Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
20/07/2022
|
The State Govt. is requested to provide following additional information for further processing of the case: - I) User Agency to provide detail breakup of the 3.35 ha plinth area and to clarify whether any
accommodation has also been included in the plinth area. 2) User Agency may inform if this drilling is exploratory off or commercial production. 3) Out of 10.48 ha CA area as per DSS software, 8.57 ha is Moderately Dense Forest. The State Govt to choose alternate site or have the area certified by an officer not below the rank of CF with clear mention of its density for each patch. 4) Whether the 2% of NPV of the entire forest area of the PML has been paid. 5) The compensatory afforestation scheme may be resubmitted after technically approved by the competent authority. 6) The Environme
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
27/07/2022
|
UA was requested to furnish the addl. information
|
|
3
|
Nodal Officer
|
EDS
|
CF (Tripura South)
|
27/07/2022
|
UA was requested to furnish the addl. information
|
|
4
|
CF (Tripura South)
|
EDS
|
DFO (South District Forest)
|
27/07/2022
|
UA was requested to furnish the addl. information
|
|
5
|
DFO (South District Forest)
|
EDS
|
User Agency (safety@oilindia.in)
|
27/07/2022
|
UA was requested to furnish the addl. information
|
|
6
|
User Agency (safety@oilindia.in)
|
REPLY
|
DFO (South District Forest)
|
02/09/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (South District Forest)
|
REPLY
|
CF (Tripura South)
|
02/09/2022
|
The correction have been made as per the instruction received
|
|
8
|
CF (Tripura South)
|
REPLY
|
Nodal Officer
|
02/09/2022
|
The correction have been made as per the instruction received
|
|
9
|
Nodal Officer
|
REPLY
|
State secretary
|
02/09/2022
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
02/09/2022
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|