FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/Others/39044/2019
(ii). Name of Project for which Forest Land is required :
Construction of North Campus Central University Dharamshala, District Kangra
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The proposal is being submitted for the construction of Central University of Himachal Pradesh in Tehsil Dharamshala of District Kangra.
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Others
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
24200
(viii). Area of forest land proposed for diversion(in ha.):
64.2016
(ix). Non-forest land required for this project(in ha.):
25.9337
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
CENTRAL UNIVERSITY OF HIMACHAL PRADESH
(ii). Address1 :
Registrar Central University
(iii). Address2 :
North Campus Dharamshala
(iv). State :
Himachal Pradesh
(v). District :
Kangra
(vi). Pin :
176215
(vii). Landmark :
NIL
(viii). Email address :
cuhpnorth@gmail.com
(ix). Landline Telephone No. :
1892-229330
(x). Fax No. :
1892-229331
(xi). Mobile No. :
7018196283
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Central Government
A-3.
Details of Person Making Application
(i). First Name:
Shilpi
(ii). Middle Name:
NIL
(iii). Last Name:
Bekta
(iv). Gender:
Female
(v). Designation:
Nodal Officer Cum SDm Dharamshala
(vi). Address 1:
Nodal Office, Dharamshala
(vii). Address 2:
NIL
(viii). State:
Himachal Pradesh
(ix). District:
Kangra
(x). Tehsil:
NIL
(xi). Pin:
176215
(xii). Landmark:
NIL
(xiii). Email Address:
cuhpnorth@gmail.com
(xiv). Landline Telephone No.:
0-
(xv). Fax No.:
NIL
(xvi). Mobile No.:
7018196283
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Approved
FP/HP/Others/4519/2014
8-120/2011-FC
238.452
80.7916
27 Aug 2015
17 Feb 2021
Total
238.452
80.7916
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
D/sala
64.2016
25.9337
Total
64.2016
25.9337
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Kangra
64.2016
25.9337
Total
64.2016
25.9337
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Tang
0
0.4887
2
Patola
0
5.3394
3
Salag
2.5125
0
4
Bagiyara
13.9748
2.1347
5
Kand
43.2865
7.5819
6
Kardiyana
4.4278
5.2582
7
Sakoli
0
5.1308
Total
64.2016
25.9337
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Boys Hostel I
2
0
2
Water Tank I
0.09
0
3
Parking Area in Site I
0.12
0
4
Boys Hostel II
0.1885
0
5
Boys Hostel III
0.2404
0
6
Shopping Arcade
0.0824
0
7
International Hostel
0.4
0
8
Parking Area in Site II
0.1008
0
9
Type III Quarters I
0.384
0
10
Parking Area in Site III
0.078
0
11
Boys Hostel IV
0.768
0
12
Registrar Residence
0.03
0
13
CoE Residence
0.03
0
14
Finance Officer Residence
0.03
0
15
PVC Residence
0.03
0
16
Parking in Site IV
0.15
0
17
Parking II in Site IV
0.06
0
18
Open Air Gym and Park
0.21
0
19
Botanical Garden
1.7708
0
20
Water Tank in Site IV
0.09
0
21
Guard Room in Site IV
0.01
0
22
Administrative Block I
0.3004
0
23
Lecture Hall
0.1833
0
24
Acd. Block School of Earth and Environ. Sciences P
0.366
0
25
Acd. Block School of Commerce and Management Ph. I
0.2509
0
26
Acd. Block School of Tourism Travel and Hospitalit
0.3404
0
27
Acd. Block School of Performing and Visual Arts Ph
0.3475
0
28
Acd. Block School of Education Ph. I
0.265
0
29
Auditorium
0.25
0
30
Multipurpose Hall
0.075
0
31
Amenities I
0.0528
0
32
Administrative Block II
0.3
0
33
Acd. Block I School of Agriculture Ph. I
0.4
0
34
Acd. Block II School of Agriculture Ph. I
0.4
0
35
Acd. Block III School of Agriculture Ph. I
0.4
0
36
Acd. Block I School of Engineering Ph. I
0.4
0
37
Acd. Block II School of Engineering Ph. I
0.4
0
38
Acd. Block III School of Engineering Ph. I
