Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kalimpong Forest Division)
|
EDS
|
User Agency (acefzoslg@gmail.com)
|
29/08/2022
|
Kindly Submit signed 6 hard copy of the proposal to this Office
|
|
2
|
User Agency (acefzoslg@gmail.com)
|
REPLY
|
DFO (Kalimpong Forest Division)
|
21/02/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kalimpong Forest Division)
|
EDS
|
User Agency (acefzoslg@gmail.com)
|
28/02/2023
|
correct the observation
|
|
4
|
User Agency (acefzoslg@gmail.com)
|
REPLY
|
DFO (Kalimpong Forest Division)
|
03/05/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Kalimpong Forest Division)
|
EDS
|
User Agency (acefzoslg@gmail.com)
|
31/05/2023
|
As per new guideline the compensatory afforestation should be Non-Forest land .
so kindly submit the details of NFL equivalent to the diversion land
|
|