TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/ROAD/126851/2021              (ii). Name of Project for which Forest Land is required : Widening and Strengthening of existing intermediate lane /two lane to two lane with pavedshoulder from km 678/555 to km 699/655 of nirmal to khanapur section of NH-61 on EPC mode in Nirmal district -              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 17.498 Ha of forest land in Nirmal and Khanapur division for Widening and Strengthening of existing intermediate lane /two lane to two lane with pavedshoulder from km 678/555 to km 699/655 of nirmal to khanapur section of NH-61 on EPC mode in Nirmal district in favour MoRTH, Hyderabad              (iv). File no. : 4-TSC184/2021-HYD              (v). State : Telangana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 17.498
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/TG/ROAD/126851/202108/03/202129/03/2021   29/05/2021   29/05/2021   29/05/2021

Nirmal :29/05/2021


Khanapur :29/05/2021

Kawal Tiger Reserve:
  29/05/2021 (Nirmal)

Kawal Tiger Reserve:
  29/05/2021 (Khanapur)

Telangana:
29/05/2021
Telangana:
29/05/2021
Hyderabad:
11/06/2021
18/08/2021
By :Regional Office
Telangana
14/03/2023
28/12/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Hyderabad) on:29/07/2021  
Replied by State Government(Telangana) on:18/08/2021  
Query raised by State Government (Telangana) on:11/06/2021  
Replied by Nodal Officer (Telangana) on:11/06/2021  
Query raised by Nodal Officer (Telangana) on:11/06/2021  
Replied by Circle(Kawal Tiger Reserve) on:11/06/2021  
Query raised by Circle (Kawal Tiger Reserve) on:11/06/2021  
Replied by DFO (Khanapur) on:11/06/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Hyderabad) on:14/03/2023  
Replied by State Government(Telangana) on:14/03/2023  
Query raised by Regional Office (Hyderabad) on:31/05/2023  
Replied by State Government(Telangana) on:31/10/2023  
Query raised by Regional Office (Hyderabad) on:20/11/2023  
Replied by State Government(Telangana) on:23/11/2023  
Query raised by State Government (Telangana) on:24/08/2023  
Replied by Nodal Officer (Telangana) on:31/10/2023  
NOTE:- Stage-II Approval accorded by : Regional Office .