TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/ROAD/38474/2019   (ii). Name of Project for which Forest Land is required : Construction of Approach Road for Proposed Hindustan petroleum Retail Outlet on Ganganagar -Bikaner NH-15(R.H.SIDE) ,Between Chainage ms stone 89/760 to 89/841.40,Lunkaransar-Malkisar at Village- Chak -2 BHM, Tehsil-Lunkaransar, District Bikaner   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Approach Road forProposed Hindustan petroleum Retail Outlet,on Ganganagar -Bikaner NH-15(R.H.S.) ,Between Chainage from ms stone 89/760 to 89/841.40,Lunkaransar-Malkisar at Village- Chak -2 BHM, Tehsil-Lunkaransar, District Bikaner   (iv). State : Rajasthan   (v). Category of the Project : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 0.1276
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/ROAD/38474/201929/01/201923/07/2019  18/02/2019   22/08/2019  18/06/2019   09/10/2019  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending with User Agency for submitting hard copy of proposal .
Close(X)