TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/Others/147643/2021              (ii). Name of Project for which Forest Land is required : Diversion of 0.0020Ha of Forest Land for installation of Automatic Data Acquisition and Real Time Data Transmission System through satellite for Snow Gauge and Rainfall measurement at Gnathang in East Sikkim              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Installation of Automatic Data Acquisition and Real Time Data Transmission System through satellite for Snow Gauge and Rainfall measurement at Gnathang in East Sikkim              (iv). File no. : IRO/KOL/SK/Others/147643/2021              (v). State : Sikkim              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.002
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/Others/147643/202124/09/202101/10/2021  27/09/2021   04/10/2021  27/09/2021   21/10/2021   21/10/2021 East Territorial :03/11/2021Territorial:
  13/01/2022 (East Territorial)

Sikkim:
24/03/2022
Sikkim:
03/08/2022
Kolkata:
03/08/2022
31/08/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Sikkim) on:29/07/2022  
Replied by Circle(Territorial) on:03/08/2022  
Query raised by Circle (Territorial) on:29/07/2022  
Replied by DFO (East Territorial) on:03/08/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .