Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
19/09/2019
|
As per letter no. 1078/12-1 dated 19-09-2019
|
|
2
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
20/09/2019
|
objection reply dated 20-09-2019
|
|
3
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
31/10/2019
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
11/11/2019
|
objection reply dated 11-11-2019
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
13/11/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
16/11/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
7
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
18/11/2019
|
objection reply dated 18-11-2019
|
|
8
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
11/02/2020
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
14/05/2020
|
objection reply dated 14-05-2020
|
|
10
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
26/05/2020
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
11
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
05/06/2020
|
objection reply dated 05-06-2020
|
|
12
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
06/07/2020
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
19/08/2020
|
objection reply dated 19-08-2020
|
|
14
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
29/08/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 13-11-2019 has been clarified by Dfo Almora letter no 1030/12-1 dated 19-08-2020
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
26/11/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
26/11/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
26/11/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
18
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
28/11/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
19
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
05/12/2020
|
Do needful as per EDS raised
|
|
20
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
16/02/2021
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
05/03/2021
|
reply of EDS point no 4 is seems not to be correct. please do needful
|
|
22
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
07/04/2021
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
12/04/2021
|
reply of EDS point no 4 is seems not to be correct. please do needful
|
|
24
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
08/07/2021
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
03/09/2021
|
please submit the authenticated hard copy of online part 1 in 5 copies
|
|
26
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
18/09/2021
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
28/09/2021
|
please find the attached letter
|
|
28
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
11/12/2021
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
04/03/2022
|
As per objection Point No. 1 Alternate alignment Road has been not shown in KML File
|
|
30
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
19/05/2022
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
03/05/2023
|
Please find the letter attached.
|
|
32
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
12/05/2023
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
14/06/2023
|
Please find the letter attached regarding Joint Inspection dated 21.06.2023
|
|
34
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
28/06/2023
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
30/06/2023
|
Please find the letter attached.
|
|
36
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
07/05/2025
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
24/05/2025
|
correction has been not made as per instruction given.
|
|