agency
  (i). Name : RAJASTHAN RAJYA VIDHYUT PRASARAN NIGAM   (ii). Address1 : VIDHYUT BHAWAN, JAN PATH, JYOTI NAGAR, JAIPUR   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Jaipur   (vi). Pin : 302005   (vii). Landmark : VIDHYUT BHAWAN   (viii). Email address : xen_220_nimbahera@rvpn.co.in   (ix). Landline Telephone No. : 1477-220084   (x). Fax No. : 1477-0   (xi). Mobile No. : 9413382269   (xii). Website (if any) : www.rvpn.co.in   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Ajay   (ii). Middle Name: Kumar   (iii). Last Name: Malhotra   (iv). Gender: Male   (v). Designation: Executive Engineer   (vi). Address 1: 66 KV GSS Campus Sagar Road Bikaner   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Bikaner   (x). Tehsil: Bikaner   (xi). Pin: 334001   (xii). Landmark: 66 KV GSS   (xiii). Email Address: guptivivek@gmail.com   (xiv). Landline Telephone No.: 151-2226272   (xv). Fax No.: 01512226270   (xvi). Mobile No.: 9414061376   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1ReturnedFP/RJ/TRANS/7145/20142.210
2Under Processing in MoEFFP/RJ/TRANS/1686/201280
3Under Processing in MoEFFP/RJ/TRANS/1677/201235.3610
4Under Processing at State GovernmentFP/RJ/TRANS/1443/20110.54740
5Under Processing in MoEFFP/RJ/TRANS/4124/20131.63841.638403 Mar 2014
6Under Processing in MoEFFP/RJ/TRANS/1686/20128B/RAJ/04/17/2012/FC27.90
7WithdrawnRJ/FP/TRANS/8305/2014RJ-035/201514.8430
8Under Processing at State GovernmentFP/RJ/TRANS/19489/201635.42910
Total 125.9289 1.6384
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chhatargarh Territorial16.48120.45
Total16.48120.45
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bikaner16.48120.45
Total16.48120.45
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Awa0.29161.35
2Lunkha2.31124.65
3Nawabwali0.8512
4Masjidawali5.75114.45
5Beriyanwali3.469419.35
6CHHATARGARH3.80748.65
Total 16.48 120.45
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Chhatargarh Forest Block3.80748.6486
2Awa Minor0.29161.35
3Lunkha Distributory & Forest Block2.3109324.6483
4Nawabwali Forest Block0.8499611.9961
5Masjidawali Forest Block5.75114.44986
6Berriyanwali Forest Block3.4692319.34982
Total 16.47972 120.44268
C. Maps of forest land proposed to be diverted
Division 1. : Chhatargarh Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 16.48   (ii). Nature of the Project: Linear   (b). No. of Segments : Nine
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.3.807    View File
2.0.135    View File
3.0.1566    View File
4.0.27    View File
5.2.041    View File
6.0.85    View File
7.0.6291    View File
8.5.1219    View File
9.3.4694    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 600
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Project report.
2Undertaking for NOC of Canal Authorities.
3khasa Map and jamabandi.
4Undertaking for PWD-BRO NOC.
5Undertaking for Muck Disposal Plan.
6Tower Coordinates of Complete Transmission Line.
7Undertaking for Crossing of Notified Roads Under FCA Act 1980.
8Compliance Report.
9Component wise forest and non forest land
10Segment wise forest land calculation
11Mendatory strips for IGNP canals
12Revenue Maps of land
13Reply of EDS
14BAR CHART
15ALTERNATIVE ROUTE MAP
16DGPS MAP
17KML PDF
18GT SHEET MAP
19Revised segment wise calculation
20Undertaking for CA cost
21Reply of EDS of MOEFCC
22Area Calculation Sheet.
23FRA Chhattargarh Khajuwala Tr Line.
24Alternative Route Analysis report.
25Alternative Route KML File.
26Authorisation Letter.
27Technical and Financial Sanction.
28COST BENEFIT ANALYSIS REPORT.
29JUSTIFICATION FOR LOCATING PROJECT IN FOREST AREA.
30UNDERTAKING FOR USE OF ANY MATERIAL FROM FOREST LAND.
31UNDERTAKING FOR CONSERVATION OF FLORA FAUNA DURING TRANSMISSION LINE.
32UNDERTAKING FOR NO CHANGE’S IN STATUTORY POSITION OF DIVERTED FOREST LAND.
33UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE AND DIVERSION OF MINIMUM FOREST LAND.
34UNDERTAKING FOR PAYMENT OF ANY OTHER COST AND CONDITION.
35UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA.
36UNDERTAKING FOR USE OF FOREST LAND.
37NOC canal crossing
38Cost benifit analysis
39UNDERTAKING FOR WASTE MANAGEMENT.
40UNDERTAKING FOR TWO TIME DEGRADED FOREST LAND.
41UNDERTAKING FOR FRA CERTIFICATE.