TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/119900/2021              (ii). Name of Project for which Forest Land is required : Proposed Road Widening and Strengthening of Saursot Khurd to Sirsiya Road from Km.0.00 to 19.200 Under Rural Road Connectvity Project on Left Wing Extermism Area(CPCPLWEA) in Tehsil:Robertsganj,Dist:Sonbhadra              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Widening and Strengthening of Saursot Khurd to Sirsiya Road from Km.0.00 to 19.200 Under Rural Road Connectvity Project on Left Wing Extermism Area(CPCPLWEA) in Tehsil:Robertsganj,Dist:Sonbhadra              (iv). File no. : 8B/UP/06/316/2022/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 11.79
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/ROAD/119900/202101/02/202103/09/2021  03/02/2021   04/09/2021  02/09/2021   06/09/2021   10/09/2021 Forest Division Sonbhadra :10/09/2021Mirzapur Circle Mirzapur:
  27/07/2022 (Forest Division Sonbhadra)

Uttar Pradesh:
20/08/2022
Uttar Pradesh:
04/11/2022
Lucknow:
14/12/2022
04/05/2023
By :Regional Office
Uttar Pradesh
22/02/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:10/01/2023  
Replied by State Government(Uttar Pradesh) on:27/03/2023  
Query raised by State Government (Uttar Pradesh) on:10/01/2023  
Replied by Nodal Officer (Uttar Pradesh) on:27/03/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:24/08/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:03/10/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:03/10/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:06/10/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:06/10/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:10/10/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:10/10/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:04/11/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:11/01/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:24/03/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:28/07/2022  
Replied by DFO (Forest Division Sonbhadra) on:29/07/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:02/09/2022  
Replied by DFO (Forest Division Sonbhadra) on:22/09/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:13/10/2022  
Replied by DFO (Forest Division Sonbhadra) on:04/11/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:11/01/2023  
Replied by DFO (Forest Division Sonbhadra) on:15/03/2023  
Query raised by DFO (Forest Division Sonbhadra) on:14/09/2021  
Replied by UA on :09/11/2021  
Query raised by DFO (Forest Division Sonbhadra) on:27/11/2021  
Replied by UA on :17/06/2022  
Query raised by DFO (Forest Division Sonbhadra) on:21/06/2022  
Replied by UA on :22/07/2022  
Query raised by DFO (Forest Division Sonbhadra) on:05/09/2022  
Replied by UA on :17/09/2022  
Query raised by DFO (Forest Division Sonbhadra) on:14/10/2022  
Replied by UA on :21/10/2022  
Query raised by DFO (Forest Division Sonbhadra) on:22/10/2022  
Replied by UA on :04/11/2022  
Query raised by DFO (Forest Division Sonbhadra) on:12/01/2023  
Replied by UA on :15/03/2023  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:24/04/2024  
Replied by State Government(Uttar Pradesh) on:29/06/2024  
Query raised by Regional Office (Lucknow) on:01/08/2024  
Query raised by State Government (Uttar Pradesh) on:26/04/2024  
Replied by Nodal Officer (Uttar Pradesh) on:29/06/2024  
Query raised by State Government (Uttar Pradesh) on:02/08/2024  
Query raised by Nodal Officer on:26/04/2024  
Replied by UA on :28/06/2024  
Query raised by Nodal Officer on:05/08/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .