  (i). Proposal No. : FP/UK/ROAD/33094/2018              (ii). Name of Project for which Forest Land is required : Garath (Diwarikhol) to Garath link motor road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To provide road connectivity for village Garath (population-372)minimum forest land route is selected because there is no other forestless route to provide connectivity to Garath. Construction of this road is necessary for the development of villageres.              (iv). File no. : 8B/UCP/06/185/2019/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.5975
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/33094/201823/04/201809/08/2018  17/07/2018  19/05/2018   03/09/2018  05/08/2018  09/06/2018   10/09/2018   15/09/2018 Uttarkashi :18/09/2018Bhagirathi:
  27/03/2019 (Uttarkashi)

Uttarakhand:
18/06/2019
Uttarakhand:
26/09/2019
Dehradun:
15/10/2019
28/08/2020
By :Regional Office
Uttarakhand
28/08/2021
30/08/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:08/11/2019  
Replied by State Government(Uttarakhand) on:18/08/2020  
Query raised by State Government (Uttarakhand) on:11/11/2019  
Replied by Nodal Officer (Uttarakhand) on:18/08/2020  
Query raised by Nodal Officer (Uttarakhand) on:18/06/2019  
Replied by Circle(Bhagirathi) on:20/07/2019  
Query raised by Nodal Officer (Uttarakhand) on:23/07/2019  
Replied by Circle(Bhagirathi) on:19/09/2019  
Query raised by Nodal Officer (Uttarakhand) on:13/11/2019  
Replied by Circle(Bhagirathi) on:30/01/2020  
Query raised by Nodal Officer (Uttarakhand) on:04/02/2020  
Replied by Circle(Bhagirathi) on:08/06/2020  
Query raised by Nodal Officer (Uttarakhand) on:12/06/2020  
Replied by Circle(Bhagirathi) on:30/07/2020  
Query raised by Circle (Bhagirathi) on:12/04/2019  
Replied by DFO (Uttarkashi) on:25/04/2019  
Query raised by Circle (Bhagirathi) on:01/05/2019  
Replied by DFO (Uttarkashi) on:23/05/2019  
Query raised by Circle (Bhagirathi) on:27/05/2019  
Replied by DFO (Uttarkashi) on:10/06/2019  
Query raised by Circle (Bhagirathi) on:19/06/2019  
Replied by DFO (Uttarkashi) on:28/06/2019  
Query raised by Circle (Bhagirathi) on:24/07/2019  
Replied by DFO (Uttarkashi) on:11/09/2019  
Query raised by Circle (Bhagirathi) on:13/11/2019  
Replied by DFO (Uttarkashi) on:28/01/2020  
Query raised by Circle (Bhagirathi) on:04/02/2020  
Replied by DFO (Uttarkashi) on:24/02/2020  
Query raised by Circle (Bhagirathi) on:02/03/2020  
Replied by DFO (Uttarkashi) on:01/06/2020  
Query raised by Circle (Bhagirathi) on:04/06/2020  
Replied by DFO (Uttarkashi) on:05/06/2020  
Query raised by Circle (Bhagirathi) on:15/06/2020  
Replied by DFO (Uttarkashi) on:21/07/2020  
Query raised by DFO (Uttarkashi) on:08/12/2018  
Replied by UA on :27/12/2018  
Query raised by DFO (Uttarkashi) on:11/01/2019  
Replied by UA on :23/03/2019  
Query raised by DFO (Uttarkashi) on:26/03/2019  
Replied by UA on :26/03/2019  
Query raised by DFO (Uttarkashi) on:03/05/2019  
Replied by UA on :15/05/2019  
Query raised by DFO (Uttarkashi) on:19/06/2019  
Replied by UA on :26/06/2019  
Query raised by DFO (Uttarkashi) on:25/07/2019  
Replied by UA on :07/09/2019  
Query raised by DFO (Uttarkashi) on:09/09/2019  
Replied by UA on :09/09/2019  
Query raised by DFO (Uttarkashi) on:13/11/2019  
Replied by UA on :14/01/2020  
Query raised by DFO (Uttarkashi) on:22/01/2020  
Replied by UA on :27/01/2020  
Query raised by DFO (Uttarkashi) on:05/02/2020  
Replied by UA on :08/02/2020  
Query raised by DFO (Uttarkashi) on:05/06/2020  
Replied by UA on :05/06/2020  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:06/09/2021  
Replied by State Government(Uttarakhand) on:14/08/2023  
Query raised by State Government (Uttarakhand) on:13/09/2021  
Replied by Nodal Officer (Uttarakhand) on:08/08/2023  
Query raised by Nodal Officer on:13/09/2021  
Replied by UA on :27/05/2022  
Query raised by Nodal Officer on:23/06/2022  
Replied by UA on :12/07/2023  
NOTE:- Stage-II Approval accorded by : Regional Office .