  (i). Proposal No. : FP/RJ/ROAD/34417/2018              (ii). Name of Project for which Forest Land is required : Construction of road from Dikwani to gadar ishartori              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of road from Dikwani to gadar ishartori in rural road scheme total road length 6.65 km and road under forest 6.21 km              (iv). State : Rajasthan              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 6.21
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/ROAD/34417/201830/08/201920/03/2020  09/10/2019   17/08/2020  26/02/2020   19/08/2020   19/09/2020 Baran Territorial :21/09/2020
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Baran Territorial) on:04/11/2020  
Replied by UA on :09/02/2021  
Query raised by DFO (Baran Territorial) on:12/02/2021  
Replied by UA on :18/09/2022  
Query raised by DFO (Baran Territorial) on:28/09/2022  
Replied by UA on :10/11/2022  
Query raised by DFO (Baran Territorial) on:17/11/2022  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .