TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/OFC/51686/2020              (ii). Name of Project for which Forest Land is required : Laying OFC from Sangrur to Dhanula via Longowal              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of forest land for Laying the Optical Fiber Cable from Sangrur Bypass (Barnala Side) to Badrukha Via Duggan Via Bhama Badi and Duggan to Longowal via SLIET College and upto Lohakehra to Dhanaula Length=19008mtr. LHS Total Area 0.86016ha.              (iv). State : Punjab              (v). Category of the Project : Optical Fibre Cable              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.86016
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/PB/OFC/51686/202029/10/202020/11/2020  30/10/2020   04/12/2020  19/11/2020   07/12/2020   11/01/2021 Sangrur :12/01/2021South Circle:
  23/08/2022 (Sangrur)

Punjab:
15/11/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Punjab) on:21/11/2022  
Query raised by Circle (South Circle) on:23/08/2022  
Replied by DFO (Sangrur) on:31/08/2022  
Query raised by Circle (South Circle) on:02/09/2022  
Replied by DFO (Sangrur) on:31/10/2022  
Query raised by Circle (South Circle) on:31/10/2022  
Replied by DFO (Sangrur) on:31/10/2022  
Query raised by Circle (South Circle) on:04/11/2022  
Replied by DFO (Sangrur) on:07/11/2022  
Query raised by Circle (South Circle) on:23/11/2022  
Replied by DFO () on:  
Query raised by DFO (Sangrur) on:02/02/2021  
Replied by UA on :04/01/2022  
Query raised by DFO (Sangrur) on:05/01/2022  
Replied by UA on :20/01/2022  
Query raised by DFO (Sangrur) on:15/03/2022  
Replied by UA on :31/05/2022  
Query raised by DFO (Sangrur) on:08/06/2022  
Replied by UA on :03/08/2022  
Query raised by DFO (Sangrur) on:05/09/2022  
Replied by UA on :26/09/2022  
Query raised by DFO (Sangrur) on:02/12/2022  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by Nodal Officer .
Close(X)
Close(X)
Please wait ...