TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/RAIL/141594/2021              (ii). Name of Project for which Forest Land is required : CMRL Phase II C5 - 06 Madhavaram to Sholinganallur- Nanmangalam Forest land required for Elevated metro station              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Chennai Metro Rail Limited is a Joint Venture of Government of India and Government of Tamil Nadu with equal equity holding. Under Phase 2, CMRL is taking up 118 km of Metro Rail network under three corridors namely C3, C4 and C5. Corridor 5 starts from Madhavaram Milk Colony and passes through CMBT              (iv). State : Tamil Nadu              (v). Category of the Project : Railway              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.569
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TN/RAIL/141594/202121/04/202128/06/2021  05/05/2021   20/07/2021  22/06/2021   02/08/2021   11/08/2021 Chengalpattu,Kancheepuram :27/08/2021Chennai:
  07/10/2021 (Chengalpattu,Kancheepuram)

C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending at CF .