TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Approach/155004/2022              (ii). Name of Project for which Forest Land is required : Proposed BPCL Retail Outlet on Kabrai-Chhatarpur Road NH-34 (Old NH-86) In Km No.04 to 05 (CH.No.4.390,LHS) At Khasra No.814Kha (Part of Khasra No.-814), Village:-Bhatipura, Tehsil:- Mahoba, District:- Mahoba              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposed Protected Forest land to be Diverted for Entry/Exit approach to BPCL Retail Outlet on Kabrai-Chhatarpur Road NH-34 (Old NH-86) In Km No.04 to 05 (CH. No. 4.390, LHS) At Khasra No. 814 Kha (Part of Khasra No.-814), Village: -Bhatipura, Tehsil: - Mahoba, District: - Mahoba.              (iv). State : Uttar Pradesh              (v). Category of the Project : Approach Access              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.052768
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/Approach/155004/202229/04/202212/05/2022   16/05/2022   17/05/2022   16/06/2022 Forest Division Mahoba :17/06/2022Chitrakoot Circle Banda:
  07/09/2022 (Forest Division Mahoba)

Uttar Pradesh:
29/09/2022
Uttar Pradesh:
30/09/2022
Lucknow:
29/11/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Chitrakoot Circle Banda) on:12/09/2022  
Replied by DFO (Forest Division Mahoba) on:26/09/2022  
Query raised by DFO (Forest Division Mahoba) on:07/07/2022  
Replied by UA on :01/09/2022  
Query raised by DFO (Forest Division Mahoba) on:15/09/2022  
Replied by UA on :26/09/2022  
NOTE:- Proposal is pending at Regional Office .