TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/WB/WATER/146891/2021              (ii). Name of Project for which Forest Land is required : Darjeeling Water supply Scheme under AMRUT              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed scheme is to avoid the scarcity of the water in and around Darjeeling Municipality Area extent to 10.6 Sqkm. The Existing Municipality Water Supply is very old one which was laid by the British considering the population of 10000.Due to the Increase in population in density , the existi              (iv). State : West Bengal              (v). Category of the Project : Drinking Water              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.1075
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/WB/WATER/146891/202108/09/202103/01/2022  14/09/2021   06/02/2022  30/12/2021   21/02/2022   09/03/2022 Darjeeling Wildlife :14/03/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Darjeeling Wildlife) on:18/06/2022  
Replied by UA on :24/08/2022  
Query raised by DFO (Darjeeling Wildlife) on:13/09/2022  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .