Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Tripura North)
|
EDS
|
DFO (North District Forest)
|
09/08/2021
|
Rectification required.
|
|
2
|
DFO (North District Forest)
|
REPLY
|
CF (Tripura North)
|
10/08/2021
|
Action taken
|
|
3
|
CF (Tripura North)
|
EDS
|
DFO (North District Forest)
|
10/08/2021
|
Clarification/ justification to be submitted by user agency
|
|
4
|
DFO (North District Forest)
|
EDS
|
User Agency (akilmorth@gmail.com)
|
10/08/2021
|
User Agency is to take needful action.
|
|
5
|
User Agency (akilmorth@gmail.com)
|
REPLY
|
DFO (North District Forest)
|
10/08/2021
|
The correction have been made as per the instruction received
|
|
6
|
DFO (North District Forest)
|
REPLY
|
CF (Tripura North)
|
10/08/2021
|
Action taken
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
22/10/2021
|
The State Govt. is requested to provide following additional information for further
processing of the case: -
I. In the proposal submitted it is seen that from chainage 16077 to 42500 the existing ROW is
given as O. State Govt may clarify if this proposal covering 26.423 km is a new road
alignment. If so
i. The three alternative routes may be provided.
ii. The total length in which new alignment has been proposed may be given Division-wise.
2. The User Agency has given undertaking of trees to be affected with a rider that the number
of trees to be affected and detailed will be given after Joint-verification. Hence, State Govt
may submit the final list of trees to be affected and to be checked and countersigned by the
CF. 3. State Govt has demanded total amount at Rs.3 .12 crore
|
|
8
|
State secretary
|
REPLY
|
Regional Office
|
09/11/2021
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|