Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
11/04/2022
|
After resolving the objections in the proposal, send it again
|
|
2
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
20/04/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
29/04/2022
|
Hard Copy Not Submitted By User Agency
|
|
4
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
02/05/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
25/05/2022
|
Concerning Department NOC not enclosed by user Agency
|
|
6
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
26/05/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
30/05/2022
|
Resend the proposal after resolving the objection
|
|
8
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
07/06/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
25/06/2022
|
The Hard Copy of the objection related certificates has not been provided by the user Agency
|
|
10
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
02/08/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
10/08/2022
|
Badaun Chandausi Road SH-43 PWD Related NOC Not Submitted By User Agency
|
|
12
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
17/08/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
30/08/2022
|
Badaun Chandausi Road SH-43 PWD Related NOC hard & soft copy Not Submitted By User Agency
|
|
14
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
30/08/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
07/09/2022
|
Please Provied the Topo Sheet in Full Size
|
|
16
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
13/09/2022
|
The correction have been made as per the instruction received
|
|
17
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Sambhal)
|
28/10/2022
|
Hard copies of proposal has been not submitted in this office.
|
|
18
|
DFO (Social Forestry Division Sambhal)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
29/10/2022
|
Quiari removed
|
|
19
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Sambhal)
|
31/10/2022
|
Hard copies of proposal has been not submitted in this office.
|
|
20
|
DFO (Social Forestry Division Sambhal)
|
EDS
|
User Agency (prabhashkumar@torrentgas.com)
|
31/10/2022
|
The CD of the KML file presented by the petitioner department in the proposal is not opening.
|
|
21
|
User Agency (prabhashkumar@torrentgas.com)
|
REPLY
|
DFO (Social Forestry Division Sambhal)
|
02/11/2022
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Social Forestry Division Sambhal)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
02/11/2022
|
Quiary Removed
|
|