  (i). Proposal No. : FP/RJ/TRANS/34423/2018   (ii). Name of Project for which Forest Land is required : Construction of 132 KV D/C LILO from 132 KV S/C Bagidora - Mahi (PH-2) Line to 132 KV GSS Chordi, District- Banswara (Raj.)”   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 132 KV D/C LILO from 132 KV S/C Bagidora - Mahi (PH-2) Line to 132 KV GSS Chordi, District- Banswara (Raj.)”   (iv). State : Rajasthan   (v). Category of the Project : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 1.9003
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/TRANS/34423/201826/07/2018aa24/09/2018   09/10/2018 Banswara Territorial :09/10/2018Udaipur:
  24/01/2019 (Banswara Territorial)

Rajasthan:
18/02/2019
Rajasthan:
28/05/2019
Lucknow:
26/06/2019
14/01/2020
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:19/07/2019  
Replied by State Government(Rajasthan) on:03/01/2020  
Query raised by State Government (Rajasthan) on:26/07/2019  
Replied by Nodal Officer (Rajasthan) on:12/12/2019  
Query raised by Nodal Officer (Rajasthan) on:07/03/2019  
Replied by Circle(Udaipur) on:25/04/2019  
Query raised by Nodal Officer (Rajasthan) on:14/05/2019  
Replied by Circle(Udaipur) on:27/05/2019  
Query raised by Nodal Officer (Rajasthan) on:01/08/2019  
Replied by Circle(Udaipur) on:26/11/2019  
Query raised by Circle (Udaipur) on:07/03/2019  
Replied by DFO (Banswara Territorial) on:10/04/2019  
Query raised by Circle (Udaipur) on:15/05/2019  
Replied by DFO (Banswara Territorial) on:22/05/2019  
Query raised by Circle (Udaipur) on:06/08/2019  
Replied by DFO (Banswara Territorial) on:22/11/2019  
Query raised by DFO (Banswara Territorial) on:30/10/2018  
Replied by UA on :21/12/2018  
Query raised by DFO (Banswara Territorial) on:10/03/2019  
Replied by UA on :01/04/2019  
Query raised by DFO (Banswara Territorial) on:13/08/2019  
Replied by UA on :02/09/2019  
Query raised by DFO (Banswara Territorial) on:14/11/2019  
Replied by UA on :20/11/2019  