  (i). Proposal No. : FP/TR/TRANS/47082/2020              (ii). Name of Project for which Forest Land is required : Diversion of 5.09487 Ha of Forest land for construction of 33kV Overhead line from Teliamura to Taidu under NERPSIP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed 33 kV Overhead Line from Teliamura to Taidu Line is a part of the NERPSIP Project. Since the line passes through the Teliamura RF & Jambukchara village and to be terminated at the Taidu Substation, it unavoidably passes through some Forest(UGF/RF) areas.              (iv). File no. : 3-TR C 012/2021-SHI              (v). State : Tripura              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 5.09487
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TR/TRANS/47082/202004/07/202007/10/2020  31/07/2020  27/07/2020  09/07/2020   20/10/2020  05/10/2020  31/07/2020  27/07/2020   03/11/2020   17/11/2020

Khowai District Forest :23/11/2020


Gumti District Forest :23/11/2020

Tripura South:
  21/01/2021 (Gumti District Forest)

Tripura North:
  06/02/2021 (Khowai District Forest)

Tripura:
05/03/2021
Tripura:
05/03/2021
Shillong:
05/03/2021
05/05/2021
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shillong) on:01/04/2021  
Replied by State Government(Tripura) on:12/04/2021  
Query raised by Regional Office (Shillong) on:20/04/2021  
Replied by State Government(Tripura) on:23/04/2021  
Query raised by DFO (Gumti District Forest) on:08/12/2020  
Replied by UA on :16/01/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .