FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/TRANS/40694/2019   (ii). Name of Project for which Forest Land is required : 400 kV D/C North Karanpura to Chandwa Transmission Line   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Ministry of Power, Govt. of India has initiated a scheme for establishment of Transmission System for “Immediate Evacuation for North Karanpura (3X660MW) generation project of M/s NTPC North Karanpura. As a part of the said project a SPV is formed to develop the proposed project.   (iv). State : Jharkhand   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 10400   (viii). Area of forest land proposed for diversion(in ha.): 56.3254   (ix). Non-forest land required for this project(in ha.): 118.7874   (x). Total period for which the forest land is proposed to be diverted(in years): 35
A-2. Details of User Agency
  (i). Name : NORTH KARANPURA TRANSCO LIMITED   (ii). Address1 : Sunita Sadan 1st Floor Ashram Marg Bariatu Near Military Firing Range   (iii). Address2 : NIL   (iv). State : Jharkhand   (v). District : Ranchi   (vi). Pin : 834009   (vii). Landmark : NEAR MILITARY FIRING RANGE   (viii). Email address : northkaranpuratransco@gmail.com   (ix). Landline Telephone No. : 79-25559476   (x). Fax No. : 79-   (xi). Mobile No. : 7808958161   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: CHANDRA   (ii). Middle Name: SHEKHAR   (iii). Last Name: SINGH   (iv). Gender: Male   (v). Designation: ASSISTANTMANAGER   (vi). Address 1: Sunita Sadan 1st Floor Ashram Marg Bariatu Near Military Firing Range   (vii). Address 2: NIL   (viii). State: Jharkhand   (ix). District: Ranchi   (x). Tehsil: NIL   (xi). Pin: 834009   (xii). Landmark: NEAR MILITARY FIRING RANGE   (xiii). Email Address: northkaranpuratransco@gmail.com   (xiv). Landline Telephone No.: 79-25559476   (xv). Fax No.: NIL   (xvi). Mobile No.: 7808958161   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/JH/TRANS/40694/2019FP/JH/TRANS/40694/201956.325456.325417 Jan 2022
Total 56.3254 56.3254
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chatra South27.841315.9897
2.Latehar28.4841102.7977
Total56.3254118.7874
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chatra27.841315.9897
1.Latehar28.4841102.7977
Total56.3254118.7874
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1TANDWA06.691
2KAMTA4.38873.0393
3RAHAM0.69431.2854
4MASILAUNG4.86292.5322
5SARADHU10.94161.2067
6DEVALGARA0.00690.4487
7KUNDI4.03870.7864
8KURLAONGA2.90820
9ARA1.03083.9393
10CHAMATU0.00794.6134
11PHULBASIYA AMARWADIH3.769110.1582
12CHETAR3.08265.6575
13SEREGARA09.199
14NAGARA03.9811
15PUNDURLAWA1.24456.6381
16JARRI03.88
17BASIYA2.184313.6045
18GERENJA1.17022.2659
19JOGIADIH1.07842.7498
20SEMARSOT1.339.3591
21HEMPUR0.49724.4631
22MURGAON2.22636.6985
23CHITARPUR4.51220.9876
24NAGAR5.07310.003
25CHATRO00.261
26ANGARA0.57410.9462
27AMBADOHAR0.70353.3924
Total 56.3254 118.7874
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1TOWER FOUNDATION3.37598.6031
2STRINGING27.812259.7443
3REMAINING ROW25.137350.44
Total 56.3254 118.7874
C. Maps of forest land proposed to be diverted
Division 1. : Latehar
  (i). Area of forest land proposed to be diverted(in ha.) : 28.4841   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.28.4841    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Chatra South
  (i). Area of forest land proposed to be diverted(in ha.) : 27.8413   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.27.8413    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 68   (iii). Temporary Employment(Number of person-days): 385000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Company Incorporation Certificate
2Section 68 Approval
3Transmission Licence
4Project Report
5ARCHAEOLOGICAL IMPORTANCE
6COST OF FELLING TREE
7MINIMUM TREE FELL
8NOT PASSING THROUGH ANY PROTECTED WILDLIFE SANCTUARY , ECO SENSITIVE ZONE, NATIONAL PARK AND BIOSPHERE RESERVE
9UNDERTAKING FOR MUCK DISPOSAL
10UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE & DIVERSION OF MINIMUM FOREST LAND
11UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING CONSTRUCTION OF TRANSMISSION LINE
12Angle tower COORDINATES
13EMPLOYMENT GENERATION
14UNDERTAKING OF FRA CERTIFICATE
15CO Report Tandwa
16CO Report Chandwa
17Bar Chart
18CO report Bariyatu and Balumath Block
19SPV FORMATION INFORMATION MOA AOA NKTL
20Replies to EDS raise by nodal office
21Chatra South Forest Division_GM JJ Land Schedule
22Chatra South Forest Division_PF Land Schedule
23Replies to EDS raise by nodal office
24Acknowledgement Chatra South division
25DGPS report
26Cadastral Maps Chatra
27Cadastral Maps Latehar
28CHATRA SOUTH DIVISION AREA STATEMENT
29COMPONENT WISE AREA
30VILLAGE WISE AREA STATEMENT
31FRA -GMJJ LETTER CHATRA DISTRICT
32FRA LETTER LATEHAR DISTRICT
33JUNGLE JHARI NOC LETTER LATEHAR DISTRICT
34LETTER NON FOREST CERTIFICATE LATEHAR DISTRICT
35submission letter dfo chatra south
36submission letter dfo latehar division
37Latehar Division Area statement
38Latehar Division PF area
39submission letter to dfo latehar
40Replies to EDS raise by DFO Chatra South
41Replies to EDS raise by DFO Chatra South
42Replies to EDS raise by DFO Latehar
43CERTIFICATE FOR MINIMUM USE OF FOREST LAND
44Compliance to DFO Chatra South
45CONSENT LETTER FOR NET PRESENT VALUE
46UNDERTAKING FOR COMPENSATORY AFFORESTATION (CA)
47Form A -Part 1 Chatra South Division
48Form A- Part 1 Latehar Division
49Tree details chatra south
50Tree details chatra south
51Tree details chatra south
52Tree details chatra south
53Tree details chatra south
54Tree details chatra south
55Tree details chatra south
56Tree details chatra south
57Tree details chatra south
58Tree details chatra south
59Annexure 3- Justification of forest land
60Annexure 4- CCL NoC NKTL
61Annexure 4- MOU - CCL to NKTL
62FRA proceeding and Ghram Shabha Chatra district - PART1
63FRA proceeding and Ghram Shabha Chatra district - PART2
64FRA proceeding and Ghram Shabha Latehar district- PART1
65FRA proceeding and Ghram Shabha Latehar district- PART 2
66Submission EDS reply to DFO Latehar on 01-11-2021
67Annexure 1- Undertaking for tree cutting
68GM JJ NOC Chatra District
69GM JJ NOC Latehar District
70EDS Reply for NKC-CHATRA 24-11-2021
71Annexure 5- Maintaining 25 feet height at Maximum Sagging Point-Wildlife Management and Soil Conservation Measure