TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/TRANS/22004/2016   (ii). Name of Project for which Forest Land is required : 132 KV S/C Chattargarh – Khajuwala Transmission Line”   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To meet out the load growth in the area and improve the existing system parameters it is proposed to create a 132 KV GSS at Chhatargarh of capacity 20/25 MVA which is at the load centre, by laying 50 Km 132 KV S/C line from Khajuwala to Proposed 132 KV GSS at Chhattargarh.   (iv). State : Rajasthan   (v). Category of the Project : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 16.48
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/RJ/TRANS/22004/201621/10/201608/11/2016   11/12/2016   26/12/2016   10/01/2017 Chhatargarh Territorial :10/01/2017Bikaner:
  15/02/2017 (Chhatargarh Territorial)

Rajasthan:
16/02/2017
Rajasthan:
26/04/2017
30/08/2017
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:08/06/2017  
Replied by State Government(Rajasthan) on:27/06/2017  
Replied by State Government(Rajasthan) on:24/07/2017  
Replied by State Government(Rajasthan) on:14/08/2017  
Query raised by Regional Office (Lucknow) on:19/07/2017  
Replied by State Government(Rajasthan) on:24/07/2017  
Replied by State Government(Rajasthan) on:14/08/2017  
Query raised by Regional Office (Lucknow) on:03/08/2017  
Replied by State Government(Rajasthan) on:14/08/2017  
Query raised by State Government (Rajasthan) on:09/06/2017  
Replied by Nodal Officer (Rajasthan) on:24/06/2017  
Query raised by State Government (Rajasthan) on:19/07/2017  
Replied by Nodal Officer (Rajasthan) on:21/07/2017  
Query raised by State Government (Rajasthan) on:03/08/2017  
Replied by Nodal Officer (Rajasthan) on:11/08/2017  
Query raised by Nodal Officer (Rajasthan) on:09/03/2017  
Replied by Circle(Bikaner) on:11/04/2017  
Query raised by Nodal Officer (Rajasthan) on:09/06/2017  
Replied by Circle(Bikaner) on:22/06/2017  
Query raised by Nodal Officer (Rajasthan) on:19/07/2017  
Replied by Circle(Bikaner) on:20/07/2017  
Query raised by Nodal Officer (Rajasthan) on:03/08/2017  
Replied by Circle(Bikaner) on:09/08/2017  
Query raised by Circle (Bikaner) on:16/03/2017  
Replied by DFO (Chhatargarh Territorial) on:08/04/2017  
Query raised by Circle (Bikaner) on:10/04/2017  
Replied by DFO (Chhatargarh Territorial) on:10/04/2017  
Query raised by Circle (Bikaner) on:12/06/2017  
Replied by DFO (Chhatargarh Territorial) on:21/06/2017  
Query raised by Circle (Bikaner) on:19/07/2017  
Replied by DFO (Chhatargarh Territorial) on:20/07/2017  
Query raised by Circle (Bikaner) on:04/08/2017  
Replied by DFO (Chhatargarh Territorial) on:08/08/2017  
Query raised by DFO (Chhatargarh Territorial) on:08/02/2017  
Replied by UA on :13/02/2017  
Query raised by DFO (Chhatargarh Territorial) on:27/03/2017  
Replied by UA on :04/04/2017  
Query raised by DFO (Chhatargarh Territorial) on:10/04/2017  
Replied by UA on :10/04/2017  
Query raised by DFO (Chhatargarh Territorial) on:12/06/2017  
Replied by UA on :17/06/2017  
Query raised by DFO (Chhatargarh Territorial) on:19/07/2017  
Replied by UA on :19/07/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...