TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/TRANS/153857/2022              (ii). Name of Project for which Forest Land is required : 66 KV line from 66 KV G/S/S Lohakhera to 66 KV G/S/S Longowal SC ON DC Tower line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For construction of 66 KV Transmission line from 66 KV G/S/S Lohakhera to 66 KV G/S/S Longowal SC ON DC Tower line.              (iv). File no. : 9-HRB001-2024-CHA              (v). State : Punjab              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0504
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/PB/TRANS/153857/202226/03/202212/04/2022  31/03/2022   13/04/2022  11/04/2022   20/04/2022   30/04/2022 Sangrur :02/05/2022South Circle:
  20/01/2023 (Sangrur)

Punjab:
24/01/2023
Punjab:
28/11/2023
Chandigarh:
27/12/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:31/01/2024  
Query raised by State Government (Punjab) on:01/02/2024  
Query raised by Nodal Officer (Punjab) on:31/01/2023  
Replied by Circle(South Circle) on:17/07/2023  
Query raised by Nodal Officer (Punjab) on:27/07/2023  
Replied by Circle(South Circle) on:20/10/2023  
Query raised by Nodal Officer (Punjab) on:01/02/2024  
Replied by Circle() on:  
Query raised by Circle (South Circle) on:20/01/2023  
Replied by DFO (Sangrur) on:23/01/2023  
Query raised by Circle (South Circle) on:31/01/2023  
Replied by DFO (Sangrur) on:14/07/2023  
Query raised by Circle (South Circle) on:27/07/2023  
Replied by DFO (Sangrur) on:20/10/2023  
Query raised by Circle (South Circle) on:01/02/2024  
Replied by DFO () on:  
Query raised by DFO (Sangrur) on:13/05/2022  
Replied by UA on :02/08/2022  
Query raised by DFO (Sangrur) on:12/08/2022  
Replied by UA on :12/09/2022  
Query raised by DFO (Sangrur) on:16/09/2022  
Replied by UA on :29/09/2022  
Query raised by DFO (Sangrur) on:16/02/2023  
Replied by UA on :04/05/2023  
Query raised by DFO (Sangrur) on:11/05/2023  
Replied by UA on :15/05/2023  
Query raised by DFO (Sangrur) on:05/03/2024  
Replied by UA on :  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .