  (i). Proposal No. : FP/RJ/TRANS/19489/2016   (ii). Name of Project for which Forest Land is required : 132 KV S/C Nokha Daiya- Khajuwala Tr LINE   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Transmission Line between Nokha Daiya and Khajuwala is rquird to strengthn the system reliability of Transmission network in West Rajathan.   (iv). State : Rajasthan   (v). Category of the Project : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 35.4291
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/RJ/TRANS/19489/201619/05/201601/09/2016  27/05/2016   06/10/2016  27/08/2016   25/10/2016   03/01/2017 DCF STII BIKANER :03/01/2017
Chhatargarh Territorial :03/01/2017
Bikaner:
  03/02/2017 (Chhatargarh Territorial)

Bikaner:
  03/02/2017 (DCF STII BIKANER)

Rajasthan:
13/02/2017
Rajasthan:
02/05/2017
28/08/2017
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:27/06/2017  
Replied by State Government(Rajasthan) on:19/07/2017  
Replied by State Government(Rajasthan) on:14/08/2017  
Query raised by Regional Office (Lucknow) on:31/07/2017  
Replied by State Government(Rajasthan) on:14/08/2017  
Query raised by State Government (Rajasthan) on:10/05/2017  
Replied by Nodal Officer (Rajasthan) on:16/05/2017  
Query raised by State Government (Rajasthan) on:27/06/2017  
Replied by Nodal Officer (Rajasthan) on:18/07/2017  
Query raised by State Government (Rajasthan) on:31/07/2017  
Replied by Nodal Officer (Rajasthan) on:11/08/2017  
Query raised by Nodal Officer (Rajasthan) on:02/03/2017  
Replied by Circle(Bikaner) on:11/04/2017  
Query raised by Nodal Officer (Rajasthan) on:11/05/2017  
Replied by Circle(Bikaner) on:11/04/2017  
Query raised by Nodal Officer (Rajasthan) on:28/06/2017  
Replied by Circle(Bikaner) on:12/05/2017  
Query raised by Nodal Officer (Rajasthan) on:31/07/2017  
Replied by Circle(Bikaner) on:17/07/2017  
Query raised by Circle (Bikaner) on:03/03/2017  
Replied by DFO (DCF STII BIKANER) on:08/04/2017  
Query raised by Circle (Bikaner) on:03/03/2017  
Replied by DFO (Chhatargarh Territorial) on:08/04/2017  
Query raised by Circle (Bikaner) on:10/04/2017  
Replied by DFO (DCF STII BIKANER) on:10/04/2017  
Query raised by Circle (Bikaner) on:10/04/2017  
Replied by DFO (Chhatargarh Territorial) on:11/04/2017  
Query raised by Circle (Bikaner) on:12/05/2017  
Replied by DFO (DCF STII BIKANER) on:12/05/2017  
Query raised by Circle (Bikaner) on:12/05/2017  
Replied by DFO (Chhatargarh Territorial) on:12/05/2017  
Query raised by Circle (Bikaner) on:28/06/2017  
Replied by DFO (DCF STII BIKANER) on:04/07/2017  
Query raised by Circle (Bikaner) on:28/06/2017  
Replied by DFO (Chhatargarh Territorial) on:06/07/2017  
Query raised by Circle (Bikaner) on:06/07/2017  
Replied by DFO (DCF STII BIKANER) on:11/07/2017  
Query raised by Circle (Bikaner) on:06/07/2017  
Replied by DFO (Chhatargarh Territorial) on:11/07/2017  
Query raised by Circle (Bikaner) on:11/07/2017  
Replied by DFO (Chhatargarh Territorial) on:14/07/2017  
Query raised by Circle (Bikaner) on:11/07/2017  
Replied by DFO (DCF STII BIKANER) on:14/07/2017  
Query raised by Circle (Bikaner) on:01/08/2017  
Replied by DFO (Chhatargarh Territorial) on:08/08/2017  
Query raised by Circle (Bikaner) on:01/08/2017  
Replied by DFO (DCF STII BIKANER) on:08/08/2017  
Query raised by DFO (Chhatargarh Territorial) on:27/03/2017  
Replied by UA on :29/03/2017  
Query raised by DFO (Chhatargarh Territorial) on:10/04/2017  
Replied by UA on :10/04/2017  
Query raised by DFO (DCF STII BIKANER) on:12/05/2017  
Replied by UA on :12/05/2017  
Query raised by DFO (Chhatargarh Territorial) on:28/06/2017  
Replied by UA on :04/07/2017  
Query raised by DFO (DCF STII BIKANER) on:29/06/2017  
Replied by UA on :04/07/2017  
Query raised by DFO (Chhatargarh Territorial) on:07/07/2017  
Replied by UA on :10/07/2017  