  (i). Proposal No. : FP/RJ/TRANS/149363/2021              (ii). Name of Project for which Forest Land is required : SHIFTING /MODIFICATION OF 132 KV D/C LILO LINE FOR 132 KV GSS SISARAMA (220 KV AMBERI & 132 KV GOGUNDA DOUBLE CIRCUIT ) 339 MT.LENTH              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : SHIFTING /MODIFICATION OF 132 KV D/C LILO LINE FOR 132 KV GSS SISARAMA (220 KV AMBERI & 132 KV GOGUNDA DOUBLE CIRCUIT) 339 MT.LENTH              (iv). State : Rajasthan              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.9153
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/TRANS/149363/202116/12/202105/05/2022  24/03/2022  10/02/2022  11/01/2022   07/05/2022  19/04/2022  04/03/2022  13/01/2022   13/05/2022   26/05/2022 Udaipur (South) Territorial :26/05/2022Udaipur:
  24/11/2022 (Udaipur (South) Territorial)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Udaipur) on:28/11/2022  
Replied by DFO (Udaipur (South) Territorial) on:28/11/2022  
Query raised by Circle (Udaipur) on:28/11/2022  
Replied by DFO (Udaipur (South) Territorial) on:28/11/2022  
Query raised by Circle (Udaipur) on:08/12/2022  
Replied by DFO () on:  
Query raised by DFO (Udaipur (South) Territorial) on:17/06/2022  
Replied by UA on :09/08/2022  
Query raised by DFO (Udaipur (South) Territorial) on:22/08/2022  
Replied by UA on :18/10/2022  
Query raised by DFO (Udaipur (South) Territorial) on:19/12/2022  
Replied by UA on :31/07/2023  
Query raised by DFO (Udaipur (South) Territorial) on:22/08/2023  
Replied by UA on :27/09/2023  
Query raised by DFO (Udaipur (South) Territorial) on:07/11/2023  
Replied by UA on :  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .