TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Pipeline/150710/2021              (ii). Name of Project for which Forest Land is required : IGL project for Laying of 125 mm MDPE gas pipeline along NH-24 (New NH-9) (Delhi-Lucknow Road (RHS)) from Km.27.500 to Km.33.350 & NH-709 B (Delhi-Baghpat Road (LHS)) from Km.15.600 to Km.16.000 & from Km.19.300 to Km.22.200. Total Km.9.15 & 0.4575 Ha. in Social Forestry Division Ghaziabad, District-Ghaziabad, UP.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : IGL project for Laying of 125mm MDPE gas pipeline along NH-24(New NH-9)(Delhi-Lucknow Road(RHS)) from Km.27.500 to Km.33.350 & NH-709B(Delhi-Baghpat Road(LHS))from Km.15.600 to Km.16.000 & fromKm.19.300 to Km.22.200.Total Km.9.15 &0.4575Ha. in SocialForestryDivision Ghaziabad, District-Ghaziabad,UP.              (iv). State : Uttar Pradesh              (v). Category of the Project : Pipeline              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.4575
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/Pipeline/150710/202101/01/2022aa05/01/2022   08/02/2022 Social Forestry Division Ghaziabad :09/02/2022Meerut Circle Meerut:
  01/06/2022 (Social Forestry Division Ghaziabad)

Uttar Pradesh:
22/06/2022
Uttar Pradesh:
24/06/2022
Lucknow:
03/08/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:02/09/2022  
Query raised by State Government (Uttar Pradesh) on:12/09/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:12/09/2022  
Query raised by Circle (Meerut Circle Meerut) on:03/06/2022  
Replied by DFO (Social Forestry Division Ghaziabad) on:08/06/2022  
Query raised by Circle (Meerut Circle Meerut) on:09/06/2022  
Replied by DFO (Social Forestry Division Ghaziabad) on:18/06/2022  
Query raised by Circle (Meerut Circle Meerut) on:16/09/2022  
Replied by DFO () on:  
Query raised by DFO (Social Forestry Division Ghaziabad) on:23/02/2022  
Replied by UA on :26/04/2022  
Query raised by DFO (Social Forestry Division Ghaziabad) on:05/05/2022  
Replied by UA on :05/05/2022  
Query raised by DFO (Social Forestry Division Ghaziabad) on:20/05/2022  
Replied by UA on :24/05/2022  
Query raised by DFO (Social Forestry Division Ghaziabad) on:28/10/2022  
Replied by UA on :21/11/2022  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .
Close(X)
Close(X)
Please wait ...