FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/OR/THE/29588/2017   (ii). Name of Project for which Forest Land is required : 3x800 MW Super Critical Thermal Power Plant at Kamakhyanagar Tahasil in Dhenkanal District   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for establishment of 3x800 MW Super Critical Thermal Power Plant   (iv). State : Orissa   (v). Category of the Proposal : Thermal   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 1821800   (viii). Area of forest land proposed for diversion(in ha.): 38.098   (ix). Non-forest land required for this project(in ha.): 542.7831   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : ODISHA THERMAL POWER CORPORATION LTD (OTPCL)   (ii). Address1 : 3rd Floor, SetuBhawan, OBCC Building, Nayapally   (iii). Address2 : Bhubaneswar   (iv). State : Orissa   (v). District : Khordha   (vi). Pin : 751012   (vii). Landmark : Near CA/ICMA Bhawan Nayapally   (viii). Email address : otpcl@hotmail.com   (ix). Landline Telephone No. : 674-2390731   (x). Fax No. : 674-2390732   (xi). Mobile No. : 9437145887   (xii). Website (if any) : www.otpcl.com   (xiii). Legal status of User Agency : State PSU
A-3. Details of Person Making Application
  (i). First Name: Bhabani   (ii). Middle Name: Sankar   (iii). Last Name: Panda   (iv). Gender: Male   (v). Designation: CEO   (vi). Address 1: 3rd Floor, SetuBhawan, OBCC Building, Nayapally   (vii). Address 2: Bhubaneswar   (viii). State: Orissa   (ix). District: Khordha   (x). Tehsil: Saheednagar   (xi). Pin: 751012   (xii). Landmark: Near CA/ICMA Bhawan Nayapally   (xiii). Email Address: otpcl@hotmail.com   (xiv). Landline Telephone No.: 674-2390731   (xv). Fax No.: 06742390732   (xvi). Mobile No.: 9437145887   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dhenkanal38.098542.7831
Total38.098542.7831
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dhenkanal38.098542.7831
Total38.098542.7831
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Annapurnapur Khamar16.3942252.9563
2Dhobabaheli0.14983.3428
3Kusumajodi4.815993.4156
4Kanatapal0.34419.0854
5Analabereni048.1384
6Aluajharan2.8530.6273
7kateni13.5411125.2173
Total 38.098 542.7831
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Steam Generator & Auxiliaries019.242
2Chimney03.447
3Switch Yard028.242
4Ash Handling System & F.G.D03.05
5Water Treatment System07.369
6Cooling Water System0.30420.452
7Coal System, MGR & Water Reservoir0.82683.413
8Rain Water Harvesting Pond01.742
9Fire Station/Security03.118
10Green Belt14.4881.068
11Misc BOP facilities, stores & Roads014.749
12Ash pond and Ash water recycling system19.195169.491
13Raw water Corridor2.10426.945
14Ash slurry & water corridor0.72813.371
15R & R Colony (A)09.47
16Enabling area for Misc Facilities0.4610.996
17Township048.138
183 x 800 MW STG Building & Tr. Yard08.48
Total 38.098 542.783
C. Maps of forest land proposed to be diverted
Division 1. : Dhenkanal
  (i). Area of forest land proposed to be diverted(in ha.) : 38.098   (ii). Nature of the Project: Non Linear   (a). No. of patches : One
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of PatchesTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.38.098    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 1000   (iii). Temporary Employment(Number of person-days): 3000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: Yes   (a). Total Number of families : 89   (b). Number of Scheduled Caste families : 11   (c). Number of Schedule Tribes families : NIL   (d). Number of other families : 78   (ii). Copy of Rehabilitation and Resettlement Plan:   (a). Copy of approval to Ministry of Tribal Affairs,Government of India to Rehabilitation and Resettlement:
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes   (a). Status of the Environmental Clearance to the Project: EC application yet to be submitted
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Yes   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Yes   (a). Reason Category: Other reason   (b). Provide reasons thereof: Remaining 4.128 Ha of no forest land is identified   (c). Area of non-forest or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation (in ha.): 33.97   (iii). No. of districts involved for raising Compensatory Afforestation: 1   (iv). No. of patches: Four
District 1. : Dhenkanal
  (a). Village: Kantakhola, Jogidiha, Kateni   (b). Area(in ha.): 33.77   (c). Copy of KML file of the patch:     View File   (d). Khasra details: plot no476,481,487,532,3 Khata no69,148,834Kissam Patharabani,Pahad-2,Parabt-1   (e). Present owner: Others   (f). Copy of ownership proof:   (g). Copy of Mou/agreement executed between the Present owner and the User Agency:   (h). Copy of non encumberence certificate for the forest land:
  (v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:   (vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No Documents
Remarks
1Undertaking for FRA
2TOR Letter
3undertaking for remaining 4.128 ha of non forest land for CA.
4EDS Compliance letter