TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/29385/2017              (ii). Name of Project for which Forest Land is required : Dewal-Mundoli Motor Road to G.I.C. Mundoli Motor Road.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For Construction of this Motor Road 0.288 Ha. Van Panchyat is required. After construction of this Motor Road Students of G.I.C. Mundoli and 944 Population of Mundoli will Benefited.              (iv). File no. : 8B/UCP/06/47/2018/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.288
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/29385/201721/09/2017aa25/10/2017   15/11/2017 Badrinath,Gopeshwar :15/11/2017Garhwal:
  30/12/2017 (Badrinath,Gopeshwar)

Uttarakhand:
06/01/2018
Uttarakhand:
03/03/2018
Dehradun:
22/03/2018
13/10/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:04/04/2018  
Replied by State Government(Uttarakhand) on:26/04/2018  
Query raised by Regional Office (Dehradun) on:01/06/2018  
Replied by State Government(Uttarakhand) on:18/06/2018  
Query raised by Regional Office (Dehradun) on:12/07/2018  
Replied by State Government(Uttarakhand) on:12/06/2020  
Query raised by Regional Office (Dehradun) on:25/06/2020  
Replied by State Government(Uttarakhand) on:05/10/2020  
Query raised by State Government (Uttarakhand) on:13/04/2018  
Replied by Nodal Officer (Uttarakhand) on:13/04/2018  
Query raised by State Government (Uttarakhand) on:20/04/2018  
Replied by Nodal Officer (Uttarakhand) on:26/04/2018  
Query raised by State Government (Uttarakhand) on:11/09/2018  
Replied by Nodal Officer (Uttarakhand) on:12/06/2020  
Query raised by State Government (Uttarakhand) on:26/06/2020  
Replied by Nodal Officer (Uttarakhand) on:05/10/2020  
Query raised by Nodal Officer (Uttarakhand) on:06/01/2018  
Replied by Circle(Garhwal) on:22/02/2018  
Query raised by Nodal Officer (Uttarakhand) on:11/09/2018  
Replied by Circle(Garhwal) on:02/06/2020  
Query raised by Nodal Officer (Uttarakhand) on:26/06/2020  
Replied by Circle(Garhwal) on:28/09/2020  
Query raised by Circle (Garhwal) on:08/01/2018  
Replied by DFO (Badrinath,Gopeshwar) on:15/02/2018  
Query raised by Circle (Garhwal) on:16/02/2018  
Replied by DFO (Badrinath,Gopeshwar) on:16/02/2018  
Query raised by Circle (Garhwal) on:19/09/2018  
Replied by DFO (Badrinath,Gopeshwar) on:11/05/2020  
Query raised by Circle (Garhwal) on:27/06/2020  
Replied by DFO (Badrinath,Gopeshwar) on:24/09/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:10/01/2018  
Replied by UA on :18/01/2018  
Query raised by DFO (Badrinath,Gopeshwar) on:19/09/2018  
Replied by UA on :08/11/2019  
Query raised by DFO (Badrinath,Gopeshwar) on:11/11/2019  
Replied by UA on :30/12/2019  
Query raised by DFO (Badrinath,Gopeshwar) on:13/01/2020  
Replied by UA on :15/02/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:27/02/2020  
Replied by UA on :29/02/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:29/06/2020  
Replied by UA on :24/08/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...