TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/WATER/42099/2019              (ii). Name of Project for which Forest Land is required : Rudraprayag Nagar Pumping Water Supply Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Rudraprayag Nagar Pumping Water Supply Scheme has been proposed for Rudraprayag Nagar. The old existing water Supply system is 33 years old. Due to which most of pipe lines are rusted badly and it affects the water Quality and is all so not safe for drinking purpose. The present rate of water supply              (iv). State : Uttarakhand              (v). Category of the Project : Drinking Water              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 2.0951
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/WATER/42099/201919/09/201910/10/2019  20/09/2019   06/11/2019  05/10/2019   14/11/2019   09/12/2019 Rudraprayag :10/12/2019
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Rudraprayag) on:12/12/2019  
Replied by UA on :27/12/2019  
Query raised by DFO (Rudraprayag) on:09/01/2020  
Replied by UA on :14/01/2020  
Query raised by DFO (Rudraprayag) on:05/02/2020  
Replied by UA on :26/08/2020  
Query raised by DFO (Rudraprayag) on:10/09/2020  
Replied by UA on :22/12/2021  
Query raised by DFO (Rudraprayag) on:31/12/2021  
Replied by UA on :24/02/2022  
Query raised by DFO (Rudraprayag) on:28/02/2022  
Replied by UA on :04/04/2022  
Query raised by DFO (Rudraprayag) on:11/04/2022  
Replied by UA on :19/04/2022  
Query raised by DFO (Rudraprayag) on:01/06/2022  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .
Close(X)