FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/19489/2016   (ii). Name of Project for which Forest Land is required : 132 KV S/C Nokha Daiya- Khajuwala Tr LINE   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Transmission Line between Nokha Daiya and Khajuwala is rquird to strengthn the system reliability of Transmission network in West Rajathan.   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 925   (viii). Area of forest land proposed for diversion(in ha.): 35.4291   (ix). Non-forest land required for this project(in ha.): 183.2386   (x). Total period for which the forest land is proposed to be diverted(in years): 35
A-2. Details of User Agency
  (i). Name : RAJASTHAN RAJYA VIDHYUT PRASARAN NIGAM   (ii). Address1 : VIDHYUT BHAWAN, JAN PATH, JYOTI NAGAR, JAIPUR   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Jaipur   (vi). Pin : 302005   (vii). Landmark : VIDHYUT BHAWAN   (viii). Email address : xen_220_nimbahera@rvpn.co.in   (ix). Landline Telephone No. : 1477-220084   (x). Fax No. : 1477-0   (xi). Mobile No. : 9413382269   (xii). Website (if any) : www.rvpn.co.in   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Ajay   (ii). Middle Name: Kumar   (iii). Last Name: Malhotra   (iv). Gender: Male   (v). Designation: Executive Engineer   (vi). Address 1: 66 KV GSS Campus Sagar Road Bikaner   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Bikaner   (x). Tehsil: Bikaner   (xi). Pin: 334001   (xii). Landmark: 66 KV GSS   (xiii). Email Address: guptivivek@gmail.com   (xiv). Landline Telephone No.: 151-2226272   (xv). Fax No.: 01512226270   (xvi). Mobile No.: 9414061376   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1ReturnedFP/RJ/TRANS/7145/20142.210
2Under Processing in MoEFFP/RJ/TRANS/1686/201280
3Under Processing in MoEFFP/RJ/TRANS/1677/201235.3610
4Under Processing at State GovernmentFP/RJ/TRANS/1443/20110.54740
5Under Processing in MoEFFP/RJ/TRANS/4124/20131.63841.638403 Mar 2014
6Under Processing in MoEFFP/RJ/TRANS/1686/20128B/RAJ/04/17/2012/FC27.90
7WithdrawnRJ/FP/TRANS/8305/2014RJ-035/201514.8430
8Under Processing at State GovernmentFP/RJ/TRANS/19489/201635.42910
Total 125.9289 1.6384
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.DCF STII BIKANER6.0589146.8745
2.Chhatargarh Territorial29.370236.3641
Total35.4291183.2386
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bikaner35.4291183.2386
Total35.4291183.2386
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Nokha Daiya016.3647
2Chilan09.531
3Bhanipura0.640529.0055
4Amarpura07.5168
5Ramsar2.463122.9169
6Gogliwala014.7798
7Chhagoliya09.423
8Pugal2.680727.1651
9Phelwan Ka bera2.302214.5728
102BLD5.25623.5242
116PB8.617110.4935
12Madhodigi11.08599.8796
13Beriyanwala2.38338.0657
Total 35.429 183.2386
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Forest patches35.429076183.23766
Total 35.429076 183.23766
C. Maps of forest land proposed to be diverted
Division 1. : Chhatargarh Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 29.3702   (ii). Nature of the Project: Linear   (b). No. of Segments : Nine
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.2.0276    View File
2.0.387    View File
3.2.3986    View File
4.2.3896    View File
5.0.081    View File
6.8.3235    View File
7.0.2936    View File
8.11.0859    View File
9.2.3833    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : DCF STII BIKANER
  (i). Area of forest land proposed to be diverted(in ha.) : 6.0589   (ii). Nature of the Project: Linear   (b). No. of Segments : Ten
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.16    View File
2.0.4805    View File
3.0.1447    View File
4.1.7311    View File
5.0.5873    View File
6.0.287    View File
7.0.081No Data
8.2.1332    View File
9.0.1795    View File
10.0.27460
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 8   (iii). Temporary Employment(Number of person-days): 18250
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Bar Chart
2Project Report
3Undertaking certificate
4Tree Details
5Alternate Route Analysys
6Revenue Map
7Guzette Notification
8Tower Drawings
9Tower Foundation Drawings
10Jamabandi
11Geo reference Map
12Undrtaking FRA
13Annexure D2
14Annexure D1
15Annexure D3
16Annexure D4
17Annexure D5
18Annexure D6
19Annexure D7
20Form A Part-1
21NOC CANAL CROSSING
22NOC ROAD CROSSING
23DFO WISE DETAILS OF FOREST AREA
24DFO WISE DETAILS OF NON FOREST AREA
25DISTRICT WISE DETAILS OF NON FOREST AREA
26SEGMENT WISE DETAILS OF FOREST AREA
27VILLAGE WISE DETAILS OF FOREST AREA
28VILLAGE WISE DETAILS OF NON FOREST AREA
29Revised NOC of Road crossing
30PDF of KML of alternative routes
31Revise Authority Letter
32Revise Geo Reference map
33NEW Guzette Notification of forest area
34Reply EDS
35Revised Cost Benefit Analysis
36Revised FRA with Annextures