TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/SubStation/42955/2019              (ii). Name of Project for which Forest Land is required : Construction of 765 /400 kV Sub Station at Village-Jasrapur, Tehsil- Khetri, District–Jhunjhunu UnderTransmission System Associated with LTA Applications for Rajasthan Solar Energy Zone, Part -C              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 765 /400 kV Sub Station at Village- Jasrapur, Tehsil- Khetri, District–Jhunjhunu under Transmission System Associated with LTA Applications for Rajasthan Solar Energy Zone, Part -C which inter-alia includes 765 kV D/C Khetri-Jhatikra (Delhi) Hexa Zebra Transmission Line, 400 kv D/C K              (iv). File no. : 8B/Raj/04/4/2020/FC              (v). State : Rajasthan              (vi). Category of the Project : Sub Station              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 35.1938
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/RJ/SubStation/42955/201922/11/201927/11/2019   30/11/2019   05/12/2019   05/12/2019 Jhunjhunu Territorial :05/12/2019Jaipur:
  24/12/2019 (Jhunjhunu Territorial)

Rajasthan:
01/01/2020
Rajasthan:
07/01/2020
Jaipur:
20/01/2020
20/02/2020
By :Regional Office
Rajasthan
29/04/2020
12/05/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Jaipur) on:30/01/2020  
Replied by State Government(Rajasthan) on:10/02/2020  
Query raised by State Government (Rajasthan) on:31/01/2020  
Replied by Nodal Officer (Rajasthan) on:10/02/2020  
Query raised by Nodal Officer (Rajasthan) on:31/01/2020  
Replied by Circle(Jaipur) on:06/02/2020  
Query raised by Circle (Jaipur) on:31/12/2019  
Replied by DFO (Jhunjhunu Territorial) on:01/01/2020  
Query raised by Circle (Jaipur) on:04/02/2020  
Replied by DFO (Jhunjhunu Territorial) on:05/02/2020  
Query raised by DFO (Jhunjhunu Territorial) on:16/12/2019  
Replied by UA on :16/12/2019  
Query raised by DFO (Jhunjhunu Territorial) on:18/12/2019  
Replied by UA on :20/12/2019  
Query raised by DFO (Jhunjhunu Territorial) on:04/02/2020  
Replied by UA on :05/02/2020  
NOTE:- Stage-II Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...