TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/ROAD/16317/2015   (ii). Name of Project for which Forest Land is required : CONSTRUCTION OF B.T. ROAD FROM MANDAS TO KALAT PHALA KM.0/0-5/100 .   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : CONSTRUCTION OF B.T. ROAD FROM MANDAS TO KALAT PHALA KM.0/0-5/100. THE PROPOSED ROAD GO TO MANDAS AND TEHSIL HQ SARADA FOR THEIR PERSONAL MARKETING NEEDS.EDUCATIONAL,MEDICAL,RECREATIONAL AND OTHER TYPE OF WORK.AT PRESENT THERE IS NO DIRECT ALTERNATE ROUTE.   (iv). State : Rajasthan   (v). Category of the Project : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Area of forest land proposed for diversion(in ha.): 1.5
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/ROAD/16317/201503/08/201719/05/2019  19/03/2019  05/08/2018  16/04/2018  31/01/2018  20/11/2017  12/09/2017   09/08/2019  12/04/2019  05/03/2019  02/07/2018  09/04/2018  31/12/2017  29/10/2017   23/09/2019   04/11/2019 Udaipur (South) Territorial :08/11/2019Udaipur:
  06/12/2019 (Udaipur (South) Territorial)

C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Udaipur) on:06/12/2019  
Replied by DFO (Udaipur (South) Territorial) on:09/12/2019  
NOTE:- Proposal is pending at CF .