FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/RAIL/30545/2017   (ii). Name of Project for which Forest Land is required : MOHANPUR-HANSDIHA NEW BG RAIL LINE   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of new BG Rail line between Mohanpur to Hansdiha.   (iv). State : Jharkhand   (v). Category of the Proposal : Railway   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 69273   (viii). Area of forest land proposed for diversion(in ha.): 9.144   (ix). Non-forest land required for this project(in ha.): 164.32   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : DY CHIEF ENGINEER CONSTRUCTION BHAGALPUR   (ii). Address1 : NEAR GUMTI NO. 3 BHIKHANPUR BHAGALPUR PIN 812001   (iii). Address2 : NIL   (iv). State : Bihar   (v). District : Bhagalpur   (vi). Pin : 812001   (vii). Landmark : NEAR WATER TANK   (viii). Email address : dycebgp@gmail.com   (ix). Landline Telephone No. : 641-2406485   (x). Fax No. : 641-2406485   (xi). Mobile No. : 9771420270   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Central Government
A-3. Details of Person Making Application
  (i). First Name: AMIT   (ii). Middle Name: NIL   (iii). Last Name: KUMAR   (iv). Gender: Male   (v). Designation: DY CHIEF ENGINEER CONSTRUCTION   (vi). Address 1: ASANSOL STATION   (vii). Address 2: NIL   (viii). State: West Bengal   (ix). District: Barddhaman   (x). Tehsil: NIL   (xi). Pin: 713301   (xii). Landmark: NEAR ASANSOL STATION   (xiii). Email Address: dycebgp@gmail.com   (xiv). Landline Telephone No.: 641-   (xv). Fax No.: NIL   (xvi). Mobile No.: 9002020267   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/JH/RAIL/23964/2017pf/JH/Rail2356/2018-25082.542.5423 Aug 2018
2InprincipleFP/JH/RAIL/3045/20172379.1449.14404 Mar 2022
Total 11.684 11.684
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dumka2.826102.861
2.Deoghar6.31861.459
Total9.144164.32
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dumka2.826102.861
1.Deoghar6.31861.459
Total9.144164.32
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Siltha03.178
2Jalwe04.393
3Pokhariya06.893
4Karhariya00.009
5Balwara04.535
6Baija0.2783.294
7Khojwa03.231
8Panchubad03.823
9Sarwa05.108
10Bank01.008
11Babupur01.37
12Panrekesho01.963
13Asikhandha02.446
14Kanoli00.056
15Bhoja03.615
16Mathakesho04.124
17Jamua00.317
18Patnuki02.683
19Kakani05.401
20Garbher01.297
21Muriyar05.597
22Khirdhana03.86
23Khirdhana-203.561
24Baratanr03.367
25Jamua 1002.095
26Tilakpur02.701
27Bhalua00.059
28Amjora0.5936.183
29Nawadih0.5276.01
30Haralatanr1.4288.719
31Malghaghar01.965
32Budhwakura03.902
33Nagpur00.377
34Rampur3.4033.94
35Ghutiyadundiya2.2393.705
36Khapachua Nawakurwa0.3374.535
37Bhagwanpur08.298
38Chihutiya05.057
39Kaniyari Pokhar01.847
40Khariyadih05.497
41Nawakurwa0.2255.043
42Buturuadih02.884
43Araji Buturuadih0.1142.416
44Tasariya00.026
45Kita ramsagar00.331
46Araji ramsagar00.871
47SingRaidih01.048
48Barasati Ghat01.877
49Chandayan04.403
50Araji Dummabad00.248
51Chhatakurum03.303
52Hindolabaran01.849
Total 9.144 164.318
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1SEG-10.27822.302
2SEG-20.59363.865
3SEG-30.5276.01
4SEG-41.4288.719
5SEG-53.40310.186
6SEG-62.2398.24
7SEG-70.33715.202
8SEG-80.22513.424
9SEG-90.11416.372
Total 9.144 164.32
C. Maps of forest land proposed to be diverted
Division 1. : Dumka
  (i). Area of forest land proposed to be diverted(in ha.) : 2.826   (ii). Nature of the Project: Linear   (b). No. of Segments : Four
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.1.428    View File
2.0.527    View File
3.0.593    View File
4.0.278    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Deoghar
  (i). Area of forest land proposed to be diverted(in ha.) : 6.318   (ii). Nature of the Project: Linear   (b). No. of Segments : Five
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.3.403    View File
2.2.239    View File
3.0.337    View File
4.0.225    View File
5.0.114    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 60000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1
2
3
4compliance of the letters of DFO Deoghar & DFO Dumka
5FRA JUNGLE JHARI DUMKA
6essential documents demanded vide letter dtd. 20/5/21 and uploaded dtd. 25/06/2021
7EDS by DFO/Deoghar. Undertaking for gram sabha & FRA (Deoghar) and certified copy of Rampur plot no. 35
8Additional documents against quarry raised on 21/09/2021.Part I offline, Undertaking of wild life management for both division
9tree list Dumka
10FRA for PF and JJ for both division
11Justification and comparison of alternative alignments
12No Dataalternative alignments
13Employment generation
14Tree list Deoghar
15Proposed alignment Mohanpur-Hansdiha new BG Rail line
16Alternative alignments