0.4
0
39
Incubation Centre
0.3
0
40
Exp. of Acd. Block School of Earth and Env. Scienc
0.3
0
41
Exp. of Acd. Block School of Commerce and Manageme
0.3
0
42
Exp. of Acd. Block School of Tourism Travel and Ho
0.3
0
43
Exp. of Acd. Block I School of Performing and and
0.3
0
44
Exp. of Acd. Block in Phase II
0.3
0
45
Examination or CoE Centre
0.16
0
46
Computer and Informatics Centre
0.1
0
47
Central Instrumentiation Lab
0.2
0
48
Central Library
0.3
0
49
University School
0.2
0
50
Exp. of Acd. Block I School of Agriculture Ph.II
0.3
0
51
Exp. of Acd. Block II School of Agriculture Ph.II
0.3
0
52
Exp. of Acd. Block III School of Agriculture Ph. I
0.3
0
53
Exp. of Acd. Block IV School of Agriculture Ph.II
0.3
0
54
Exp. of Acd. Block I School of Engineering Ph.II
0.3
0
55
Exp. of Acd. Block II School of Engineering Ph.II
0.3
0
56
Exp. of Acd. Block III School of Engineering Ph.II
0.3
0
57
Exp. of Acd. Block IExp. of Acd. Block IV School o
0.3
0
58
Disaster Training Centre
0.1
0
59
Student Activity Centre
0.04
0
60
Academic Staff College Building
0.1
0
61
Sub Station
0.45
0
62
Parking I in Site V
0.3
0
63
Parking II in Site V
0.2025
0
64
Parking III in Site V
0.119
0
65
Open Park
0.48
0
66
Guard Room in Site V
0.01
0
67
Stadium
2.63
0
68
Indoor Sports Hall and Gym
0.15
0
69
Water Sports Complex
0.02
0
70
Faculty Club
0.08
0
71
STP I
0.12
0
72
Girls Hostel I
0.1885
0
73
Girls Hostel II
0.2404
0
74
International Hostel II
0.19
0
75
Guest House
0.0815
0
76
Shopping Arcade II
0.0824
0
77
Amenities II
0.0528
0
78
Health Centre
0.0536
0
79
Transit Hostel I
0.3635
0
80
Transit Hostel II
0.3955
0
81
Transit Hostel III
0.3208
0
82
Transit Hostel IV
0.802
0
83
Transit Hostel V
0.2685
0
84
Transit Hostel VI
1.074
0
85
Girls Hostel III
2
0
86
Honourable VC Residence
0.2
0
87
WTP
0.1375
0
88
STP II
0.225
0
89
Parking in Site VII
0.21
0
90
Guard Room in Site VII
0.01
0
91
Type III Quarters III
0.256
0
92
STP III
0.1064
0
93
Open Air Gym and Park in Site VIII
0.6
0
94
Main Roads
5.2896
0.6328
95
Access Roads
6.4536
0
96
Transmission Line
0.6345
1.3155
97
Pump House
0.06
0
98
Water Pipe Line
0.231
0.1276
99
Sewerage Line
0.456
0.221
100
Playground I
0
0.6
101
Playground II
0
0.684
102
STP IV
0
0.2805
103
Set Back Area
21.2628
22.0723
Total
64.2016
25.9337
C.
Maps of forest land proposed to be diverted
Division 1. : D/sala
(i). Area of forest land proposed to be diverted(in ha.) :
64.2016
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
64.2016
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
300
(iii). Temporary Employment(Number of person-days):
500000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Form A Part I
2
Detail Note
3
Revised Layout Plan
4
Statement of Forest Land
5
Statement of Non Forest Land
6
DC Certificate No Alternative
7
Certificate Minimum Use and Alternative Detail
8
Undertaking to Pay Cost of CA
9
Undertaking to Pay Cost of NPV
10
Undertaking to Pay Cost of Additional NPV
11
Undertaking to Submit FRA Certificate of Balance Land
12
Joint Inspection Report
13
Undertaking Non Violation
14
DC Certificate Non Availability of CA Land
15
Detail of Road and Transmission Line
16
NOC TCP
17
NOC IPH Department
18
Muck Management Plan
19
Component Wise Detail of Land
20
Certificate Beneficiary
21
Certificate Eco Sensitive Zone
22
Geological Report
23
Site Inspection 2013
24
Site Inspection 2016
25
Scanned Proposal I
26
Scanned Proposal II
27
Scanned Proposal III
28
Scanned Proposal IV
29
Reply to Observations
30
Reply to the Observations
31
Certificate from Collector Regarding Non Availability of Suitable Non Forest Land
32
Reply to the Observations raised by FAC
Print