Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
20/07/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
2
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
21/07/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
3
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
22/07/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
4
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
25/07/2017
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
02/08/2017
|
Please remove the objection.
|
|
6
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
21/08/2017
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
12/09/2017
|
Sir, EDS reply date 11-09-2017. Send soft copy your mail id.
|
|
8
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
12/09/2017
|
sir please receive the information of the proposal.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
06/10/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
10
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
09/10/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
11
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
11/10/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
12
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
03/11/2017
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
15/11/2017
|
Sir, EDS objection reply.
|
|
14
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
20/11/2017
|
sir, please receive the information of the proposal.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
29/11/2017
|
find the letter attached
|
|
16
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
30/11/2017
|
please remove the objection.
|
|
17
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
06/12/2017
|
please remove the objection.
|
|
18
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
26/12/2017
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
29/01/2018
|
please remove theo objection.
|
|
20
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
07/03/2018
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
18/04/2018
|
Sir, EDS Objection reply.
|
|
22
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
23/04/2018
|
Sir please receive the information of the proposal.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
10/05/2018
|
find the letter attached
|
|
24
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
16/05/2018
|
please remove the objection.
|
|
25
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
19/05/2018
|
Please remove the objection.
|
|
26
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
15/03/2019
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
23/04/2019
|
please remove the objection.
|
|
28
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
25/06/2019
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
05/08/2019
|
Sir eds objection reply by user agency.
|
|
30
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
16/08/2019
|
Sir please received the information this proposal.
|
|
31
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
27/08/2019
|
find the letter attached
|
|
32
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
28/08/2019
|
Sir Please remove the objection
|
|
33
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
29/08/2019
|
please remove the objection.
|
|
34
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
29/09/2019
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
05/10/2019
|
Please remove the objection.
|
|
36
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
05/12/2019
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
23/12/2019
|
Please remove the objection.
|
|
38
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
11/02/2020
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
27/02/2020
|
Please remove the objection.
|
|
40
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
26/05/2020
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
16/06/2020
|
Sir, EDS objection has been removed by user agency.
|
|
42
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
23/06/2020
|
Sir Please received the information this proposal
|
|
43
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
25/06/2020
|
find the letter attached
|
|
44
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
29/06/2020
|
Sir Please remove the objection
|
|
45
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
29/06/2020
|
Sir, Please remove the objection.
|
|
46
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
08/07/2020
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
20/07/2020
|
Sir, EDS objection has been remove by user agency.
|
|
48
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
04/08/2020
|
Sir Please received the information this proposal
|
|
49
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
05/08/2020
|
find the letter attached
|
|
50
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
10/08/2020
|
Please remove the objection
|
|
51
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
13/08/2020
|
Sir, EDS no 02 related to your office. please remove the objection.
|
|
52
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
25/09/2020
|
Regarding Proposal No FP/UK/ROAD/22108/2016, the query has been resolved.
|
|
53
|
Regional Office
|
EDS
|
State secretary
|
17/11/2020
|
State Govt. may attend the following shortcomings as per the given attachment
|
|
54
|
State secretary
|
EDS
|
Nodal Officer
|
17/11/2020
|
State Govt. may attend the following shortcomings as per the given attachment
|
|
55
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
17/11/2020
|
State Govt. may attend the following shortcomings as per the given attachment
|
|
56
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
18/11/2020
|
State Govt. may attend the following shortcomings as per the given attachment
|
|
57
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
27/11/2020
|
Please find the attachment.
|
|
58
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
15/01/2021
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
29/01/2021
|
Sir, EDS objection has been removed by user agency.
|
|
60
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
10/02/2021
|
Sir Please received the information this proposal
|
|
61
|
Nodal Officer
|
REPLY
|
State secretary
|
27/02/2021
|
The correction have been made as per the instruction received
|
|
62
|
State secretary
|
REPLY
|
Regional Office
|
27/02/2021
|
The correction have been made as per the instruction received
|
|
63
|
Regional Office
|
EDS
|
State secretary
|
17/03/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
64
|
State secretary
|
EDS
|
Nodal Officer
|
17/03/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
65
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
17/03/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
66
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
19/03/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
67
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
23/03/2021
|
Please remove the objection.
|
|
68
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
03/04/2021
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
15/04/2021
|
please remove the objection.
|
|
70
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
31/05/2021
|
The correction have been made as per the instruction received
|
|
71
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
25/06/2021
|
the objection of point no. 3 has not been removed.
|
|
72
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
25/06/2021
|
The correction have been made as per the instruction received
|
|
73
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
09/07/2021
|
EDS objection has been removed.
|
|
74
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
09/07/2021
|
Sir Please received the information this proposal
|
|
75
|
Nodal Officer
|
REPLY
|
State secretary
|
22/07/2021
|
The correction have been made as per the instruction received
|
|
76
|
State secretary
|
REPLY
|
Regional Office
|
22/07/2021
|
The correction have been made as per the instruction received
|
|
77
|
Regional Office
|
EDS
|
State secretary
|
29/07/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
78
|
State secretary
|
EDS
|
Nodal Officer
|
29/07/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
79
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
29/07/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
80
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
29/07/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
81
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
30/07/2021
|
please remove the objection.
|
|