TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/WATER/42511/2019   (ii). Name of Project for which Forest Land is required : Mussoorie reorgnisation water supply scheme forest land transfer proposal   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Mussoorie is one of the world famous tourist hill station in Uttarakhand, the existing water supply is not fulfill the water demand of Mussoorie town. Hence, to provide sufficient drinking water supply to Mussoorie, re organization of Mussoorie water supply scheme has been prepared to fulfill the   (iv). State : Uttarakhand   (v). Category of the Project : Drinking Water   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 2.323
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/WATER/42511/201916/10/201931/10/2019   17/01/2020   18/01/2020   12/02/2020 Mussoorie :18/02/2020Yamuna:
  29/02/2020 (Mussoorie)

C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Mussoorie) on:20/02/2020  
Replied by UA on :24/02/2020  
NOTE:- Proposal is pending at CF .